(i) That the 2021/22 capital outturn position of £78.220m be noted and that the requests for re-profiling from the 2021/22 programme to future years, totalling £49.153m, be approved. (ii) That the adjustments to schemes reducing expenditure in 2021/22 by a net £211k be noted. (iii) That the use of £4m contingency to fund the additional costs of the Guildhall refurbishment be approved. Reason: To enable the effective management and monitoring of the council’s capital programme. (i) That the 2021/22 capital outturn position of £78.220m be noted and that the requests for re-profiling from the 2021/22 programme to future years, totalling £49.153m, be approved. (ii) That the adjustments to schemes reducing expenditure in 2021/22 by a net £211k be noted. (iii) That the use of £4m contingency to fund the additional costs of the Guildhall refurbishment be approved. Reason: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Capital Programme Outturn 2021/22 and Revisions to the 2022/23 – 2026/27 Programme
Report Summary
1. The purpose of this report is to set out the capital programme outturn position including any under or over spends, overall funding of the programme and an update as to the impact on future years of the programme.
2. The report contains details of the capital investment made during 2021/22 and how this has supported delivery of the Council Plan. Key areas of investment are listed below with further details contained in the body of the report.
£4.9m on the expansion and improvement of school facilities across the city £10.7m on construction of new council housing £12.7m on the modernisation of and ongoing repairs to council homes £1.2m for new apartments, along with community facilities and café at Marjorie Waite Court £5.6m on highways £2.9m on the purchase of new waste vehicles £10m on the delivery of the Guildhall scheme
3. Some of the direct outcomes from this investment include:
Upgraded kitchen and dining room facilities at Huntington School 34 additional apartments at Marjorie Waite Court, including 10 dementia ready apartments, a community hall and a community café. 88 homes completed at Lowfield Green 289 tenants choice works completed with a further 143 homes modernised through the standing water and voids programme 470 households benefited from new gas central heating systems and 136 properties benefited from new windows Upgrades to traffic signals at 11 locations across the city Installation of electric vehicle charging points at nine sites across the city 72.5km of carriageway was renewed and 371 street lighting columns were replaced A range of high quality office, meeting room and business spaces are available at the Guildhall
4. The economy is currently experiencing levels of inflation that have not been seen for around 20 years. At the time of writing this report inflation stands at 9% and inflation in the construction sector is running at a higher level. Prices of raw materials such as steel and timber are particularly expensive due to supply issues, global demands and wider economic factors. This has also impacted on the prices quoted by contractors and willingness to fix prices in quotes and tenders. This has and will continue to put pressure on the Council Capital programme. Many of the estimates for costs assumed lower inflation pressures (c 2%) so there will be a need to review costs on the major schemes and rolling programmes. Any impact will be reported back to future Executive meetings.
5. This report in particular reports on the completion of the Guildhall project which is reporting a £4.0m pressure compared to the latest budget. The additional costs have arisen partly due to the impact of the economic factors above but were more so by a number of delays resulting from the complexities of refurbishing this unique historic building. These are detailed further in the sections later in the report.
6. The report shows an outturn of £78.220m compared to an approved budget of £127.584m, an overall variation of £49.364m.
7. The net variation of -£49.364m is made up as follows:
Requests to re-profile budgets of a net -£49.153m of schemes from 2021/22 to future years (currently approved budgets in the capital programme but requires moving to or from future years in line with a changing timetable of delivery for individual schemes) Adjustments to schemes decreasing expenditure by a net £211k, mainly due to additional grant funding being received.
8. The level of re profiling reflects the scale of the capital programme, and in particular that it contains a number of major and complex projects. The overall capital programme continues to operate within budget, due to careful management of expenditure against the budget.
9. The main areas of re-profiling included within the £49.153m include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.