Decision The Council – 1. Noted the contents of the report and the financial summaries as detailed at Appendix 6. 2. Approved the proposed virements at Appendix 3 and the roll forward of any over or underspends in relation to expenditure and income as part of the year end process. (Ref: Report by Section 95 Officer dated 6 June 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides an update on the position of the capital budget as at 31 March 2022. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
1.2Financial Position:
• Outturn for 2021-22 – actual net expenditure for the full financial year is £24,831k compared to an annual budget of £31,012k giving rise to an underspend for the year of £6,181k (19.9%). • Total Capital Plan – forecast total net project costs on the total capital plan are £194,796k compared to a total budget for all projects of £194,701k giving rise to a forecast overspend for the overall capital plan of £95k (0.05%).
1.3Project Delivery:
• Asset Sustainability – Out of 112 projects there are 63 projects (56%) on track, 49 projects (44%) off track but recoverable and 0 projects off track (0%). • Service Development - Out of 42 projects there are 23 projects (55%) on track, 19 projects (45%) off track but recoverable and 0 projects (0%) off track. • Strategic Change – Out of 26 projects there are 8 projects (31%) on track, 18 projects (69%) off track but recoverable and 0 projects (0%) off track.
1.4The Capital Programme is funded by various income streams as detailed in Appendix 4. Additional funding allocated since the last report relates to Cycling, Walking, Safer Routes, Town Centre Fund and Campbeltown Flood Scheme.
1.5Due to the Covid-19 outbreak there has been a reduction in anticipated capital receipts in 2021-22 however this appears to be a delay rather than a permanent reduction and over the life of the entire capital programme there is no overall impact. The position will continue to be monitored on an ongoing basis. ARGYLL AND BUTE COUNCIL COUNCIL
FINANCIAL SERVICES 30 JUNE 2022
CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2022
2.0INTRODUCTION
2.1This report provides an update on the position of the capital budget as at 31 March 2022. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
2.2Following the decision at Policy and Resources Committee on 9 December 2021, the Rothesay Pavilion project is on pause whilst potential funding options are being considered. The financial information included within this report therefore now excludes amounts relating to Rothesay Pavilion however for your information actual expenditure during the year was £718k.
2.3A £1m cost pressure was identified during the year in relation to repairs to the A884 Ardbeg Sea Wall, where severe storm damage resulted in failure of the sea wall on Bute. Emergency works were carried out and a permanent solution is currently being developed. Additional funding of £1m was allocated for this purpose at the Council meeting on 24 February 2022 however there remains a risk that costs will exceed this. It was agreed at Environment, Development and Infrastructure Committee on 2 June 2022 that the Chair would approach the Scottish Government with a view to securing additional resources to support the scheme.
2.4Project Managers were asked to identify specific Covid-19 impacts on the capital programme. At the budget meeting on 25 February 2021, the Council agreed to provide £2.5m of funding and following agreement at the Policy and Resources Committee on 14 October 2021, this, plus a further £0.146m, was added to the capital programme.
Furthermore, at the budget meeting on 24 February 2022, an additional £3.9m was set aside for future capital contract increases. This includes up to £1.2m for Campbeltown Flood Scheme, the final costs of which are estimated to be £15.215m. The Scottish Government will fund 80% of scheme costs with the Council expected to contribute an estimated £3.043m.
It should be noted that there are likely to be other significant financial impacts, as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.