Report of the Director of Customer & Business Support Services
CAPITAL PROGRAMME – MONITOR THREE
Report Summary 1. The purpose of this report is to:
• Inform Members of the likely outturn position of 2010/11 Capital Programme based on the spend profile and information to mid January 2011;
• Inform the Executive of any under or overspends and seek approval for any resulting changes to the programme;
• Inform the Executive of any slippage and seek approval for the associated funding to be slipped to or from the financial years to reflect this;
• To inform Members of the funding position of the capital programme, taking account of the current capital receipts forecasts for the capital programme.
2. The 2010/11 – 2014/15 capital programme was approved by Council on 25th February 2010. Since then a number of amendments have taken place as reported to the Executive in the 2009/10 Capital Programme Monitor 3 report, the 2009/10 Capital Programme Outturn report and the 2010/11 Capital Programme Monitor 1 and 2 report. The changes made as result of the above papers have resulted in a current approved capital programme for 2010/11 of £73.306m, financed by £37.818m of external funding, and internal funding of £35.488m. Table 1 illustrates the movements from the start budget to the current approved position at monitor 2. Gross External Internal Budget Funding Funding £m £m £m Original Budget Approved by Council at 73.298 38.880 34.418 25 Feb 2010 Amendments from 2009/10 Monitor 3 5.324 3.390 1.934 report Amendments from 2009/10 Outturn 3.357 1.372 1.985 report Amendments from 2010/11 Monitor 1 (0.447) 0.114 (0.561) report Amendments from 2010/11 Monitor 1 (8.226) (5.938) (2.288) report Current Approved Capital 73.306 37.818 35.488 Programme Table 1 Current Approved Capital Programme
Consultation 3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 25 February 2010. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues 4. The information contained within this report reflects all the latest known information following the Budget Settlement in relation to the Councils capital programme. As further information becomes available Members will be updated to ensure they are kept abreast of the latest changes and the resultant impact on the programme.
5. A decrease of £8.38m is detailed in this monitor that results in a revised capital programme budget of £64.926m; £6.446m higher than the 2009/10 capital outturn of £58.480m.
6. Against the current approved budget post 2010/11 Monitor 1 of £73.306m, there is a predicted outturn of £64.926m, a net decrease of £8.38m made up of: • Adjustments to schemes decreasing budgeted expenditure by £523k. • Reprofiling of £7.857m of schemes into future years
Table 2 outlines the variances reported against each portfolio area. Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m ACE Children’s 26.797 24.645 (2.152) Services ACE Adult Social 0.941 0.876 (0.065) Services CANS Leisure and 4.388 2.971 (1.417) Culture CANS Neighbourhood 8.879 6.957 (1.922) Services CANS Housing 10.517 9.492 (1.025)
City Strategy City Strategy 5.986 5.926 (0.060) (P&T) City Strategy City Strategy 11.251 10.651 (0.600) (Admin Accom) City Strategy City Strategy 0.035 0.035 0.000 (Economic Development) City Strategy Property 2.063 1.264 (0.799) Services CBSS Resources 1.894 1.594 (0.300)
CBSS Miscellaneous 0.555 0.515 (0.040) (Contingency etc) Total 73.306 64.926 (8.38)
Table 2 Capital Programme Forecast Outturn 2010/11
7. To the mid point in January there was £39.132m of capital spend representing 53% of the monitor 3 budget.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Monitor 3Appendix A | 117 KB | Download |
PDF |
Capital Programme: Monitor 3Report | 174 KB | DownloadRead as text |
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Apr 2011 | MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... | Approved | Open |
| 26 Apr 2011 | Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... | Agreed | Open |
| 26 Apr 2011 | Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... | Noted | Open |
| 12 Apr 2011 | MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... | Approved | Open |
| 12 Apr 2011 | Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.