Recommended: (i) That Council agree the revised capital programme of £546.880m , reflecting a net overall increase of £41.037m (as set out in Table 2 at paragraph 13 of the report and in Annex A), key elements of which include: a) New schemes funded by prudential borrowing totalling £7.513m, as set out in Table 3; b) New schemes funded by a combination of prudential borrowing and external funds totalling £3.300m, as set out in Table 4 and summarised in Table 5; c) New schemes funded by a combination of prudential borrowing and other internal funds totalling £200k, as set out in Table 6; d) Extension of prudential borrowing funded Rolling Programme schemes totalling £10.870m, as set out in Table 5 and summarised in Table 7; e) Extension of externally funded Rolling Programme schemes totalling £7.00m, as set out in Table 9; and f) An increase in HRA-funded schemes totalling £11.954m, funded from a combination of HRA balances and Right to Buy balances, as set out in Table 10. (ii) That Council note that the total increase in council borrowing as a result of new schemes being recommended for approval is £20.483m, the details of which (schemes) are considered within this report and the financial strategy report. (iii) That Council approve the full re-stated programme totalling £546.880m , covering financial years 2021/22 to 2025/26, as set out in Table 14 at paragraph 75 of the report, and in Annex B. Reason: In accordance with the statutory requirement to set a capital budget for the forthcoming financial year.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. This report sets out the capital programme for 2021/22 to 2025/26, and in particular sets out proposals to continue the Council’s approach to prioritise investment in the economy, housing, transport and to invest to save including energy efficiency.
2. Schemes funded by borrowing have an associated revenue impact. In order to minimise the additional growth required in future years and, mindful of the Council’s current financial position in light of both the ongoing pressures in social care and the uncertainty regarding the COVID-19 pandemic, the Council has reviewed the level of capital investment needed. It has been possible to reprioritise some areas of the existing capital budget to invest in the Council’s priorities and to support the city’s recovery from the impacts of Covid-19. The Council’s main focus is to build back better form the pandemic. The schemes outlined in this report continue the transformational capital programme to drive regeneration and accelerate the city’s economic recovery.
3. As part of this budget process over £41m of new capital funding will be added to the 5 year capital programme to continue to support the objectives outlined in the Council Plan, including a further £8.8m on highways schemes, £5.3m on fleet infrastructure and vehicles to deliver as many electric vehicles as possible and £3.3m on flood alleviation schemes including Germany Beck. A summary of this new funding can be found at Annex A, and specific examples of capital investment include:
Good Health & Wellbeing – additional capital investment of over £3m on a range of schemes employing the latest technology to enable people to live in their own homes for longer, including £200k to trial the use of robotics to improve the quality of social care and to support adult social services, and over £3m on assistance to older & disabled people schemes, disabled facilities grants, telecare equipment, and major items of disability equipment to support vulnerable residents.
Safe Communities and Culture for all – capital investment of £200k to fund the development of a Multi Use Games Area at Westfield.
A Greener and Cleaner City – capital investment of over £5m to develop new initiatives to reduce carbon emissions, including £5m to support the Council’s vehicle and infrastructure policy to deliver as many electric vehicles as possible and a further £250k on carbon reduction schemes to fit carbon reduction technology on Council assets.
Getting around sustainably - capital investment of over £18m including over £12m for a range of highways schemes including repairs and improvement to the highways network, investment in gully repair and drainage works and further investment in the Bar Walls, and £3.3m investment in flood alleviation schemes including Germany Beck.
Creating homes and world class infrastructure – capital investment of nearly £12m, including over £10 million to increase the scale of modernisation works to Council housing stock.
An Open and effective Council - capital investment of over £3m to support the Council’s digital programme and support change in a range of front line services.
Well Paid Jobs and an Inclusive economy – capital investment of £1m in a Covid Recovery Fund to ensure that capacity is available within the 2021/22 programme to respond to any capital investment needed to ensure a strong recovery for the city.
4. Further details on the schemes referred to above can be found in the body of this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.