Decision 1. Noted the Capital Plan position; and 2. Noted that a report would be brought to the Area Committees advising on progress with flood prevention works in their respective areas. (Reference: Report by Head of Strategic Finance dated 26 January 2010, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
3.1The overall council financial summary outlines financial performance on the capital plan at 31 December 2009. Year to date expenditure is £20,031k compared to the year to date budget of £21,686k, resulting in an underspend of £1,655k. The forecast for the whole of 2009/10 is for expenditure of £28,893k compared to a budget of £29,266k giving a slippage of £373k. In terms of total project costs these are expected to exceed the budget by £3,080k.
3.2As at 31 December, the year to date actual is less than year to date budget by £1.655m. This is an increase of £1.825m from November. This can be attributed to the following main projects:
Rothesay Harbour Ferry Berth Improvement – decrease in YTD overspend of £0.594m. This has been caused by a significant payment to the contractor in November rather than December and the inability to collect the outstanding marine Grant which was profiled for December. Maintenance certificate must be issued.
Roads Reconstruction - increase in YTD underspend of £0.256m. There has been a substantial failure in one of the projects and payment to the contractor has been withheld pending resolution.
Class Size Reduction – increase in YTD underspend of £0.254m. Slippage as a result of extremely competitive tenders being received for a number of projects within this scheme, and a slight delay in issue of tenders for the new classroom at Rhu.
North Bute Primary School – increase in YTD underspend of £0.197m. Delays in obtaining building warrant and planning consent, in addition extensive negotiations required following receipt of over budget tenders. Glencruitten Hostel – increase in YTD underspend of £0.153m. Previous expenditure forecast was incorrect. The current figures correct this. (Contract is on programme).
Residential Respite Care – increase in YTD underspend of £0.150m. Slight delay in accepting tender (following the signing up of a service provider) , has now been compounded by delay caused by exceptionally adverse weather.
Campbeltown Infrastructure Improvements – increase in YTD underspend of £0.136m. - Due to the unavailability of contractors to start ground investigation work when originally anticipated.
3.3As at 31 December,slippage of £0.373m has been forecast for this year. This is further slippage of £0.138m compared to the end of November report. In order to address some of the frost damage to the roads network as a result of the extreme winter conditions it is proposed to accelerate around £1m of roads reconstruction works from 2010-11 to 2009-10. To accommodate this within the overall capital plan for 2009-10 the expenditure on a number of projects will slip into 2010-11.
For further information please contact Bruce West, Head of Strategic Finance 01546- 604220
Bruce West Head of Strategic Finance 26 January 2010 ARGYLL AND BUTE COUNCIL - CAPITAL PLAN MONITORING REPORT - OVERALL COUNCIL FINANCIAL SUMMARY - 31 DECEMBER 2009
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.