City and Environmental Services Capital Programme – 2012/13 Outturn Report

Noted Executive 3 papers

Decision Session - Executive Member for Transport - Expired noted this item on Thursday 20 June 2013. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

That the Cabinet Member (i) Noted the progress achieved in delivering the schemes in the capital programme as indicated in the report annex. (ii) Approved the proposed carryovers as outlined in paragraphs 18 to 244 of the report, subject to approval of the Cabinet. REASON: To enable to effective management and monitoring of the councils capital programme. That the Cabinet Member (i) Noted the progress achieved in delivering the schemes in the capital programme as indicated in the report annex. (ii) Approved the proposed carryovers as outlined in paragraphs 18 to 244 of the report, subject to approval of the Cabinet. REASON: To enable to effective management and monitoring of the councils capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 8 pages

Summary

1. The purpose of this report is to inform the Cabinet Member of the outturn position for schemes in the 2012/13 CES Capital Programme, including the budget spend to 31 March 2013, and the progress of schemes in the year.

2. The report also informs the Cabinet Member of any variations between the outturn and the budget, and seeks approval for funding to be carried forward to 2013/14, subject to the approval of the Cabinet.

Background

3. The CES Planning & Transport Capital Programme budget for 2012/13 was confirmed at £7,354k at Full Council on 23 February 2012. The programme was finalised on 7 August 2012, when the Cabinet Member was presented with the Consolidated Capital Programme, which included all funding that had carried over from 2011/12.

4. A number of amendments to the programme were also made at the Monitor 1 and Monitor 2 reports to Decision Session in September and December 2012.

5. As a result of these amendments, the current approved budget for the 2012/13 Planning & Transport Capital Programme is £6,803k, which includes £1,954k of Local Transport Plan (LTP) funding, plus other funding from the Local Sustainable Transport Fund (LSTF) grant, developer contributions, council resources, funding from the Department for Transport for Access York Phase 1, and funding from the Better Bus Area Fund to improve public transport in York. This represents the budget available to spend, and is therefore net of the overprogramming built into the Local Transport Plan element of the programme, which is used to ensure the available funding is fully spent in each year.

6. The CES Planning & Transport Capital Programme also includes £72k of funding from council resources for the maintenance of the City Walls.

7. Table 1 shows the current approved capital programme.

Table 1: Current Approved Capital Programme

Gross External Capital Budget Funding* Receipts £000s £000s £000s Original CES Planning & 7,354 7,087 267 Transport Capital Programme Variations approved at +1,543 +1,434 +109 Consolidated Report Variations approved at Monitor -30 -30 1 Report Variations approved at Monitor -2,064 -1,945 -119 2 Report Current Approved CES 6,803 6,546 257 Capital Programme *External funding refers to government grants, non government grants, other contributions, developer contributions and supported capital expenditure.

Summary of Key Issues

8. Against the approved Planning & Transport budget of £6,803k in 2012/13, there is an outturn of £4,477k, and underspend of £2,326k. This is a high level of underspend compared to previous years, and is principally caused by the later than anticipated approval from the Department for Transport (DfT) for the Access York Phase 1 scheme, and delays in progressing some of the schemes in the Better Bus Area Fund programme. 9. In previous years, additional resources may have been introduced to speed up delivery on other schemes and deliver full spend in the year. This was not considered appropriate for 2012/13, due to the need for funding to be slipped to 2013/14 for delivery of schemes delayed in 2012/13. The programme included £2.083m of DfT funding which was not confirmed to be available until 28 March 2013 and therefore could not be spent on other schemes.

10. A substantial amount of work has been progressed in the year, including the following larger schemes:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Outturn ReportAppendix 1 11 pages Download
PDF
Capital Programme Outturn ReportAppendix 2 7 pages Download
PDF
City and Environmental Services Capital Programme: 2012/13 Outturn ReportReport 8 pages DownloadRead as text

At this meeting

Whole meeting
2MinutesApproved 4Westminster Road PetitionApproved
5City and Environmental Services Capital Programme – 2012/13 Outturn ReportThis decision

Who was there

1 of 2 attended
DM
Councillor Dave MerrettCabinet Member, present
AD
Councillor Andy D'AgorneAttendee, in attendance

On this subject at York

Search all
  1. City and Environmental Services Capital Programme – 2012/13 Outturn ReportThis decision
  2. City and Environmental Services Capital Programme - 2016/17 Consolidated ReportApproved
  3. City and Environmental Services Capital Programme - 2015/16 Outturn ReportNoted
  4. City and Environmental Services Capital Programme - 2016/17 Budget ReportApproved
  5. City and Environmental Services Capital Programme – 2015/16 Monitor 2 ReportApproved
  6. City and Environmental Services Capital Programme - 2015/16 Monitor 1 ReportApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies