ELECTRIC VEHICLE CHARGING STRATEGY - PROGRESS AND PROPOSED DELIVERY MODEL

Noted Committee 3 papers

AI summaryArgyll and Bute Council approved a hub first charging programme, allocating £1.033 million EVIF funding and delegating smaller Phase 2 sites to Area Committees. [D] A further report is due in March 2026. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPhase 1 hubs, then local Phase 2 spokes. [D]
Money£1.033 million allocated [D]£100,000 repair, £100,000 contingency, £833,000 infrastructure. [D]
What happens nextMarch 2026 report due [D]Costing exercise must be complete. [D]
Who it affectsResidents, visitors and businesses [P1]Public charging expands across Argyll and Bute. [P1]

What was decided

The committee noted implementation progress and approved Phase 1 hubs in key towns and island centres, followed by local Phase 2 spokes. Report P1, P13

It approved £1.033 million of EVIF funding: £100,000 for maintenance and repair, £100,000 for connection and construction cost contingency, and £833,000 for new infrastructure. Report P4

Residual Phase 2 funding was delegated to Area Committees: Bute & Cowal 19.78%, Helensburgh & Lomond 10.67%, Mid Argyll, Kintyre & Islay 32.71%, and Oban, Lorn & the Isles 36.84%. The committee noted work on a cross footway charging policy, migration to Scottish Power / Fuuse, and reviews of tariffs and maintenance arrangements. Another report is due in March 2026 after the costing exercise. Report P6, P7, P8

Why

Confirmed external funding required officers to revise the approach so its scale and pace matched available resources and investment maximised public benefit. Report P1

Hubs concentrate initial investment on high use locations, while spokes maintain connectivity and allow local flexibility. Report P1

Site choices consider population and visitor demand, seasonal tourism, electricity network capacity and connection feasibility, accessibility, cost efficiency and existing private provision. Report 4.0, P22, P25

What happens next

Officers will finalise site selection and connection estimates with Urban Foresight and report progress when complete. A further report is due in March 2026. Report 5.0, P8

Delivery will move from planning to implementation in 2026, with Phase 1 hubs followed by Phase 2 spokes. Report P1

The proposed cross footway approach is short term ramped cable protectors, then a 2026 below ground ducting pilot, then a leasing and cost recovery adoption process. Work will also continue on the back office migration, tariffs and maintenance. Report 4.0, P7

The money

  • £1.033 million Confirmed EVIF funding allocation Report P3
  • £100,000 Maintenance and repair of the existing network Report P4
  • £100,000 Contingency for connection and construction cost fluctuations Report P4
  • £833,000 New charging infrastructure Report P4
  • £1.65 million Estimated cost of the original 55 site plan Report 4.0
  • £0.70 per kWh Current charging price, still under review Report 4.0, P7

Options considered

  • Chosen: Deliver hubs first, then local spokes. This targets high impact locations with strong potential use while maintaining route coverage and local access. Report P1
  • Rejected: Continue with the original 55 site plan. The confirmed funding was below the estimated cost, so a targeted phased approach was required. Report 4.0, P1
  • Chosen: Use central hubs instead of several smaller chargers. The report says this offers improved reliability, faster charging and easier maintenance. Report 4.0
  • Chosen: Let Area Committees select Phase 2 spokes. This allows local input and flexibility within a consistent strategic framework. Report P1

Implications

  • Financial: £1.033 million is secured through EVIF, with separate allocations for repair, contingency and new infrastructure. Report P4, 6.0
  • Climate: The programme supports low carbon transport, the move to net zero and carbon reduction goals. Report P1, 6.0
  • Legal: All works must comply with roads, procurement and accessibility legislation. Report 6.0
  • Risk: Delivery faces electricity network costs and availability, private provision overlap, staffing limits, transition reliability and construction cost volatility. Report 4.0
  • Staffing: One officer currently manages the network, and officer capacity and resourcing will be reviewed as it expands. Report 4.0
  • Financial: The £0.70 per kWh charging price is under review to balance affordability and cost recovery. Report 4.0, P7
  • Other: Area Committees can prioritise Phase 2 spokes within their allocated shares under a consistent strategy. Report P1
  • Other: Cross footway policy development will include engagement with disability and access groups. Report 4.0

Who and where

  • Residents, visitors and businesses Report P1
  • Residents without private driveways Report 4.0
  • People needing accessible charging provision Report 4.0
  • Rural communities and smaller settlements Report P1
  • Island communities Report P1
  • Local Area Committees
  • Private charging operators Report 4.0
  • Existing users of the Council's charging network Report 4.0

Timeline

  • In 2022: The Council approved its Electric Vehicle Charging Strategy. Report 4.1
  • Between 2023 and 2024: Officers developed an expansion plan identifying 55 potential sites. Report 4.0
  • In August 2025: The Council secured £1.033 million through EVIF. Report 4.0
  • 13 November 2025: The officer report was dated. Report P37
  • 18TH DECEMBER 2025: The committee considered the charging strategy report. Report P9
  • Phase 1: The report proposes hubs at Helensburgh, Oban, Dunoon, Lochgilphead, Campbeltown, Bowmore, Craignure and Rothesay. Report P13, P27, P28, P29, P30, P31, P32, P33, P34
  • 2026: Implementation is due to begin, including a proposed below ground ducting pilot for cross footway charging. Report P1, 4.0
  • March 2026: A further report will return to committee after costing work. Report P8

