That Cabinet agree to: · Note the 2012/13 revised budget of £57.281m as set out in paragraph 6 and Table 2. · Note the restated capital programme for 2012/13 – 2016/17 as set out in paragraph 43, Table 4 and detailed in Annex A. · Note the re-profiling and adjustments of the Economic Infrastructure fund to align to spend and approval as set out in the Economic Infrastructure reports to Cabinet noting the overall fund remaining at £28.5m and Annex B showing current EIF position. REASON: To enable the effective management and monitoring of the Council’s capital programme. That Cabinet agree to: · Note the 2012/13 revised budget of £57.281m as set out in paragraph 6 and Table 2. · Note the restated capital programme for 2012/13 – 2016/17 as set out in paragraph 43, Table 4 and detailed in Annex A. · Note the re-profiling and adjustments of the Economic Infrastructure fund to align to spend and approval as set out in the Economic Infrastructure reports to Cabinet noting the overall fund remaining at £28.5m and Annex B showing current EIF position. 1. REASON: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 23 February 2012. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
4. A decrease of £11.752m is detailed in this monitor that results in a revised capital programme budget from £69.033m to £57.281m.
5. The decrease of £11.752m is made up of: • Under spends of £1.126m (see paragraph 45 for details). • Net re-profiling of £10.626m of schemes from the current year to future years.
6. Table 2 outlines the variances reported against each portfolio area. It should be noted that the portfolios have been aligned with the new Council Structure from 1st April 2012. Directorate Department Current Revised Variance Approved Capital Budget Budget £m £m £m ACE Children’s, 10.262 5.844 (4.418) Education and Skills ACE Adult Social 1.307 0.906 (0.401) Services CES Strategic 9.107 7.816 (1.291) Planning &Transport CES Community 2.864 0.635 (2.229) Stadium CES Economic 0.058 0.058 0.000 Development CANS Housing & 11.814 10.550 (1.264) Comm Safety CANS Culture, Leisure 2.148 2.060 (0.088) & Public Realm CES Highways, Fleet 7.476 7.476 0.000 & Waste CBSS Asset 4.841 2.618 (2.223) Management CBSS Admin Accom 14.030 14.030 0.000
CBSS IT Development 1.612 1.612 0.000 Plan CBSS Contingency 0.214 0.376 0.162
CBSS Economic 3.300 3.300 0.000 Infrastructure Fund Total 69.033 57.281 (11.752)
Table 2 Capital Programme Forecast Outturn 2012/13
7. To the mid point in January 2013 there was £30.209m of capital spend representing 54% of the revised budget.
Options
8. Members can consider the variations to the existing capital programme and choose to approve or reject the proposals contained within the report. Members can choose to approve or reject the recommendations made to Council as a result of the amendments contained in this report. Analysis
9. A summary of the key exceptions and implications on the capital programme are highlighted below.
ACE - Children’s, Education and Skills Services
Re-profiling
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.