Resolved
Decision The Council noted the contents of the financial summary. (Ref: Report by the Head of Strategic Finance dated 27 June 2019, submitted)
Argyll and Bute Council noted this item on Thursday 27 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Council noted the contents of the financial summary. (Ref: Report by the Head of Strategic Finance dated 27 June 2019, submitted)
1.1This provides an update on the position of the capital budget as at 31st March 2019. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
1.2Financial Position:
• Outturn for 2018-19 – outturn net expenditure for the full financial year is £24,966k compared to an annual budget of £29,220k (adjusted for previously agreed slippages, accelerations and virements) giving rise to an underspend for the year of £4,254k (14.6%). • Total Capital Plan – the forecast total net project costs on the total capital plan are £308,035k compared to a total budget for all projects of £307,833k giving rise to a forecast overspend for the overall capital plan of £202k (0.07%). The forecast overspend is within the capital programme tolerances and requires no corrective action to be taken as the actual spend will only be determined when the projects are completed.
1.3Project Delivery:
• Asset Sustainability – Out of 135 projects there are 120 projects (89%) on track and 15 projects (11%) off track but recoverable. • Service Development - Out of 24 projects there are 19 projects (79%) on track, 4 projects (17%) off track but recoverable and 1 project (4%) off track. • Strategic Change – Out of 34 projects there are 26 projects (76%) on track, 5 projects (15%) off track but recoverable and 3 projects (9%) off track.
1.4The Council has received £3,023k of capital receipts up to 31st March 2019 against a budget of £3,100k (97.5%).
Page 1 of 8 ARGYLL AND BUTE COUNCIL COUNCIL STRATEGIC FINANCE 27 June 2019 CAPITAL BUDGET MONITORING REPORT – 31st MARCH 2019 ,
2 INTRODUCTION 2.1 This provides an update on the position of the capital budget as at 31st March 2019. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects. .
2.2Financial Position:
• Outturn for 2018-19 – outturn net expenditure for the full financial year is £24,966k compared to an annual budget of £29,220k (adjusted for previously agreed slippages, accelerations and virements) giving rise to an underspend for the year of £4,254k (14.6%). • Total Capital Plan – the forecast total net project costs on the total capital plan are £308,035k compared to a total budget for all projects of £307,833k giving rise to a forecast overspend for the overall capital plan of £202k (0.07%). The forecast overspend is within the capital programme tolerances and requires no corrective action to be taken as the actual spend will only be determined when the projects are completed.
2.3Project Delivery:
• Asset Sustainability – Out of 135 projects there are 120 projects (89%) on track and 15 projects (11%) off track but recoverable. • Service Development - Out of 24 projects there are 19 projects (79%) on track, 4 projects (17%) off track but recoverable and 1 project (4%) off track. Strategic Change – Out of 34 projects there are 26 projects (76%) on track, 5 projects (15%) off track but recoverable and 3 projects (9%) off track.
2.4The Council has received £3,023k of capital receipts up to 31st March 2019 against a budget of £3,100k (97.5%).
3 RECOMMENDATIONS 3.1 Consider the contents of this financial summary.
Page 2 of 8 4 OUTTURN FINANCIAL POSITION 2018-19 4.1 Overall Position
Outturn net expenditure for the full financial year is £24,966k compared to an annual budget of £29,220k giving rise to an underspend for the year of £4,254k (14.6%).
4.2Project/Department Position
The table shows the forecast expenditure and budget for the year by project type and department:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Monitoring Report Year End Report 2018-19Report | 2.8 MB | DownloadRead as text |
Follow Argyll and Bute Council at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... | Decided | Open |
| 23 Sep 2026 | Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... | Noted | Open |
| 23 Sep 2026 | Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... | Noted | Open |
| 23 Sep 2026 | Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... | Noted | Open |
| 23 Sep 2026 | Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.