ROADS CAPITAL RECONSTRUCTION PROGRAMME 2020/21

Agreed Committee 2 papers

Environment, Development and Infrastructure Committee agreed this item on Thursday 5 March 2020. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision The Environment, Development and Infrastructure Committee – 1. Endorsed the proposed programme of capital works for 2020/21. 2. Agreed that the details of each area committee’s programme would be forwarded on to individual Elected Members and that updated to Area Committees would be provided as the programme progresses. (Reference: Report by Interim Executive Director with responsibility for Roads and Infrastructure dated March 2020, and Appendix 5 dated 4 March 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Executive summary

1.1The Roads Reconstruction Programme has been structured in line with the Roads Asset Management and Maintenance Strategy. The focus has been to arrest the rate of decline and provide an overall improvement in condition as has been demonstrated in the Annual Status and Options Report. In previous years this has been achieved through the delivery of a mix of carriageway resurfacing, edge strengthening, patching/surface dressing and in-situ road surface recycling. These treatments have been designed to seal the road to stop the ingress of water, improve ride quality and reduce the amount of reactive repairs. This has resulted in an overall improvement in road condition. Without these works and investment there would have been a significant deterioration in condition.

1.2Attached to this report is a draft programme for roads reconstruction and footway schemes for 2020/21. This programme has been designed using the Road Condition Index (RCI) which is produced by the national road condition survey data. This survey information is used by officers to determine a programme. In addition to the RCI data, information such as road traffic collisions, known development, activities such as timber harvesting and skid condition (of the carriageways surface) which is measured by a separate survey are also considered together with information brought from Elected Members, community groups and stakeholders. This information is considered at officer level when appropriate engineering judgement is also applied to ensure that maximum benefit can be derived from the available investment.

1.3The proposed capital works programme as presented is based on carriageway condition late autumn/early winter. With the effect of winter this programme may need to be adjusted to ensure that any investment is targeted accordingly. Should any changes be required to the programme, the Policy Lead and Depute Policy Lead will be notified prior to any amended area scheme list being sent out to local members.

1.4It is recommended that the Environment, Development and Infrastructure Committee endorses the proposed programme of capital works for 2020/21, and also agrees that details of each area committee’s programme will be forwarded on to individual Elected Members, updates to area committees will be provided as the programme progresses.

1 ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE

ROADS AND INFRASTRUCTURE SERVICES 5 MARCH 2020

ROADS CAPITAL RECONSTRUCTION PROGRAMME 2020/21

2.0INTRODUCTION

2.1This report provides details of the proposed roads reconstruction programme for 2020/21.

Recommendations

3.1That the Committee endorses the proposed programme of capital works for 2020/21, and also agrees that details of each area committee’s programme will be forwarded on to individual Elected Members, updates to area committees will be provided as the programme progresses.

4.0DETAILS

4.1Note for committee: The appendices attached to this report are working drafts, there will be some slight adjustments in terms of scheme values etc. to allow the budget to balance.

4.2The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and in-situ road surface recycling, which follow the principles set out within the Roads Asset Management Plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Capital Roads Reconstruction Programme 2020-21Appendix 5 162 KB Download
PDF
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2020/21Report 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 18 attended
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
RC
Councillor Robin CurrieChair, present
DK
Councillor Donald KellyMember, apologies
DK
Councillor David KinniburghMember, present
DM
Councillor Donald MacMillan BEMMember, present
RM
Councillor Roderick McCuishMember, apologies
SJ
Councillor Sir Jamie McGrigorMember, apologies
JM
Councillor Jean MoffatMember, present
AM
Councillor Aileen MortonMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ROADS CAPITAL RECONSTRUCTION PROGRAMME 2020/21This decision
  2. Roads capital reconstruction programme 2026-27 - update reportAgreed
  3. Roads capital reconstruction programme 2026-27Agreed
  4. Roads capital reconstruction programme - 2025/26Agreed
  5. Roads capital reconstruction programme 2024/25 - update reportAgreed
  6. Roads capital reconstruction programme 2024/25Agreed

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies