Capital Programme Budget 2013/14 to 2017/18

Agreed Executive 2 papers

Executive agreed this item on Tuesday 12 February 2013. Below is the council's own wording, with the papers it was decided on.

Item100

Resolved

RECOMMENDED: That Council: i ) Agree to the revised capital programme of £176.709m, that reflects a net overall increase of £48.381m as set out in paragraph 30 table 10 and in Annex A ‘budget amendments’ column). Key elements of this include: o Extension of prudential borrowing funded Rolling Programme schemes totalling £3.365m including the IT development fund as set out in paragraph 10 table 2 and summarised in paragraph 27 table 9; o Creation of 2 new prudential borrowing funded Rolling Programme schemes totalling £1.500m as set out in paragraph 14 table 3 and summarised in paragraph 27 table 9 o New schemes totalling £3.585m including an increase in prudential borrowing of £3.185m as set out in paragraph 16 table 4 and summarised in paragraph 27 table 9; o New externally funded schemes totalling £25.974m as set out in paragraph 18 table 5 and summarised in paragraph 26 table 9 o An increase in HRA funded schemes totalling £13.957m funded from HRA balances of £13.957m as set out in paragraph 19 table 6 and summarised in paragraph 27 table 9. ii) Approve the full restated programme as summarised in Annex A totalling £176.709m cover financial years 2013/14 to 2017/18 as set out in paragraph 30 table 10. REASON: To set a balanced capital programme as required by the Local Government Act 2003.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Background

3. The current 2012/13 –2016/17 capital programme was approved by Council on 23rd February 2012. Since then a number of amendments have taken place as reported to the Cabinet up to and including the 2012/13 Capital Monitor 3 report. The changes made as a result of the above reports have resulted in a current approved capital programme for 2012/13 – 2016/17 of £185.422m, financed by £98.564m of external funding and Council controlled resources of £86.858m. Table 1 illustrates the current approved capital programme profile from 2012/13 – 2016/17 as at capital monitor 3 2012/13.

2012/13 2013/14 2014/15 2015/16 2016/17 Total

£m £m £m £m £m £m Gross Capital Programme 57.094 58.207 30.868 19.792 19.461 185.422 Funded by: External Funding 21.227 36.347 19.131 10.140 11.719 98.564 Council Controlled 35.867 21.860 11.737 9.652 7.742 86.858 Resources Total Funding 57.094 58.207 30.868 19.792 19.461 185.422

Table 1 – Capital Programme Funding and Receipts Position

Funding Position of approved 2012/13 – 2016/17 programme

4. The current economic environment continues to place pressure on the funding of the programme over the 5 year cycle based on current projections. The capital programme continues to place reliance on the achievement of a small number of high value asset disposals which have been affected by the economic downturn.

Options

5. This report sets out the capital investment requests for the 5 year period covering 2013/15 to 2017/18. Members can consider the requests to make additions and amendments to the existing capital programme and choose to approve or reject the proposals contained within the report. Members can choose to approve or reject the recommendations made to Council as a result of the amendments contained in this report. It should be noted that it is a statutory requirement for the Council to set a capital budget for the forthcoming year (2013/14) per Local Government Act 2003 (revised). Summary of Proposed Investment

6. The CRAM process invited bids from the departments asking to submit requests for the Councils main capital priorities. Of the requests going forward 18 are asking for direct Council funding, this is comprised of 8 requests for extensions to existing rolling programme schemes, 2 requests for funding to create new rolling programme schemes and 8 requests for new schemes.

7. In total, requests that would increase the existing 13/14 – 17/18 Capital Programme by £48.381m have been made. The £48.381m is comprised as follows: • General Fund schemes requiring financing through Council borrowing £8.450m (£8.050m prudential borrowing of which £2.335m are proposed on a self financing basis, this will result in £5.715m requiring additional borrowing that will impact the revenue budget, the remaining £400k is for a specific match funding scheme) • General Fund Schemes financed entirely by external funds £25.974m (£25.074m Government grant, £900k Developers contributions) • Housing Revenue Account schemes financed by HRA funds £13.957m (£13.957 HRA funds)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 1314 1718Appendix A 56 KB Download
PDF
Capital Programme Budget 2013/14 to 2017/18Report 170 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
DL
Councillor David LeveneCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
AD
Councillor Andy D'AgorneAttendee, in attendance
MW
Councillor Mark WartersAttendee, in attendance
AR
Councillor Ann ReidAttendee, in attendance
PH
Councillor Paul HealeyAttendee, in attendance

All 17 on the meeting page

On this subject at York

Search all
  1. Capital Programme Budget 2013/14 to 2017/18This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open