Decision The Policy & Resources Committee - 1. Noted the updates on the Lorn Arc programme provided in the paper and the attached Appendices A through to I of the submitted report. 2. Noted the detail provided in para 4.4 of the submitted report and endorsed officers continuing to explore alternative funding models that would unlock the economic potential of Oban. 3. Agreed that the remaining available drawdown of £90k could be used as a contingency fund for Project 1. Lorn/ Kirk Road and noted that the Lorn Arc team would continue to manage Project 1. Lorn/ Kirk Road until the infrastructure (road and associated utilities) element of the project was delivered, and that once delivered, the project would be removed from the TIF programme. 4. Noted and endorsed that with regard to Project 3. Halfway House Roundabout, officers were working with the private sector on potential investment opportunities, and were presently awaiting feedback from private sector commercial agents. 5. Agreed to the development of a Strategic Development Framework for Project 4. Oban South and a report coming back to members in the first quarter of 2018. 6. Agreed to the development of an options appraisal for Project 5. North Pier Extension, which would be discussed with members in December. 7. Noted that with regard to Project 9. Oban Airport Access and Enablement, the Lorn Arc team were working with a range of Council Services to enable the work on this project to be completed. (Reference: Report by Executive Director – Development and Infrastructure Services dated 11 August 2017, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1On 8 May 2014, Scottish Government (“SG”) granted approval of the Lorn Arc Tax Incremental Financing (“TIF”) Business Case, thereby awarding the Argyll & Bute Council Lorn Arc project (The “Project”) TIF pilot status under the TIF pilot administration scheme. Selection of the Project as a pilot project provided SG and Scottish Futures Trust (“SFT”) with an opportunity to assess how the TIF model might operate on a smaller scale project in a rural setting. This was regarded as an innovative approach to exploring a potential funding mechanism for a range of economic development and infra structure projects that otherwise could not be delivered within available funding. The Project consisted of 9 individual projects across various locations, namely: Barcaldine, Oban Airport, Dunbeg Corridor, and Oban town centre.
Unfortunately, due to a number of changes, such as changes in the wider economy and the follow on effects for business in Argyll & Bute, the business case, as originally envisaged, has proved unviable. A re-modelling exercise indicates that in all cases (best to worst case scenarios), there is a deficit over the 25 year TIF period for the full potential capital spend programme of £14.74m. Whilst the full programme has been assessed as financially unviable, it should be noted that the current level of approved drawdown (£1.388m. of which £0.785m has actually been drawn down and spent), is forecast as being capable of being paid from TIF income over the life of the project based on the current NDR assumptions.
1.2Argyll & Bute Council submitted a letter (dated 3 February 2017), signed by the Leader of the Council and the Policy Lead for Sustainable Economic Growth, seeking confirmation from the SG of their willingness to engage with the Council to find alternative funding sources and/ or financing models for the delivery of the Lorn Arc programme and its associated social and economic outcomes. The Cabinet Secretary for Finance and the Constitution Derek MacKay replied (dated 26 February 2017), and confirmed that the affordability position of the Lorn Arc programme has been noted and advised that the SG remains committed to supporting Local Authorities and their use of innovative financing models to support inclusive growth.
1.3At the March 2017 Policy & Resource Committee meeting, the Lorn Arc team was authorised to engage with SG and the SFT to progress alternative solutions for the delivery for the Lorn Arc programme, in line with the Ministerial comments noted above. The team met with SFT in March 2017 and a Council TIF Programme Board was subsequently held in April 2017.
1.4The TIF Programme Board have noted that the likely solution for the programme would be the progression of a case for use of a growth model such as the Growth Accelerator or a Rural Growth Fund. Moving forward with an alternative funding model, however, requires a high degree of clarity and clear identification of the projects that would form the basis of that deal.
1.5Individual projects are being progressed in different ways. A briefing meeting (on Wednesday 9 August) for the Oban members included an overview of this. In addition to the detail within the main body of the paper, the updates provided at this meeting are included as appendices.
1.6Budget: Detailed below is the current budget position for both the revenue and capital approved budget allocations.
REVENUE £000s Total approved funds 1,607 Total project spend to date June 2017 464 Balance 1,143 CAPITAL £000s Total borrowing approved 1,388 Total project spend to date June 2017 785 Balance 603
1.7It is recommended that the Policy & Resources Committee:
1. Note the updates on the Lorn Arc programme provided in the paper and the attached Appendices A through to I.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.