Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 5 March 2014. Below is the council's own wording, with the papers it was decided on.
Decision Members agreed: 1. To note the progress of the Roads Reconstruction Programme for 2012-2015. 2. That a progress report on the Council’s contractual partner Breedon Aggregates would come to the MAKI April Area Committee meeting. (Reference: Report by the Acting Executive Director of Development and Infrastructure Services, dated 24 February 2014, submitted). Councillor John Semple joined the meeting by way of video Lync call from Campbeltown .
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Roads Reconstruction Capital Programme Total Provisional Budget £6,822,000 Allocation for 2014/15 , for Area based schemes Provisional Scheme List 2014/15 Current Total Programme Programme is subject to review following assessment of any winter £6,822,000 Estimate damage in 2013/14
Provisional Budget MAKI £2,114,000 Allocation for 2014/15 Current MAKI Total £2,114,000 Programme Estimate MID ARGYLL
WDM Scheme Route Location** Estimated Value Proposed Scheme Details*** Number* Preparation and surface 617822 A816 Kilmartin South £40,000 dressing Pre-Surface Dressing 599846 A816 Kilmartin Garage £68,000 preparation Preparation and surface 617834 B8025/C41 Tayvallich Kiells & Danna £185,000 dressing Edge Strengthening, Widening 599859 A816 Meadows £200,000 & Overlay Edge Strengthening, Widening, 617825 A816 South of Hill Park £100,000 Overlay & Safety Barrier Inlay surfacing & associated 617826 UC42 Redwell Park - Furnace £60,000 drainage. Footway Crossing Point - - Mid Argyll Footway's £45,000 Improvement Area Total £698,000 KINTYRE
WDM Scheme Route Location** Estimated Value Proposed Scheme Details*** Number*
Pre-Surface Dressing 617828 UC6 Skipness - Pier House £45,000 preparation
Pre-Surface Dressing 617838 UC34 East Gruinart £46,000 preparation - - Islay Footway's £50,000 Footway Resurfacing Area Total £711,000
NOTES * "WDM Scheme Number" is unique scheme reference and is not an indication of priority ** "Location" is a general descriptor and does not represent the exact scheme extents *** "Cost Estimate" and "Proposed Scheme Details" are subject to review (eg after detailed site investigation) Provisional Budget OLI £2,388,000 Allocation for 2014/15 Current OLI Total £2,388,000 Programme Estimate LORN
WDM Scheme Route Location** Estimated Value Proposed Scheme Details*** Number* 617857 UC46 Campbell Street £50,000 Inlay 617858 UC11 Dalrioch Road £115,000 Inlay 600472 UC72 Polvinster Road £125,000 Inlay 600488 A816 Oude Dam £40,000 Carriageway Re-surfacing Carriageway Widenening & 617859 A819 Kilchurn South £246,000 Overlay Edge Strengthening, Widening 600334 B845 Taynuilt - Kilchrennan £200,000 & Overlay 617860 Private Achaleven £57,000 Works Towards Adoption Carriageway Widenening & 600484 A816 Kilninver - Scammadale £110,000 Overlay - - Lorn Footway's £25,000 Footway Improvements Area Total £968,000 MULL
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.