Children and Young People's Services and Advisory Panel noted this item on Thursday 4 September 2008. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised: (i) That the capital programme forecast outturn for 2008/09, as shown in Annex A of the report , be noted; (ii) That the additions and amendments to the capital programme outlined in the report and summarised in Annex A be approved; (iii) That the scheme reprofiling and slippage outlined in the report and summarised in Annex A be approved; (iv) That the revised capital programme, as shown in Annex A of the report, be agreed, subject to the approval of the Executive. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Summary
1 This report is to:
• inform Members of the likely out-turn position of the 2008/09 Capital Programme.
• advise Members of changes to existing schemes and reprofiling of expenditure to allow the more effective management and monitoring of the Capital Programme
• inform Members of any slippage in budgets between financial years
• inform Members of any new schemes and seek approval for their addition to the 2008/11 Capital Programme.
Background
2 The original capital programme for the financial year 2008/09 was approved at Council on 21 February 2008. Since then, a number of amendments to the programme have been approved as part of the 2007/08 out-turn report. This results in a current approved Children’s Services capital programme for 2008/09 which shows gross capital expenditure of £33.347m with £27.112m of other funding which gives a net capital programme cost to the authority of £6.235m.
3 The table below details the approved changes to the 2008/09 capital programme since the original programme was approved in February 2008.
Table 1- Current Approved Children’s Services Capital Programme 2008/09
Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2008/09 45.103 39.300 5.803 Slippage and Adjustments from the 2007/08 (11.756) (12.188) 0.432 Outturn report Current Approved Capital Programme 2008/09 33.347 27.112 6.235 Consultation
4 Not applicable.
Options and Analysis Scheme Progress Reports and Updates
Devolved Capital 5 This scheme represents the devolved capital which has been allocated to schools in 2008/09, net of any contributions which the schools have agreed towards LA led schemes.
Fulford Secondary Targeted Capital (Scheme Cost £3.489m) 6 This scheme is now complete with only the retention payment on Phase 1 outstanding. This is still being finalised but is expected to be within the remaining budget.
Huntington Secondary (Scheme Cost £5.674m) 7 The major scheme for the provision of new Teaching and Performing Arts blocks is complete with the new facilities in full use. The final retention has not yet been settled, but is expected to be within the remaining budget.
Integrated Children’s Centres (Overall Scheme Cost (£4.871m) 8 The schemes at the five new Children’s Centres are now all complete or nearing completion.
st 9 The scheme at Carr is now complete and was handed over on 31 July 2008.
10 Haxby Road Children’s Centre is progressing, with completion still expected in the autumn.
11 The Children’s Centre at New Earswick is now complete. A key component of this scheme was the provision of a new school library and anecdotal evidence so far suggests that usage has increased significantly since the new facility was opened.
12 St Lawrence’s is also complete. An official opening has been set for 26th September 2008.
13 As previously reported, Tang Hall Children’s Centre became operational in mid- February with only some minor outstanding issues. The majority of these issues have now been rectified with only a small number of snagging issues to complete.
14 The outturn report for 2007/08 presented to EMAP on 10th June reported on the allocation of a further £1.196m of funding over the period 2008/11 to further develop the network of Children’s Centres across the city. A separate paper on this agenda seeks approval for revising the reach areas of the eight existing children’s centres and establishing a ninth centre. NDS Modernisation (Scheme Cost £17.053m) 15 This scheme addresses condition and suitability issues at a number of schools in the city. In order to maximise the resources available schools have been invited to bid for this funding and encouraged to contribute their devolved capital to projects.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.