Decision The Council noted the contents of the report, the financial summaries as detailed in Appendix 7, approved the roll forward of any over or underspends in relation to expenditure and income as part of the year and process and approved the proposed virement requests in Appendix 3. (Ref: Report by Section 95 Officer dated 1 June 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This provides an update on the position of the capital budget as at 31 March 2021. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
Variances in the financial position have been split to show the value relating to the impact of the COVID-19 pandemic.
1.2Financial Position:
• Outturn for 2020-21 – net expenditure for the full financial year is £16,176k compared to an annual budget of £16,608k giving rise to an underspend for the year of £432k (2.6%). • Total Capital Plan – the forecast net project costs on the total capital plan are £172,310k compared to a total budget for all projects of £172,098k giving rise to a forecast overspend for the overall capital plan of £212k (0.1%).
1.3It should be noted that the figures reported in relation to Rothesay Pavilion reflect the best case financial scenario, however there is a risk that this is not achieved in which case Prudential Borrowing would need to be taken out to cover any additional costs as agreed at the budget setting meeting in February 2021. The Service will ensure that all mitigating measures are taken to reduce any requirement for borrowing.
In addition, the Council have received notification of potential additional costs in relation to the Helensburgh Waterfront Development project as a direct consequence of COVID-19. Negotiations with the contractor are ongoing to come to an acceptable solution but as the position is not certain at this stage, the project forecast has not been increased.
Project Managers are working to identify underspends elsewhere within the capital programme to fund overspends.
1.4Project Delivery:
• Asset Sustainability – Out of 92 projects there are 77 projects (85%) on track, 15 projects off track but recoverable (16%) and 0 projects off track (0%). • Service Development - Out of 34 projects there are 28 projects (82%) on track, 5 projects off track but recoverable (15%) and 1 project off track (3%). • Strategic Change – Out of 29 projects there are 22 projects (76%) on track, 6 projects off track but recoverable (21%) and 1 project off track (3%). 1.5 Funding:
The Capital Programme is funded by various income streams as detailed in Appendix 4. Changes during March 2021 relate to adjustments to externally funded projects including Cycling, Walking and Safer Routes, SPT Bus Infrastructure, Dunoon CHORD, Digital Inclusion and Hermitage Park.
Due to the COVID-19 outbreak it was anticipated that there would be a significant impact on capital receipts in 2020-21. It is hoped this will correct itself over the subsequent two years and therefore overall there would be no impact to the longer term capital programme. The position will continue to be monitored on an ongoing basis, however there has been a delay of £666k in capital receipts during 2020-21 as a result of this. ARGYLL AND BUTE COUNCIL COUNCIL FINANCIAL SERVICES 24 JUNE 2021 CAPITAL BUDGET MONITORING REPORT – 31 MARCH 2021 ,
2 INTRODUCTION 2.1 This provides an update on the position of the capital budget as at 31 March 2021. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
Variances in the financial position have been split to show the value relating to the impact of the COVID-19 pandemic.
3 RECOMMENDATIONS 3.1 Note the contents of this report, the financial summaries as detailed in Appendix 7, approve the roll forward of any over or underspends in relation to expenditure and income as part of the year end process and approve the proposed virement requests in Appendix 3. 4 OUTTURN FINANCIAL POSITION 2020-21 4.1 Overall Position
Actual net expenditure for the full financial year is £16,176k compared to an annual budget of £16,608k giving rise to an underspend for the year of £432k (2.6%).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.