CAMPBELTOWN FLOOD PROTECTION SCHEME

Noted Committee 2 papers

AI summaryArgyll and Bute's environment committee noted progress on the £15.939m Campbeltown Flood Protection Scheme, with main construction complete and a £350k property flood resilience contract due to be tendered in 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedUpdates on land acquisition and final construction phases
Money£15.939m total scheme budget80% Scottish Government, 20% Argyll and Bute Council
What happens nextPFR procurement in 2026/27Tendering scheduled for Q2 and Q3 of 2026/27
Who it affectsCampbeltown residents and businessesFlood protection for 163 properties plus 24 PFR sites

What was decided

The committee noted project updates on land acquisition and the final construction phases of the Campbeltown Flood Protection Scheme. Report 3.1, P2

The committee noted the progress made towards completion of the scheme, whose main construction contract was certified complete on 10 May 2024. Report P3, P10

Why

The report is a project update covering construction completion, remaining defects, property flood resilience procurement, land acquisition, and financial position. Report 4.0, P5, P10, P11

The main contract was awarded to specialist contractor Dawson WAM and construction ran from September 2022 to May 2024. Report P9, P10

The scheme includes four main components: Millknowe Flood Storage Area Reservoir, Dalaruan Culvert upgrade, Burnside Surface Water Management and Meadows Surface Water Management. Report P7

What happens next

The contractor is programming a schedule of remaining remedial works, including delayed manhole cover repairs, to close out the defects register. Report P11, P12, P13

Property Flood Resilience measures for 24 properties will be tendered in Q2 and Q3 of 2026/27, with two drop-in sessions planned for the proprietors. Report P14, P15

A dedicated Campbeltown Potentially Vulnerable Area web page is being developed by the Infrastructure Design team to communicate scheme scope and reporting channels. Report P38, P39, P40

The money

  • £15.939m Total scheme budget (excludes PFR) Report P18, 6.2
  • £15.215m Original project budget Report P18
  • £724k Additional funding for Burnside Square enhancements and contract adjustments Report P18
  • £13.535m Final committed value of main construction contract Report P22
  • £0.842m Increase over original main contract value Report P22
  • £0.230m Burnside Square betterment works Report P23
  • £350k Allocation for Property Flood Resilience works Report P16, P18
  • £14,991,060 Spend to date at 6th May 2026 Report P18

Options considered

  • Chosen: Note project updates and progress. Officer recommendation to update committee on land acquisition and construction phases Report 3.1, P2, P3

Implications

  • Financial: All scheme costs are currently committed and accounted for within the current capital plan; the £350k PFR allocation will be reviewed on receipt of tender returns in 2026/27. Report P16, P18, 6.2, 6.6
  • Legal: Land access was secured using statutory powers under the Flood Risk Management (Scotland) Act 2009; several compensation settlements remain outstanding through the Council's Estates Team. Report P6, P29, P30, 6.3
  • Climate: The scheme is described as a key climate adaptation project providing long-term resilience against more frequent extreme weather events. Report 5.1, 6.7
  • Equalities: The scheme targets areas of high social vulnerability including Millknowe Road, Saddell Street and Longrow, and protects emergency services, Kinloch Park and listed buildings in the Conservation Area. Report 6.8, P53
  • Risk: The primary remaining risk is the final tender cost of the PFR works; the main contract remains open until all defects are rectified. Report P13, 6.6

Who and where

  • Residents and businesses in Campbeltown at risk of flooding Report P7, 6.8
  • 24 properties identified for Property Flood Resilience measures Report P14, P15
  • Emergency services (Police and Fire Stations) protected by the scheme Report P53
  • Landowners subject to ongoing compensation negotiations Report P29, P30

Timeline

  • 5 December 2019: EDI Committee confirmed the Campbeltown Flood Protection Scheme with modifications Report P5
  • 28 January 2020: Council requested deemed planning permission from Scottish Ministers Report P6
  • September 2022: Main construction works commenced Report P10
  • 10 May 2024: Main works contract certified complete Report P10
  • April 2026: Site walkover to review final defects register Report P11
  • 6th May 2026: Date of financial position summary Report P18
  • Q2 and Q3 of 2026/27: PFR procurement scheduled Report P14
  • June 2026: Report submitted to EDI Committee Report P60

Plain English for the jargon

  • CFPS: Campbeltown Flood Protection Scheme
  • PFR: Property Flood Resilience, measures installed at individual properties
  • PVA: Potentially Vulnerable Area, a designation used in Scottish flood risk planning
  • BCR: Benefit-Cost Ratio, used to appraise whether scheme benefits justify costs
  • FSA: Flood Storage Area, an area that temporarily holds floodwater
  • EDI Committee: Environment, Development and Infrastructure Committee of Argyll and Bute Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Decision The Environment, Development and Infrastructure Committee noted: 1. the project updates provided regarding land acquisition and final construction phases; and 2. the progress made towards the completion of the Campbeltown Flood Protection Scheme. (Reference: Report by Executive Director with Responsibility for Roads and Infrastructure, dated June 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Recommendations

3.1It is recommended that the Environment, Development and Infrastructure Committee:

a) Consider the project updates provided regarding land acquisition and final construction phases; and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAMPBELTOWN FLOOD PROTECTION SCHEMEReport 341 KB DownloadRead as text
PDF
CFPS: Appendix 1 (002)Appendix 331 KB Download

At this meeting

Whole meeting

Who was there

13 of 20 attended
IP
Councillor Iain PatersonMember, apologies
JS
Julieann SmallSecretary, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, present
GH
Councillor Graham HardieMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainMember, present
JL
Councillor Jim LynchMember, present
TM
Councillor Tommy MacPhersonMember, apologies
IM
Councillor Ian MacQuireMember, present

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CAMPBELTOWN FLOOD PROTECTION SCHEMEThis decision
  2. Campbeltown flood prevention schemeNoted
  3. Campbeltown flood protection schemeNoted
  4. Campbeltown flood protection schemeApproved
  5. Campbeltown flood prevention schemeAgreed
  6. Campbeltown flood protection schemeNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies