PROPOSED DUNOON BUSINESS IMPROVEMENT DISTRICT

Agreed Committee 1 paper

CHORD Programme Management Board agreed this item on Tuesday 18 May 2010. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision Following a lengthy discussion when concerns were expressed about whether or not the BID proposal would support and add value to the Dunoon CHORD projects, the Board:- 1. Welcomed the interest of the Dunoon and Cowal Business Association in developing a BID proposal and agreed in principle to support the request from DCBA for £15,000 to support development subject to the DCBA attracting match funding from the Scottish Government, LEADER and HIE with approval being conditional on receipt of a fully costed business case and subject to the proposal being assessed through the gateway process of initial, outline and final business cases; and 2. Agreed that this did not commit future funding to the BID. (Reference: Report by Head of Economic Development dated 7 May 2010, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to CHORD Programme Management Board

Summary

1.1A proposal to assist, financially, with the establishment of a Business Improvement District (BID) in Dunoon has been received by the Dunoon CHORD Project Board, via the Dunoon and Cowal Business Association (DCBA) - see Appendix 1.

1.2This paper provides background information on a BID, details the proposal from the DCBA and suggests the circumstances under which the Council would consider supporting a BID proposal.

Recommendations

2.1That the Programme Management Board:

x discuss the proposal received from DCBA, and; x advise the Dunoon CHORD Project Board of the circumstances under which the Council would consider supporting a BID proposal.

3. DETAIL

Background to a BID

3.1There are several key stages in progressing a BID:

Stage Comment Concept A BID is a business led initiative within a defined geographical area, where businesses work together and invest collectively in local improvements to their business environment. Improvements The improvements are in addition to those projects / services delivered by local authorities. A BID is often, but not exclusively, a partnership arrangement through which the local business community and statutory authorities take forward projects to benefit the local economy. It is essential that a Service Legal Agreement be drawn up with the BID company to regulate any payments to the Local Authority. The Need There must be a clear demonstrable need. A decision must be made in respect of which projects / services are needed to enhance the business environment. The business plan must be developed - including the delivery mechanisms, performance indicators, governance and management structures. The business plan would also include any exemptions to the levy and the justification for these. The business plan must be developed in advance of the vote. The Vote The business community vote to collectively invest. If “Yes” – the business plan is activated. A BID proposal in Scotland will only go ahead if more than half of the businesses that vote, vote in favour and they represent more than half the rateable value of the BID area. A minimum turnout figure of 25% of businesses is also required. NORMAL TIMEFRAME TO GET TO THIS POINT IS 12 – 18 MONTHS Stage Comment The Levy The BID is financed through a levy on business rates. This is normally between 1p and 5p. This represents 2.5% and 12.5% respectively of the rates charge. The Council would also be subject to the levy applied in the BID area. The levy is set out in the business plan. This usually covers a 5 year period - after this time businesses can vote on a new business plan and start the whole process again. The levy is collected via a separate bill to Non-Domestic Rates by the billing authority and then handed over to the BID company. Additional funds The BID company can lever in additional funds from elsewhere to improve the value for money of projects / services. Measure results The success of the BID will be judged by the outputs that the BID company delivers. Every year the BID Company should publish an action plan that will detail specific services / projects that the company will deliver. Progress against this plan will be scrutinised. Key performance indicators will relate to the completion of the action plan. Management A Steering Group will have the responsibility for agreeing and managing the budget, which will be set on an annual basis. Financial management of the BID project will be operated in accordance with appropriate financial and project management procedures recommended by the BID company appointed accountants.

3.2The Scottish Government have a development fund for reaching ballot stage of £20,000. Evidence from areas that have already progressed to this stage suggests that the cost to reach ballot stage is usually in excess of £20,000.

DCBA BID Progress

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PROPOSED DUNOON BUSINESS IMPROVEMENT DISTRICTReport 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 7 attended
DH
Douglas HendryOfficer, present
SL
Sally LoudonOfficer, present
RM
Councillor Robert MacintyreMember, apologies
SM
Sandy MactaggartOfficer, expected
FM
Fiona McCallumSecretary, expected
DW
Councillor Dick WalshMember, present
BW
Bruce WestOfficer, present

On this subject at Argyll and Bute

Search all
  1. PROPOSED DUNOON BUSINESS IMPROVEMENT DISTRICTThis decision
  2. Scottish government - funding of schools for the future projects; proposed new school facilities for dunoon and campbeltown; governance and other mattersNoted
  3. Proposed BIDS Scheme for Dunoon Town CentreAgreed
  4. Timber Haul Road, Dunoon - Proposed Grant of Servitude to Forestry CommissionAgreed
  5. Proposed Sale of Former Holy Loch Community Centre, Sandbank, Dunoon - The Chairman has determined that this matter will be reconsidered in terms of Standing Order 16.2 (1&2) and the previous decision may be altered or revoked in the light of a material change in circumstancesDecided
  6. Proposed lease extension - dunoon pipe bandApproved

More from Argyll and Bute CHORD Programme Management Board

All decisions
MeetingDecisionOutcome
5 Mar 2013 Chord programme update - highlight / progress reportDecision The CHORD Programme Board – 1. Noted the report. 2. Agreed that a brief paper containing the detail that had... Noted Open
5 Mar 2013 Chord consultancy frameworkDecision The CHORD Programme Board noted the verbal update. (Reference: Verbal update by CHORD Programme Manager) Noted Open
5 Mar 2013 Lorn arc updateDecision The CHORD Programme Management Board noted the information provided in the presentation. (Reference: Present... Noted Open
5 Mar 2013 Strategic programme board - discussion paperDecision The CHORD Programme Management Board – 1. Agreed to recommend the proposed formation of a Strategic Programm... Agreed Open
13 Feb 2012 LORN ARCDecision Noted the updated position. (Reference: Verbal report by CHORD Programme Manager) E1 Noted Open