Plain English for the jargon

  • Electric Vehicle Charging (EVC): Public charging infrastructure for electric vehicles.
  • EVIF: The Electric Vehicle Infrastructure Fund, which awarded the Council's funding.
  • Hub: A well equipped site with several chargers in a key town or island centre.
  • Spoke: A smaller site, usually with one or two chargers, serving rural communities.
  • Cross footway charging: Charging at home across a footway for residents without private driveways.
  • Back office system: The Scottish Power / Fuuse system used to manage the Council's charging network.
  • Area Committees: Local committees that can select and prioritise Phase 2 spokes within allocated shares.
  • Phase 1 and Phase 2: Phase 1 delivers strategic hubs. Phase 2 delivers smaller local spokes.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

Decision The Environment, Development and Infrastructure Committee: 1. noted the progress on the implementation of the Electric Vehicle Charging Strategy; 2. approved the proposed “hub-first” delivery methodology, whereby key town and island hubs will be delivered as Phase 1 of the programme, followed by local “spoke” installations in Phase 2; 3. approved the proposed allocation of the £1.033 million EVIF funding, comprising: • £100,000 for maintenance and repair of the existing network, • £100,000 as a contingency to address connection and construction cost fluctuations, and • £833,000 for the delivery of new infrastructure; 4. agreed that the residual budget for Phase 2 be delegated to local Area Committees on the following basis: • Bute & Cowal – 19.78% • Helensburgh & Lomond – 10.67% • Mid Argyll, Kintyre & Islay – 32.71% • Oban, Lorn & the Isles – 36.84%; 5. noted the ongoing parallel workstreams relating to the development of a cross-footway charging policy, the migration of the back-office system to Scottish Power / Fuuse , and the continued review of tariffs and maintenance arrangements; and 6. noted that a further report would come back to committee in March 2026 once the costing exercise, which is currently underway, is complete. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated 13 November 2025, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee, 10 pages

Executive summary

This report provides Members with an update on the delivery of the Council’s Electric Vehicle Charging (EVC) Strategy and seeks approval for a revised approach to delivery now that external funding has been confirmed. The Strategy, approved by the Council in 2022, set out a vision and a strategic basis to expand the availability of public electric vehicle charging (EVC) infrastructure throughout Argyll and Bute. Its purpose was to provide fair and convenient access for residents, visitors and businesses, supporting both the transition to low-carbon transport and the Council’s wider climate objectives. Following confirmation that the Council has now been awarded £1.033 million through the national Electric Vehicle Infrastructure Fund (EVIF), officers have reviewed the existing strategy and expansion plan to ensure that proposals for the scale and pace of delivery reflect the resources available and that investment achieves the greatest possible public benefit. It is therefore proposed that the Council alter its strategy to include an additional layer – a “hub-first” delivery model, concentrating initial investment on a network of well-equipped, high-use charging hubs in key towns and island centres. This would then be followed by a second phase of smaller “spoke” installations across smaller settlements/in other key areas, maintaining connectivity and enabling local flexibility, with the latter element being delegated to local Area Committees. The report also provides updates on related workstreams, including the transition to the new Scottish Power back-office system and the development of a local cross-footway charging approach to support safe home charging. Overall, the report seeks Member approval for the proposed revised delivery methodology, funding allocation and next steps that will allow us to move from planning to implementation in 2026. RECOMMENDATIONS It is recommended that the Environment, Development and Infrastructure Committee: a) Note progress on the implementation of the Electric Vehicle Charging Strategy;

b) Approve the proposed “hub-first” delivery methodology, whereby key town and island hubs will be delivered as Phase 1 of the programme, followed by local “spoke” installations in Phase 2;

c) Approve the proposed allocation of the £1.033 million EVIF funding, comprising:

• £100,000 for maintenance and repair of the existing network, • £100,000 as a contingency to address connection and construction cost fluctuations, and • £833,000 for the delivery of new infrastructure;

d) Agree that the residual budget for Phase 2 be delegated to local Area Committees on the following basis:

• Bute & Cowal – 19.78% • Helensburgh & Lomond – 10.67% • Mid Argyll, Kintyre & Islay – 32.71% • Oban, Lorn & the Isles – 36.84%

e) Note the ongoing parallel workstreams relating to the development of a cross-footway charging policy, the migration of the back-office system to Scottish Power / Fuuse, and the continued review of tariffs and maintenance arrangements; and

f) Note that a further report will come back to committee in March once the costing exercise which is currently underway is complete. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE ROADS AND INFRASTRUCTURE 18TH DECEMBER 2025

ELECTRIC VEHICLE CHARGING STRATEGY – PROGRESS AND PROPOSED DELIVERY MODEL

2.0INTRODUCTION

2.1This report provides Members with an update on the delivery of the Council’s Electric Vehicle Charging (EVC) Strategy and seeks approval for a revised approach to delivery now that external funding has been confirmed.

Recommendations

It is recommended that the Environment, Development and Infrastructure Committee: a) Note progress on the implementation of the Electric Vehicle Charging Strategy;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ELECTRIC VEHICLE CHARGING STRATEGY: PROGRESS AND PROPOSED DELIVERY MODELReport 10 pages DownloadRead as text
PDF
EVC Appendix 1: EXPANSION LIST UPDATED DEC 2025Appendix 3 pages Download
PDF
EVC Appendix 2 Strategy.pptx UPDATED 28.10.25Appendix 19 pages Download

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. ELECTRIC VEHICLE CHARGING STRATEGY - PROGRESS AND PROPOSED DELIVERY MODELThis decision
  2. Electric vehicle charging strategy - progress and proposed delivery modelNoted
  3. Electric vehicle charging strategyNoted
  4. Electric vehicle charging strategy updateNoted
  5. Electric vehicle charging strategy updateAgreed
  6. Electric Vehicle Charging PointsNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies