CAPITAL BUDGET MONITORING REPORT - 31 MARCH 2023

Noted Committee 1 paper

Argyll and Bute Council noted this item on Thursday 29 June 2023. Below is the council's own wording, with the papers it was decided on.

Item8d

Resolved

Decision The Council noted the contents of the submitted report and the financial summaries as detailed in Appendix 8 to the report. (Reference: Report by Section 95 Officer dated 21 June 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Council

Executive summary

1.1This report provides an update on the position of the capital budget as at 31 March 2023. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.

1.2Financial Position:

 Outturn for 2022-23 – actual net expenditure for the full financial year is £30,215k compared to an annual budget of £33,374k giving rise to an underspend for the year of £3,159k (9.47%). This variance is after previously agreed slippage of £47,164k that has been approved throughout 2022-23.  Total Capital Plan – forecast total net project costs on the total capital plan are £206,689k compared to a total budget for all projects of £206,689k. No variance is projected.

1.3Project Delivery:

 Asset Sustainability – Out of 95 projects there are 49 projects (52%) on track and 46 projects (48%) off track but recoverable.  Service Development - Out of 42 projects there are 22 projects (52%) on track and 20 projects (48%) off track but recoverable.  Strategic Change – Out of 27 projects there are 3 projects (11%) on track and 24 projects (89%) are off track but recoverable.

1.4The Capital Programme is funded by various income streams as detailed in Appendix 4.

1.5Originally the Council was projecting £1,387k of capital receipts this financial year which was then revised to £500k. Actual receipts of £560k have been received. The estimated level of receipts for future years will be kept under review as market conditions change, as will values following due diligence undertaken by prospective purchasers on the condition of asset. ARGYLL AND BUTE COUNCIL COUNCIL

FINANCIAL SERVICES 29 JUNE 2023

CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2023

2.0INTRODUCTION

2.1This report provides an update on the position of the capital budget as at 31 March 2023. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.

2.2Following the decision at Policy and Resources Committee on 9 December 2021, the Rothesay Pavilion project was put on pause whilst potential funding options were being considered. At the budget meeting in February 2023 additional funding was allocated to this project which will allow the project to progress towards success by supporting completion of certain work stages. The financial information included within this report excludes amounts relating to Rothesay Pavilion, however now that a programme of works has been defined this project will be added back on to the capital programme in financial year 2023-24.

2.3A £1m cost pressure was identified during 2021-22 in relation to repairs to the A884 Ardbeg Sea Wall, where severe storm damage resulted in failure of the sea wall on Bute. Emergency works were carried out and a permanent solution is currently being developed. Additional funding of £1m was allocated for this purpose at the Council meeting on 24 February 2022 however there remains a risk that costs will exceed this.

2.4The impact of the pandemic along with the UK exit from the European Union, the Russian invasion of Ukraine and sanctions on Russian owned entities has seen significant price increases as well as disruptions to the supply chain and longer lead in times. The increased rate of inflation impacts costs such as energy prices, labour, packaging and transport. These all have an effect on the overall contract price and make it extremely challenging to manage expenditure and the availability of supply.

As a result of this it should be noted that there are likely to be other significant financial impacts which are not quantifiable at this stage, as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL BUDGET MONITORING REPORT: 31 MARCH 2023Report 9.5 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

35 of 39 attended
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
JB
Councillor Jan BrownMember, present
MC
Councillor Math Campbell-SturgessMember, present
GC
Councillor Garret CornerMember, present
MC
Councillor Maurice CorryChair, present
RC
Councillor Robin CurrieMember, present
AF
Councillor Audrey ForrestMember, present
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
DH
Councillor Daniel HampseyMember, present
GH
Councillor Graham HardieMember, present

All 39 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CAPITAL BUDGET MONITORING REPORT - 31 MARCH 2023This decision
  2. Capital Budget Monitoring - year ending 31 March 2026Noted
  3. Capital Budget Monitoring Report - 31 March 2024Noted
  4. Capital budget monitoring report - 31 march 2022Noted
  5. Capital budget monitoring report - 31 march 2021Noted
  6. Capital Budget Monitoring Report Year End Report 2019-20Noted

More from Argyll and Bute Argyll and Bute Council

All decisions
MeetingDecisionOutcome
23 Sep 2026 Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... Decided Open
23 Sep 2026 Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... Noted Open
23 Sep 2026 Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... Noted Open
23 Sep 2026 Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... Noted Open
23 Sep 2026 Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... Decided Open