That the Executive: (i) Note the 2015/16 revised budget of £95.290m as set out in paragraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2015/16 – 2019/20 as set out in paragraph 30, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme. That the Executive: (i) Note the 2015/16 revised budget of £95.290m as set out in paragraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2015/16 – 2019/20 as set out in paragraph 30, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1 The purpose of this report is to set out the projected outturn position for 2015/16 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.
2 The 2015/16 capital programme approved by Council on 26 February 2015, and updated for amendments reported to Executive and Council including the 16 July Budget Amendments, resulted in an approved capital budget of £100.381m.
Recommendations
3 Executive is asked to:
Recommend to Full Council the adjustments in the programme of a decrease of £5.091m in 2015/16 as detailed in the report and contained in Annex A. Note the 2015/16 revised budget of £95.290m as set out in paragraph 6 and Table 1.
Note the restated capital programme for 2015/16 – 2019/20 as set out in paragraph 30, Table 2 and detailed in Annex A.
Reason: To enable the effective management and monitoring of the Council’s capital programme.
Consultation
4 The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 26 February 2015. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
5 A decrease of £5.091m is detailed in this monitor resulting in a revised capital programme of £95.290m. £5.300m of the decrease is attributable to re-profiling to budgets to future years. Offsetting this is a net increase of £209k attributable to an increase in government grants available and use of S106 funds. The Councils borrowing need across the 5 year programme has reduced slightly, by £174k, as a result of the changes set out in this report.
6 Table 1 outlines the variances reported against each portfolio area.
Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m CSES Children’s 18.185 13.361 (4.824) Services, Education & Skills ASC Adult Social 1.679 1.464 (0.215) Services CANS Communities 3.015 3.127 0.112 Culture & Public Realm CANS Housing & 19.193 19.193 0.000 Community Safety
CES Highways & Waste 6.226 6.226 0.000
CES Transport 8.483 8.619 0.136
CES Economic 0.058 0.058 0.000 Development CES Community 20.714 20.714 0.000 Stadium CBSS Asset Management 3.559 3.559 0.000
CBSS West Offices - 0.512 0.512 0.000 Admin Accom CBSS IT Development 2.996 2.696 (0.300) Plan CBSS Misc(Contingency ) 0.443 0.443 0.000
CBSS Economic 15.318 15.318 0.000 Infrastructure Fund Total 100.381 95.290 (5.091)
Table 1 Capital Programme Forecast Outturn 2015/16
7 To the mid point in August there was £13.2m of capital spend representing 13% of the revised monitor 1 budget.
Analysis
8 A summary of the key exceptions and implications on the capital programme are highlighted below.
CSES – Children Services, Education and Skills
9 There is a single request for re-profiling funds from 15/16 to 16/17 required as part of this report.
10 In 2015/16 the main focus of Basic Need expenditure is on the schemes at Fulford School and St Barnabas Primary School. Apart from these expansions, only a small number of minor schemes will be carried out in this financial year. A total of £520k is committed to providing the local authority’s contributions to the two EFA funded school rebuilds (Carr Infant and Lord Deramore’s Primary), under the Priority Schools Building Programme (PSBP), that were the subject of successful bids in 2012. At Carr Infant an estimated contribution of £370k is funding additional classrooms within the new building and some landscaping works, neither of which will be funded by the EFA. These two schemes are expected to complete in 2015/16 therefore the contributions will be required in this financial year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.