Resolved
Decision The Environment, Development and Infrastructure Committee – 1. Noted that the modelling of flood protection options has been completed, with clear recommendations for solutions eligible for Scottish Government funding to be taken forward to the next stage of investigation, design and planning approvals. 2. Requested that the Council, as part of the budget process, allocate the project £127k of capital and consider the potential need for additional funding in 20/21 through to 22/23. 3. Acknowledged the final scheme would be subject to approval of Outline Business and Full Business cases, which are expected to be submitted late 2019 prior to tender and late 2020 prior to tender award respectively and if approved additional funding may be needed as indicated in table 1 within the submitted report. (Reference: Report by Executive Director – Development and Infrastructure Committee dated November 2018, submitted)