Advice of the Advisory Panel That the Executive Member be advised: (i) That the capital programme forecast outturn for 2008/09, as shown in Annex A of the report, be noted; (ii) That the additions and amendments to the capital programme, as set out in the report and summarised in Annex A, be approved; (iii) That the scheme reprofiling and slippage, as set out in the report and summarised in Annex A, be approved; (iv) That the revised capital programme, as shown at Annex A of the report, be agreed, subject to the approval of the Executive. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Summary
1 This report is to: • inform Members of the likely out-turn position of the 2008/09 Capital Programme. • advise Members of changes to existing schemes and reprofiling of expenditure to allow the more effective management and monitoring of the Capital Programme • inform Members of any slippage in budgets between financial years • inform Members of any new schemes and seek approval for their addition to the 2008/11 Capital Programme.
Background
2 The original capital programme for the financial year 2008/09 was approved at Council on 21 February 2008. Since then, a number of amendments to the programme have been approved as part of the 2007/08 out-turn report and the Monitor 1 report. This results in a current approved Children’s Services capital programme for 2008/09 which shows gross capital expenditure of £33.217m with £26.982m of other funding which gives a net capital programme cost to the authority of £6.235m to be funded from capital receipts.
3 The table below details the approved changes to the 2008/09 capital programme since the original programme was approved in February 2008.
Table 1- Current Approved Children’s Services Capital Programme 2008/09
Gross External Section Prudential Capital Spend Funding 106 Borrowing Receipts £m £m £m £m £m Original Capital Programme 45.103 37.322 0.337 1.641 5.803 2008/09 Slippage and Adjustments from (11.756) (12.016) 0.228 (0.400) 0.432 the 2007/08 Outturn report Monitor 1 Slippage and (0.130) (0.130) - - - Adjustments
Current Approved Capital 33.217 25.176 0.565 1.241 6.235 Programme 2008/09 Consultation
4 The capital programme has been developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 21 February 2008. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local councillors and residents in the locality of the individual schemes.
Scheme Specific Updates
Devolved Formula Capital (Scheme Cost £18.385m) 5 This scheme represents the devolved capital which has been allocated to schools in 2008/09, net of any contributions which the schools have agreed towards LA led schemes elsewhere in the programme. The amendments detailed on the annex are the result of removing the VA schools devolved capital amounts from the programme as the funding does not come via the local authority, together with the updating of the programme for amounts agreed by schools towards other schemes in the programme which are in progress during 2008/09 which have not previously been reflected.
Fulford Secondary Targeted Capital (Scheme Cost £3.489m) 6 The final payment on Phase 1 of this scheme has now been settled. However the actual final payment is £26k above the remaining budget. This amount will be funded by a virement from the unallocated contingency held within NDS Modernisation.
Huntington Secondary (Scheme Cost £5.674m) 7 The major scheme for the provision of new Teaching and Performing Arts blocks is complete with the new facilities in full use. The final retention has not yet been settled, but is expected to be within the remaining budget.
Integrated Children’s Centres (Overall Scheme Cost (£4.871m) 8 Four of the five new Children’s Centres are now complete. Only Haxby Road CC is still in progress and this is due to be completed shortly. Due to delays in the completion of some of the children’s centres some of the retention payments will now not be made until 2009/10 therefore a small amount of the individual budgets require slipping from 2008/09.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.