CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council
Executive, Thursday 11 February 2021 at 5.30pm

Capital Programme - Monitor 3 2020/21

Noted Executive 3 papers

Executive noted this item on Thursday 11 February 2021. Below is the council's own wording, with the papers it was decided on.

Item97

Resolved

(i) That the 2020/21 revised budget of £119.859m, as set out in paragraph 6 of the report and in Table 1, be noted. (ii) That the re-stated capital programme for 2020/21-2024/25, as set out in Table 2 at paragraph 75, be noted. (iii) That approval be given to fund the schemes listed in the table at paragraph 15 from the existing Maintenance programme for 2021/22. Reason: To enable the effective management and monitoring of the council’s capital programme. (i) That the 2020/21 revised budget of £119.859m, as set out in paragraph 6 of the report and in Table 1, be noted. (ii) That the re-stated capital programme for 2020/21-2024/25, as set out in Table 2 at paragraph 75, be noted. (iii) That approval be given to fund the schemes listed in the table at paragraph 15 from the existing Maintenance programme for 2021/22. Reason: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Summary

1 The purpose of this report is to set out the projected outturn position for 2020/21 including any under/over spends and adjustments, along with requests to re-profile budgets to/from current and future years.

2 The 2020/21 capital programme approved by Council on 27 February 2020 and updated for amendments reported to Executive in the 2019/20 outturn report resulted in an approved capital budget of £144.683m.

3 Whilst capital investment has been disrupted due to the pandemic, progress has still been made in a number of areas including

 Continued delivery of Shared Ownership homes with the portfolio now totalling 48 properties with a further 17 in the process of being purchased  Continued conversion of bus fleets up to the emissions standard required for the city centre Clean Air Zone, with all conversion works due to be completed by 31 March 2021.  Completion of major expansion at Archbishop Holgate Academy delivering a new three storey classroom block, together with the conversion of some existing classrooms into specialist teaching facilities for Science, ICT and Graphics  Further rollout of ICT and support to enable continued remote working  The completion and opening of facilities the Community Stadium as set out at paragraphs 60 - 73. Recommendations

4 Executive is asked to:

 Recommend to Full Council the adjustments resulting in a decrease in the 2020/21 budget of £24.824m as detailed in the report and contained in Annex A.

 Note the 2020/21 revised budget of £119.859m as set out in paragraph 6 and Table 1.  Note the restated capital programme for 2020/21 – 2024/25 as set Reason: to enable the effective management and monitoring of the Council’s capital programme.  Approve the schemes listed in the table at paragraph 18 to be funded from the existing Maintenance programme for 2021/22

Consultation

5 The capital programme was developed under the capital budget process and agreed by Council on 27 February 2020. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.

Summary of Key Issues

6 A decrease of £24.824m is detailed in this monitor resulting in a revised capital programme for 2020/21 of £119.859m. There is an increase of £2.769m in 2020/21 and a re-profiling of budgets to future years totalling £27.593m. The majority of this re-profiling is due to revisions in assumed spend profile in schemes such as York Outer Ring Road dualling, Fleet acquisition and Waste Vehicle replacement,

7 Table 1 outlines the variances reported against each portfolio area and a summary of the key exceptions and implications on the capital programme are highlighted in the paragraphs that follow. Department Current Projected Increase Reprofile Total Paragraph Approved Outturn (decrease) Variance Ref Budget £m £m £m £m £m Children, Education & 15.667 13.231 0.221 (2.657) (2.436) 8 - 19 Communities Health, Housing & Adult 3.366 3.867 0.473 0.028 0.501 20 – 22 Social Care – Adult Social Care Health, Housing & Adult 44.095 45.050 1.254 (0.299) 0.955 23 – 31 Social Care – Housing & Community Safety Economy & Place – 56.545 33.342 0.527 (23.730) (23.203) 32 – 54 Transport, Highways & Environment Economy & Place – 18.150 17.675 - (0.475) (0.475) 55 – 58 Regeneration & Asset Management Community Stadium 1.865 2.219 0.354 - 0.354 60 – 73 Customer & Corporate 2.358 2.108 (0.060) (0.190) (0.250) - services IT Development Plan 2.637 2.367 - (0.270) (0.270) 74

Total 144.683 119.859 2.769 (27.593) (24.824)

Table 1 Capital Programme Forecast Outturn 2020/21 Analysis

Children, Education & Communities

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Abbreviated Annex AAppendix 208 KB Download
PDF
Capital Programme: Monitor 3 2020/21Report 529 KB DownloadRead as text
PDF
View item 97. as HTML 298 KBReport 298 KB Copy on its way

At this meeting

Whole meeting

Who was there

10 of 10 attended
KA
Councillor Keith AspdenChair, present
NA
Councillor Nigel AyreCommittee Member, present
DC
Councillor Denise CraghillCommittee Member, present
IC
Councillor Ian CuthbertsonCommittee Member, present
AD
Councillor Andy D'AgorneCommittee Member, present
KO
Councillor Keith OrrellCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
DS
Councillor Darryl SmalleyCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present
PW
Councillor Paula WiddowsonCommittee Member, present

On this subject at York

Search all
  1. Capital Programme - Monitor 3 2020/21This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies