Campbeltown CHORD Project Board, Monday 31 January 2011 at 2.00pm

KINLOCH ROAD REGENERATION - PUBLIC REALM

Noted Committee 1 paper

Campbeltown CHORD Project Board noted this item on Monday 31 January 2011. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision 1. Noted that the date on the front page of the report should have read 31 January 2011 and not 31 January 2010; 2. Noted the final proposals for public realm; and 3. Agreed to recommend to the CHORD Programme Management Board that the drawdown of the next phase of approved public realm budget to permit the procurement of materials and associated services be approved. (Reference: Report by Head of Economic Development and Strategic Transportation dated 24 January 2011, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Campbeltown CHORD Project Board

Summary

1.1The Full Business Case for Kinloch Road Regeneration (KRR) was approved by the Campbeltown CHORD Project Board, 30 April 2010.

1.2The initial drawdown of capital funds was approved in May 2010 in order to progress the first element of the project, i.e. the roads depot relocation / remediation.

1.3The next element of the KRR project is the public realm improvements associated with the provision of the new road through Park Square. This element of the public realm must be agreed in order that tenders for the new road can be finalised to allow construction to commence early 2011. This paper outlines the final proposals for the public realm improvements and seeks the drawdown of the next phase of capital funds to progress the project.

Recommendations

2.1That the Campbeltown CHORD Project Board notes the final proposals for public realm and approves the drawdown of the next phase of approved public realm budget (£1.25million) to permit the procurement of materials and associated services. The budget is in line with the approved Full Business Case for KRR.

3. DETAIL

3.1Introduction

KRR is one of three schemes being pursued in Campbeltown through the CHORD programme. The project is closely linked with Campbeltown Infrastructure Improvements, in particular a new road through Park Square, and ACHA’s plans to develop the Park Square area. The KRR project seeks to facilitate these various elements to allow the physical regeneration of the Kinloch Road area.

The Kinloch Road Regeneration public realm scheme includes key entrance points to the heart of Campbeltown. The new gateway areas will include the public realm proposals in association with new road linking Millknowe Street with Kinloch Road with its iconic view of the Aqualibrium flanked by the new ACHA housing, potential public space and office development. The public realm can be considered to be broken into 3 key elements:

• Public realm along the new road; • Public realm along the remainder of Kinloch Road, Lochend Street (as previously agreed) • Public realm along Hall Street (as recently agreed to permit an overlap between the THI and the KRR areas to maximise value for money).

The first element of these is now considered to be complete in design terms and must progress to procurement to tie in with construction of the new road. The second element has been designed in draft and consultation undertaken; detailed designs will now progress ensuring good tie in with the new road proposals.

The third element is now underway following Project Board approval on 10 December 2010. Consultation with the THI project team has taken place and an action plan to progress has been developed. This will be subject to separate consultation and will be tied into other areas of design along Kinloch Road ensuring a co-ordinated look to the area appropriate for the modern Aqualibrium and the heritage of the town centre.

The proposals for public realm associated with the new road, described below, were initially developed for the Kinloch Road Planning submission in April 2010, and have been developed in response to final road design, stakeholder and public consultation feedback.

Consultation

In May/June 2010 outline options for the Kinloch Road public realm proposals were issued for stakeholder feedback. Based on the feedback received a sketch proposal was issued in November 2010 for a further round of stakeholder and public consultation. This was submitted to the project board for comment in December 2010.

No objections have been raised in principle to the project or the design approach to public realm development. Some specific scheme elements have required further discussion with stakeholders, for example;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
KINLOCH ROAD REGENERATION: PUBLIC REALMReport 94 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 8 attended
NB
Neil BrownOfficer, apologies
RC
Councillor Rory ColvilleMember, present
AH
Councillor Anne HornMember, absent
DK
Councillor Donald KellyMember, apologies
AM
Aileen MacLennanOfficer, expected
RP
Robert PollockOfficer, present
JS
Councillor John SempleMember, present
BW
Bruce WestOfficer, expected

On this subject at Argyll and Bute

Search all
  1. KINLOCH ROAD REGENERATION - PUBLIC REALMThis decision
  2. Kinloch road regeneration public realm - position statement (agenda item 4)Agreed
  3. Argyll community housing association: erection of 30 residential units (comprising 2 semi detached dwellinghouses and 28 flats over 4 blocks) with associated access road, parking and communal garden areas: development site, mccallum street and kinloch road and longrow, campbeltown (ref: 10/02153/pp)Agreed
  4. Highlight progress report - kinloch road regenerationAgreed
  5. Kinloch road regeneration - update on the impact of extending the public realm scope to incorporate hall streetDecided
  6. Campbeltown chord - kinloch road regeneration project - acha fundingApproved

More from Argyll and Bute Campbeltown CHORD Project Board

All decisions
MeetingDecisionOutcome
7 Mar 2013 Kinloch road regeneration public realm - position statement (agenda item 4)Decision Members agreed to note the report and asked that clarification be provided by email to Members by the CHORD ... Agreed Open
7 Mar 2013 Campbeltown budget position statement (agenda item 5)Decision Members agreed to note the report. (Reference: Report by Head of Economic Development and Strategic Transpor... Agreed Open
7 Mar 2013 Campbeltown berthing facility - highlight / progress report (agenda item 6)Decision Members agreed 1. To note the report. 2. That a proper plan needs to be developed to improve the fishermen’s... Agreed Open
13 Apr 2011 Highlight progress report - campbeltown thiThe Board agreed to note the report. (Ref: A report by Audrey Martin, dated 6 April 2011, submitted). Agreed Open
13 Apr 2011 Highlight progress report - kinloch road regenerationThe Board agreed to note the report. (Ref: A report by Joanne Casey, dated 4 April, 2011, submitted). Agreed Open