Decision The Council – 1. noted the content of the submitted report and the financial summaries as detailed at Appendix 6; and 2. approved the proposed changes to the capital plan as detailed at Appendix 2. (Reference: Report by Section 95 Officer dated 13 June 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides an update on the position of the capital budget as at 31 March 2024. The report provides information on the financial position in respect of the capital plan and the performance in terms of delivery of capital plan projects.
1.2Financial Position:
Outturn for 2023-24 – actual net expenditure for the full financial year is £37,860k compared to an annual budget of £33,166k giving rise to an overspend for the year of £4,694k (14.15%). This variance is after previously agreed slippage of £27,837k that has been approved throughout 2023-24 therefore budgets will be re-profiled accordingly. Total Capital Plan – forecast total net project costs on the total capital plan are £219,771k compared to a total budget for all projects of £219,771k. No variance is projected.
1.3Project Delivery:
Asset Sustainability – Out of 96 projects there are 84 projects (87%) on track and 12 projects (13%) off track but recoverable. Service Development - Out of 44 projects there are 40 projects (91%) on track and 4 projects (9%) off track but recoverable. Strategic Change – Out of 29 projects there are 19 projects (66%) on track and 10 projects (34%) off track but recoverable.
1.4The Capital Programme is funded by various income streams as detailed in Appendix 3. Additional funding has been added for 2023-24 CFCR, STTS Income for Roads, Scottish Government Grants for Bus Partnership Fund and Road Safety Improvement Fund, third party contributions from Live Argyll and HSCP, Crown Estates Allocation, Strategic Housing Fund contribution and additional allocation of Rural Growth Deal funding.
1.5Originally the Council was projecting £1,195k of capital receipts this financial year which was then revised to £484k. Actual receipts of £622k have been received which will reduce the income target for 2024-25. The estimated level of receipts for future years will be kept under review as market conditions change; as will values following due diligence undertaken by prospective purchasers on the condition of asset. ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 27 JUNE 2024
CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2024
2.0INTRODUCTION
2.1This report provides an update on the position of the capital budget as at 31 March 2024. The report provides information on the financial position in respect of the capital plan and the performance in terms of delivery of capital plan projects.
2.2Following the decision at Policy and Resources Committee on 9 December 2021, the Rothesay Pavilion project was put on pause whilst potential funding options were being considered. At the budget meeting in February 2023 additional funding was allocated to this project which will allow the project to progress towards success by supporting completion of certain work stages. Further information regarding the progress of this project will be reported during 2024-25 once tenders have been received and finalised. The financial information included within this report includes amounts relating to Phase 1 only of the Rothesay Pavilion project.
2.3Surveys have been completed in the Councils Learning Estates in relation to RAAC with only 1 building confirmed as having it present with steps underway for its removal. This will include a decant of the students for approximately 9 months plus total removal and replacement of the roof during 2024-25. Funding of £3m was considered as part of the 2024-25 budget setting process and additional funding was allocated as agreed at the Council meeting on 22nd February 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.