CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Campbeltown CHORD Project Board, Monday 31 January 2011 at 2.00pm

HIGHLIGHT / PROGRESS REPORT - KINLOCH ROAD REGENERATION PROJECT

Noted Committee 1 paper

Campbeltown CHORD Project Board noted this item on Monday 31 January 2011. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision 1. Noted the contents of the report; 2. Noted that a further 2 potential high risks should now be highlighted to the Board in respect of the legal agreement between ACHA and the Council in respect of the transfer of land and potential costs to ACHA if their housing development at Kinloch road has to be raised to avoid flooding; 3. Noted that Joanne would circulate a briefing note to members of the Project Board advising on the outcome of a meeting being held between legal representatives from ACHA and the Council on Friday 4 February 2011 to discuss the legal agreement in respect of the transfer of land; and 4. Noted that Joanne had asked ACHA to contact Planning to find out what the implications would be for ACHA if the housing development has to be raised and that she would report back to Robert Pollock on the outcome of these discussions. (Reference: Highlight/Progress Report – Kinloch Road Regeneration Project dated 21 January 2011, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Campbeltown CHORD Project Board

HIGHLIGHT / PROGRESS REPORT PROJECT NAME: Kinloch Road Regeneration Project Manager: Joanne Casey Reporting Period: 10/12/10 – 31/01/11 Date report prepared: 21/01/01 Implementation of the Full Business Project stage: Project stage completion date: 31/01/11 Case

Tolerance levels for this stage: Project Plan + / - 15 working days Project budget + / - 10%, or £10,000 whichever is greater

Progress – please refer to Project Plan Key products completed this period Key products outstanding this Revised Key products for next reporting Delivery date (including those completed ahead of schedule) period delivery date period (including brief explanation of why product outstanding) Demolition of Roads Depot complete

Remediation of roads depot 01/04/11 Negotiation with land owners at tbc if site adjacent to roads depot. applicable (as agreed at PBM 10.12.10) Agreement on land adjacent to 31/03/11 council depot Liaison with ACHA public realm 31/01/11 designs Legal Agreement between ACHA 10/03/11 and ABC for transfer of land.

d:\moderngov\data\published\intranet\c00000433\m00004510\ai00057284\cn03highlightprogrepjan20110.doc Risk Management – please refer to Risk Register (updates risks below in red text) Target Risk Description Proposed Cate Risk Date Ref Project (event & Prob. Impact Risk Mitigation Status (incl. date) Actionee gory Owner for consequence) Measure Close Cost Time Score 16 KRR Roads Depot - Progr 3 3 2 9 Contingency Liaison with Scott Wilson Joanne Joanne 31/03/ demolition and site amm built into underway to agree Casey Casey 2011 remediation. There e costing; lower remediation strategy may be additional priority elements Additional GI work contamination issues. of work held undertaken prior to back to ensure demolition, further GI remediation can undertaken, significant be completed levels of hydrocarbon due to found which will have to significance of be addressed and which the remediation will impact on cost of work work for the Final check on waste wider KRR, CII, arising from site to be ACHA work undertaken by Contractors

Budget Management Total budget available to complete FBC stage: £100,000 Forecast expenditure for current financial year Actual expenditure to date Variance explanation if required: £69,000 £69,000 Revenue budget now fully utilised. Business Case developed and now progressing implementation stage. Total budget available to complete £3,995,000 implementation of FBC stage: Forecast expenditure for current financial year Actual expenditure to date Variance explanation if required: £2,230,000 £233,458 All capital spend to date has been on the roads depot relocation and remediation. ACHA funding, 50% of Public realm, full remediation of the depot are included in the forecast for this financial year. Any further information

PID documents: including appendices – i.e. risk register, project plan and communications plan have all been updated to reflect current position. Now working from version 1.6

Agreement of the way forward with the land adjacent to council depot on hold until remediation is complete. .

Drawdown of capital funds for public realm being requested. Separate paper – prepared for review at Project Board meeting. No alterations to cost estimates.

Drawdown of contingency fund for remediation of depot site requested. Separate paper – prepared for review at Project Board meeting. Impact on costs but allowed for in project contingency.

d:\moderngov\data\published\intranet\c00000433\m00004510\ai00057284\cn03highlightprogrepjan20110.doc

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HIGHLIGHT / PROGRESS REPORT: KINLOCH ROAD REGENERATION PROJECTReport 69 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 8 attended
NB
Neil BrownOfficer, apologies
RC
Councillor Rory ColvilleMember, present
AH
Councillor Anne HornMember, absent
DK
Councillor Donald KellyMember, apologies
AM
Aileen MacLennanOfficer, expected
RP
Robert PollockOfficer, present
JS
Councillor John SempleMember, present
BW
Bruce WestOfficer, expected

On this subject at Argyll and Bute

Search all
  1. HIGHLIGHT / PROGRESS REPORT - KINLOCH ROAD REGENERATION PROJECTThis decision
  2. Highlight/progress reportNoted
  3. Rothesay Pavilion - Highlight/Progress ReportNoted
  4. Rothesay THI - Highlight/Progress ReportNoted
  5. Campbeltown berthing facility - highlight / progress report (agenda item 6)Agreed
  6. Chord programme update - highlight / progress reportNoted

More from Argyll and Bute Campbeltown CHORD Project Board

All decisions
MeetingDecisionOutcome
7 Mar 2013 Kinloch road regeneration public realm - position statement (agenda item 4)Decision Members agreed to note the report and asked that clarification be provided by email to Members by the CHORD ... Agreed Open
7 Mar 2013 Campbeltown budget position statement (agenda item 5)Decision Members agreed to note the report. (Reference: Report by Head of Economic Development and Strategic Transpor... Agreed Open
7 Mar 2013 Campbeltown berthing facility - highlight / progress report (agenda item 6)Decision Members agreed 1. To note the report. 2. That a proper plan needs to be developed to improve the fishermen’s... Agreed Open
13 Apr 2011 Highlight progress report - campbeltown thiThe Board agreed to note the report. (Ref: A report by Audrey Martin, dated 6 April 2011, submitted). Agreed Open
13 Apr 2011 Highlight progress report - kinloch road regenerationThe Board agreed to note the report. (Ref: A report by Joanne Casey, dated 4 April, 2011, submitted). Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies