City and Environmental Services Capital Programme - 2014/15 Budget Report
ApprovedExecutive2 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 10 April 2014. Below is the council's own wording, with the papers it was decided on.
That the proposed 2014/15 City and Environmental Services Capital Programme, as set out in the report and at Annex 1, be approved. Reason: To implement the Council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the Council’s Transport Programme. That the proposed 2014/15 City and Environmental Services Capital Programme, as set out in the report and at Annex 1, be approved. Reason: To implement the Council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the Council’s Transport Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 10 pages
Summary
1. This report sets out the funding sources for the City and Environmental Services Transport Capital Programme, and the proposed schemes to be delivered in 2014/15. The report covers the Integrated Transport and City and Environmental Services (CES) Maintenance allocations.
Background
2. Following approval at Full Council on 27 February 2014, the CES Planning & Transport Capital Programme budget for 2014/15 has been confirmed as £7,637k. The budget includes £2,823k of Local Transport Plan (LTP) funding, plus other funding from the from the Local Sustainable Transport Fund (LSTF) grant, the Better Bus Area Fund (BBAF) grant, the Department for Transport’s Local Pinch Point Funding (Tranche 3) grant, developer contributions, and council resources.
3. This is a significantly lower level of funding than was available in 2013/14 (£23,649k budget at Monitor 2), due to the additional funding from the Better Bus Area Fund (BBAF) for the Access York Phase 1 scheme in 2013/14.
4. In addition to the Transport Capital Programme, major improvement schemes in the city centre are proposed as part of the Reinvigorate York programme. Funding is included in the Transport Capital Programme as a contribution towards the Reinvigorate York projects. Proposed Transport Capital Programme
5. The proposed budget has been split into a number of blocks (shown in Table 1 below), which summarise the strategic aims of the third Local Transport Plan (LTP3) and the Council Plan. More details of the proposed allocations are included in the following paragraphs and in Annex 1 to this report.
6. The allocations shown in Table 1 include funding for schemes committed in previous years and an allowance for overprogramming. Overprogramming is used in the capital programme to ensure that the funding allocation is fully spent within the year. It allows additional schemes to be developed and delivered if other schemes are delayed due to unforeseen circumstances.
7. From the start of the LTP3 period, the level of overprogramming has been kept to a much lower proportion than in previous years, due to the reduced Local Transport Plan funding allocation compared to previous years
Table 1: Proposed 2014/15 Transport Capital Programme
Proposed Transport 2014/15 £1,000s Capital Programme Access York Phase 1 2,002 Public Transport Schemes 1,115 Traffic Management 2,240 City Centre Improvements 40 Cycling & Walking Network 1,487 Safety Schemes 450 Scheme Development & Completion 100 City Walls Restoration 290 Alleygating 85 Total Transport Programme 7,809 Overprogramming 172 Total Transport Budget 7,637
8. The proposed programme for 2014/15 has been developed to support the five strategic aims of LTP3, and the priorities identified in the Council Plan, including the completion of the Access York scheme, and the delivery of the A19 Local Pinch Point Improvement scheme, following the successful bid for funding to the Department for Transport. The programme takes account of the anticipated progress delivering schemes in 2013/14, including schemes that may carry over into 2014/15, and schemes that were developed in 2013/14 for implementation in future years.
9. Work on the Access York Phase 1 scheme to provide two new Park & Ride sites at Askham Bar and Poppleton Bar, with associated highway works and improvements to the A59 Roundabout, started on site in May 2013 and is expected to be complete by June 2014. As previously reported to the Cabinet Member in the Monitor 2 report in December, progress on the scheme was delayed due to land condition and utility diversion issues, and funding was slipped to 2014/15 due to these delays. An additional £200k allowance has been allocated to cover contingencies for the project in 2014/15.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.