( i ) That the 2019/20 revised budget of £205.478, as set out in Table 1 at paragraph 6 of the report, be noted. (ii) That the re-stated capital programme for 2019/20 – 2023/24, as set out in Table 2 at paragraph 17 and detailed in Annex A, be noted. (iii) That approval be given to increase the gross budget for the Assistance to Older & Disabled People programme by £200k, funded by a revenue contribution from the Housing Revenue Account (HRA), as detailed in paragraph 25. (iv) That the contract award outlined in paragraphs 57 to 62 be approved. Reason: To enable the effective management and monitoring of the council’s capital programme. (i) That the 2019/20 revised budget of £205.478, as set out in Table 1 at paragraph 6 of the report, be noted. (ii) That the re-stated capital programme for 2019/20 – 2023/24, as set out in Table 2 at paragraph 17 and detailed in Annex A, be noted. (iii) That approval be given to increase the gross budget for the Assistance to Older & Disabled People programme by £200k, funded by a revenue contribution from the Housing Revenue Account (HRA), as detailed in paragraph 25. (iv) That the contract award outlined in paragraphs 57 to 62 be approved. Reason: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1 The purpose of this report is to set out the projected outturn position for 2019/20 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.
2 The 2019/20 capital programme approved by Council on 28 February 2019, updated for amendments reported to Executive and Council in the 2018/19 outturn report and subsequent budget amendments totalling £4.25m made by the new administration resulted in an approved capital budget of £205.478m.
Recommendations
3 Executive is asked to:
Recommend to Full Council the adjustments resulting in a decrease in the 2019/20 budget of £65.816m as detailed in the report and contained in Annex A.
Note the 2019/20 revised budget of £205.478 as set out in paragraph 6 and Table 1.
Note the restated capital programme for 2019/20 – 2023/24 as set out in paragraph 17, Table 2 and detailed in Annex A.
Agree to increase the gross budget for Assistance to Older & Disabled People programme by £200k funded by a revenue contribution from the HRA as detailed in paragraph 25
Agree to the contract award as outlined in paragraphs 57 to 62 Reason: to enable the effective management and monitoring of the Council’s capital programme.
Consultation
4 The capital programme was developed under the capital budget process and agreed by Council on 28 February 2019. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
5 A decrease of £65.816m is detailed in this monitor resulting in a revised capital programme of £205.478m. There is an increase of £1.394m in 2019/20 attributable to new schemes added to the programme agreed by members set out in the paragraphs below. This is offset by a £67.210m decrease in 2019/20 due to re-profiling of budgets to future years.
6 Table 1 outlines the variances reported against each portfolio area.
Department Current Projected Increase Reprofile Total Paragraph Approved Outturn (decrease) Variance Ref Budget £m £m £m £m £m Children, Education & 23.233 16.979 0.846 (7.100) (6.254) 8 - 17 Communities Health, Housing & Adult 7.371 6.670 0.896 (1.597) (0.701) 18 - 22 Social Care – Adult Social Care Health, Housing & Adult 55.860 39.258 (0.408) (16.194) (16.602) 23 - 34 Social Care – Housing & Community Safety Economy & Place – 78.219 41.468 2.580 (39.507) (36.927) 35 - 48 Transport, Highways & Environment
Customer & Corporate 3.482 2.999 0.000 (0.043) (0.043) 53 - 54 services IT Development Plan 5.085 5.085 0.000 0.000 0.000 55 Total 271.294 205.478 1.394 (67.201) (65.816)
Table 1 Capital Programme Forecast Outturn 2019/20
Analysis
7 A summary of the key exceptions and implications on the capital programme are highlighted below.
Children, Education & Communities
8 Amendments made as part of this report have resulted in a new reduction in the capital programme of £6.254m in 2019.20 Key variances are summarised in the table below, referenced to further narrative.
Scheme Amendment Amount Amount Further 19/20 20/21 Details – £m £m Paragraph ref Basic Need Re-profile (7.000) 7.000 9 - 14 Basic Need Adjustment (0.250) - 9 - 14 Centre of Excellence for Adjustment 1.120 - 15 disabled children (Lincoln Court) Energise Roof Re-profile (0.100) 0.100 16
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.