Decision The Policy and Resources Committee - 1. Noted the project programme key dates for Dunoon Primary School at Paragraph 4.1 of the submitted report. 2. Noted the position in regard to the Stage 2 Submission from hubNorth Scotland Ltd in respect of the Dunoon Primary School project. The detail of which is referred to in Paragraph 4.2 of the submitted report. 3. Agreed – i. That the Council enter into the DBDA agreement for Dunoon Primary School, subject to the approval of earmarked sums of £750,000 to meet the anticipated additional funds, based on the financial position as set out at paragraph 4.3 of the submitted report. ii. That delegated authority be granted to the Executive Director – Customer Services, or his nominated representative, in consultation with the Executive Director - Community Services, the Head of Strategic Finance, the Council Leader, Depute Leader, and the Policy Lead for Education, to negotiate, agree and enter into any and all documentation in regard to contract close for the Dunoon Primary School Design and Build Direct Agreement (DBDA). iii. That the Executive Director – Customer Services, or his nominated representative, be authorised to sign on behalf of the Council any and all documentation in regard to contract close for the Dunoon Primary School DBDA. iv. That the Head of Strategic Finance be authorised as the named individual on behalf of the Council for the purpose of the insurance proceeds account to be opened in terms of the Project Agreement and the Insurance Proceeds Account Agreement. 4. Noted the Dunoon Primary School decant arrangements as set out in Paragraph 4.4 of the submitted report. (Reference: Joint report by Executive Director – Customer Services and Acting Executive Director – Community Services dated 25 May 2017, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides Members with progress on the Stage 2 Submission by hubNorth Scotland Ltd (hubNorth) to refurbish/part new build Dunoon Primary School.
1.2The formal Stage 2 Submission is expected to be received by the Council shortly. The key elements of the submission have been subject to review by the Councils’ schools redevelopment project team with support from the Council’s external legal advisors and the Scottish Futures Trust (SFT) and it is considered that the project is ready to progress to Contract Close.
1.3The Dunoon Primary School project, as it is a Design and Build Direct Agreement (DBDA), is not required to undergo a Key Stage Review (KSR) by the SFT.
1.4The key programme dates are set out in Paragraph 4.1.1 for the Dunoon Primary School project. Due to the restrictions in accommodation available during the construction phases, the Early Learning and Child Care (ELCC) children and staff and ESCAPE (After School Care Provision) will be decanted out of Dunoon Primary School to Kirn Primary ELCC and the Girl Guide Hall, Dunoon, respectively until the works are completed.
1.5Council’s Financial Provision The table below summarises the Council’s current projected financial position in relation to the Dunoon Primary School project. The Council’s project team has, in liaison with the SFT, continuously challenged hubNorth to deliver a cost effective project in respect of Dunoon Primary School.
Of course, the final project costs cannot be known until after the Stage 2 process and prior to Contract Close.
The Council’s project team are currently engaged in looking at further efficiencies that can be achieved to reduce costs or minimise the risk of further increases in costs.
Table 1 sets out the comparison of the anticipated Stage 2 cost to the current Council Capital Plan contribution for the Dunoon Primary School element of the New Schools project.
1 Table 1 - Comparison to Council Capital Plan £ Current Capital Plan for Dunoon Primary School 9,259,000 Anticipated Stage 2 costs for Dunoon Primary School 10,009,000 Anticipated additional costs 750,000
Based on the anticipated Stage 2 costs, the financial requirements for the Dunoon Primary School projects are £750k higher than the current Capital Plan. It is anticipated that these additional costs will be required to be met out with the current project budget. It has therefore been proposed that £750,000 be earmarked from 2016/17 favourable outturn to meet additional costs within 2017/18 and 2018/19.
Uplift in cost The uplift in costs for the Dunoon Primary School project are due to a number of factors: An extended construction programme due to the complexities of the phasing of the works in order to keep the primary school fully operational over a period of 2 years; The extended programme has a knock-on effect on commodity prices, in particular for materials not required until the Phase 2 works commence, and inflation risk; and Dealing with a large refurbishment project as well as a Listed building, that has added an element of risk inbuilt to the costs.
Construction Risk It should be noted that refurbishment of the West Wing and demolition of the East Wing bring additional risk in that the facility is an operational school and there is therefore limited scope to carry out intrusive surveys when scoping out the extent and cost of the works required.
There are, therefore, building elements within the refurbishment and demolition which may have inherent / latent defects or in which the precise amount and nature of rot or asbestos cannot be determined where additional cost risk may materialise. In that event, the cost risk would rest with the Council and would require additional funding. That is a matter that will be monitored closely during the construction period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.