Capital Programme Budget 2011/12 to 2015/16

Agreed Executive 2 papers

Executive - for meetings from 03/06/00 to 26/04/11 agreed this item on Tuesday 15 February 2011. Below is the council's own wording, with the papers it was decided on.

Item166

Resolved

RECOMMENDED:That Council: (i)Agree to the revised capital programme of £175.318m, that reflects a net overall increase of £18.891m (as set out in the ‘growth’ column of Annex A with the amendments totalling £2.616m set out in (d) and (e) below ). Key elements of this include : a)the bids recommended in paragraph 114 (table 5) totalling £7.205m, subject to the following amendment : · the timing of Yearsley Pool energy solution moved to 2012/13 from 2011/12 to permit thorough investigation of necessity and appropriate technology; b) the schemes funded from external resources in paragraph 122 (table 8) totalling £3.629m ; c) the revised prudential borrowing profile for the IT development plan in paragraph 126 (table 9) totalling £3.750m that shows a decrease of £250k per annum in years 11/12 - 14/15 and an extension of the programme by £750k in 2015/16 containing specific schemes; d) the use of HRA balances to fund HRA capital schemes as set out in paragraph 130 (table 10) totalling £5.691m subject to the following amendment: · the inclusion of £700k (including work at The Glebe) towards a building insulation programme, including the fitting of double glazed windows, to commence in 2011/12 to bring the increase in the HRA capital programme to £6.391m; e) the inclusion of the following new/amended schemes totalling £1.916m with a revenue implication of £29k in 2011/12: · £1.000m in 2012/13 to be utilised in conjunction with the Environment Agency for the provision of the Leeman Road flood defences · an additional £50k p.a.(to the £80k p. a. already included in the LTP line) allocation for the street lamppost replacement programme from 2011/12 to 2015/16, totalling £250k · £100k p.a. from 2011/12 to 2015/16 to fund an energy generation project which will exploit modern technologies such as photovoltaic cells and which is aimed at providing an additional revenue stream, through the sale of energy, by utilising the availability of new “feed in” tariffs, totalling £500k · an additional capital investment in structural highways of £166k for 2011/12. (ii)Note that the revenue implications of the above amendments in 2011/12 are £29k, to be reflected in the revenue budget proposals. (iii)Note the overall funding position identified in the report, which highlights a current shortfall in resources over the next five years, which the Council will need to address through increased revenue contributions in the medium term . (iv)Approve the full restated programme as summarised in Annex A totalling £175.318m (£172.702m plus £2.616m amendments) up to 2015/16. REASON: To set a balanced capital programme as required by the Local Government Act 2003.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Background

3. The current 2010/11 – 2014/15 capital programme was approved by Council on 25th February 2010. Since then a number of amendments have taken place as reported to the Executive in the 2009/10 Capital Programme Monitor 3 report, the 2009/10 Capital Programme Outturn report and the 2010/11 Capital Programme Monitor 1, 2 and 3 reports. The changes made as result of the above reports have resulted in a current approved capital programme for 2010/11 – 2014/15 of £221.229m, financed by £121.209m of external funding, and Council controlled resources of £100.020m. Table 1 illustrates the current approved capital programme profile from 2010/11 – 2014/15 as at monitor 3. 2010/11 2011/12 2012/13 2013/14 2014/15 Total £m £m £m £m £m £m Gross Capital 64.802 55.875 50.084 30.161 20.307 221.229 Programme Funded by: External Funding 35.020 20.302 27.458 22.373 16.056 121.209

Council Controlled 29.782 35.573 22.626 7.788 4.251 100.020 Resources Total Funding 64.802 55.875 50.084 30.161 20.307 221.229

Table 1 – Capital Programme Funding and Receipts Position

4. The make up of the current approved 2010/11 – 2014/15 capital programme can be easily summarised in to 3 key elements. • Fully Funded (by Government Departments) - £104.472m • Political Imperatives - £86.797m • Rolling Programmes - £29.988m

5. The fully funded schemes make up the majority of the capital programme and include the: • Local Transport Plan (£9.971m), • Department for Children, Schools and Families (DCSF) (£50.552m) • Housing Revenue Account Business Plan (£37.503m) • Housing General Fund (£918k) • Various (£3.352m)

6. The political imperative schemes are made up of 5 major projects and account for £86.797m, the majority of which are funded from corporate resources. These schemes, some of which have already started are summarised below highlighting the budgeted spend between 2010/11 and 2014/15: • York Pools – £3.404m • Admin Accom - £38.488m • Community Stadium - £4.0m • West of York Salvage and Recycling Centre - £2.5m • Acomb Office - £1.750m

7. There are currently a number of rolling programme schemes totalling £29.988m over the current 5 year programme. These include: • Highways Resurfacing and Reconstruction £17.044m • Disabled Facilities Grant and Disabled Support Budget £5.007m • Special Bridge Maintenance £0.972m • City Walls £542k Funding Position of approved 2010/11 – 2014/15 programme

8. The current economic environment continues to place pressure on the funding of the programme over the 5 year cycle based on current projections. The capital programme continues to place significant reliance on the achievement of a small number of high value asset disposals which have been affected by the economic downturn.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme BudgetAppendix A 106 KB Download
PDF
Capital Programme Budget 2011/12 to 2015/16Report 273 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
JA
Councillor James AlexanderAttendee, in attendance
AW
Councillor Andrew WallerChair, present
NA
Councillor Nigel AyreCommittee Member, present
SG
Councillor Steve GallowayCommittee Member, present
RM
Councillor Richard MooreCommittee Member, present
JM
Councillor Jonathan MorleyCommittee Member, present
AR
Councillor Ann ReidCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
BW
Bill WoolleyOfficer, expected

On this subject at York

Search all
  1. Capital Programme Budget 2011/12 to 2015/16This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies