UPDATE ON THE REVIEW OF PUBLIC AND SCHOOL TRANSPORT
NotedCommittee2 papers
AI summaryArgyll and Bute councillors agreed to keep current school and public transport delivery arrangements, accepting a Systra review finding this the most viable option, and backed an action plan to improve services.
Written from the decision and the officer reportPDF Pro
OutcomeNotedSystra review found current hybrid model most viable
Money£8.486mCurrent annual budget for school and public transport
What happens nextOfficers to implement action planContinue working with existing operators
Who it affects3,500 pupils at 78 schoolsPlus public transport users across the area
What was decided
The committee noted that the council's existing service delivery arrangements are currently the most viable option. Report 1.9, 3.1
The committee agreed officers continue to review service provision with contractors and the council's own team to ensure best value. Report 1.9
The committee agreed officers continue to implement the action plan identified in paragraph 5.5 of the report.
Why
The Systra review found the current network is already operating at the minimum viable size, and any further reductions would undermine economies of scale. Report P27
A municipal bus operation would need over £2m in start-up funding and face difficulties matching the economies of scale of established commercial operators. Report P23, P25
The council already operates a hybrid model, combining in-house and contracted delivery, which Systra advised is the most viable solution. Report P26, P27
What happens next
Officers will continue reviewing service provision with contractors and the in-house team for best value. Report 1.9
Officers will review the policy options set out in the report, including the Assistance with Travel Policy, the Statutory School Transport Provision Policy and the Privilege Rides Policy. Report P22
Officers will continue implementing the eight point action plan covering contract renewal, timetable coordination, integrated ticketing, and contingency planning for municipal operation.
The money
£8.486m Current annual budget for school and public transport Report 1.5
£5.394m Allocated to payments to transport operators Report 1.5
£0.876m Budget increase for 2025/26 following tender exercises Report 1.6
£0.400m Additional budget increase for 2026/27 Report 1.6
£0.046m Potential annual saving from removing Sunday bus services Report P19
£0.104m Potential annual saving from removing evening bus services Report P19
£0.289m Potential annual saving from removing Saturday bus services Report P19
£0.439m Potential annual saving from removing all weekend and evening services Report P19
£0.2m Cumulative savings from route optimisation over the last five years Report P20, 4.3
£2m Minimum start-up funding identified for a municipal bus operation
Options considered
Rejected: Do nothing and absorb cost pressures. Not viable; providing home to school transport is a legal requirement Report 4.3
Rejected: Reduce contract costs by cutting Sunday, evening or Saturday services. Would have major social and economic impacts, increase car dependency and carbon emissions, and undermine network viability Report P19
Rejected: In-house bus operation (municipal bus company). Would need over £2m start-up funding and could not match the economies of scale of existing commercial operators Report P23, P25
Chosen: Hybrid model (in-house and contracted delivery). Already in place; Systra advised this is the most viable solution Report P26, P27
Implications
Financial: Current budget is £8.486m, with recent increases of £0.876m for 2025/26 and £0.400m for 2026/27. Report 1.6
Legal: The council has a legal duty under the Education (Scotland) Act 1980 to make arrangements for school transport, and must meet the needs of children with Additional Support Needs under the 2004 and 2009 Acts. Report P29, P30, 1.1
Legal: The Transport (Scotland) Act 2019 allows local authorities to run bus services directly and provides frameworks for franchising and partnership arrangements.
Risk: The action plan in paragraph 5.5 is intended to mitigate the risk of contractor failure in delivering school and public transport services.
Equalities: The report recognises the council's duties to identify and meet the transport needs of children with Additional Support Needs based on assessed individual needs. Report P30
Other: Children's rights, including safety, access to education and equity, must be considered when designing transport policies.
Who and where
Approximately 3,500 pupils transported daily to 78 schools across Argyll and Bute Report 1.5
Children under 8 living more than 2 miles from their nearest school Report 1.1
Children over 8 living more than 3 miles from their nearest school Report 1.1
Children with Additional Support Needs based on assessed individual needs Report 1.1, P30
Public transport passengers across rural and island communities Report 1.4, P19
Existing bus operators and contractors delivering school and public transport Report 4.3, P24
Timeline
12 September 2024: Committee agreed to engage an external consultant to review school and public transport Report 4.1, 1.1
February 2025: Council budget increased for 2025/26 following tender exercises Report 4.3, 1.6
2025: Council commissioned Systra to conduct the review and options appraisal Report 2.1
2 February 2026: Report by the Executive Director dated and submitted Report P34
19 March 2026: Committee considered the report and agreed the recommendations Report P10
Plain English for the jargon
ASN: Additional Support Needs, a legal category for children who need extra help with their education
Systra: External transport consultant commissioned by the council in 2025 to review school and public transport
Hybrid model: A delivery approach combining in-house services with services contracted to external operators
Municipal bus operation: A bus service run directly by the local authority rather than contracted to a private operator
Section 22 agreement: An arrangement under transport law allowing a local authority to run bus services itself
Privilege Rides Policy: Council policy covering use of school transport by non-entitled passengers
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
Decision The Environment, Development and Infrastructure Committee: 1. noted that the council’s existing service delivery arrangements are currently the most viable option; 2. agreed that officers continue to review service provision with contractors and the council’s own team to ensure that school and public transport services continue to deliver best value for the council; 3. noted the options for reducing costs identified at paragraph 4.11b of the report; 4. agreed that officers review the policy options at paragraph 4.11b of the report to ensure that our services reflect best practice; and 5. agreed that officers continue to implement the action plan identified in paragraph 5.5 of the report. (Reference: Report by Executive Director with responsibility for Development and Infrastructure Services, dated 2 February 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1At its meeting on 12 September 2024, members of the Environment, Development and Infrastructure Committee agreed to engage an external consultant to explore options for the future delivery of school and public bus services provided by the council. This was in the context of the legal requirement for the council to provide home to school transport for the following pupils - a. Children under 8 years of age that live more than 2 miles from their nearest school; b. Children over 8 years of age that live more than 3 miles from their nearest school; and c. Children with Additional Support Needs based on assessed individual needs.
1.2The options to be explored by the consultants were as follows -
a. Do nothing, and absorb cost pressures in future years, b. Reduce contract costs in collaboration with service providers by, for example, reducing service provision or identifying efficiencies in existing services, c. In-house operation, whereby the Council would invest in a new fleet, workforce and depots to deliver services ourselves, and d. A hybrid model. 1.3 In 2025, the council commissioned Systra to conduct the review. As well as conducting the options appraisal, the review also • identified a path forward to reduce cost to the council. • balanced this with our corporate plan objectives of reducing carbon emissions and supporting the needs of our communities. • identified how public and school transport services could be redesigned whilst considering potential shared transport schemes which can deliver on these objectives.
1.4The review acknowledged the challenges that the council faced in being the second largest administrative region in Scotland and that our large geographical area, sparse population and topography presented particular difficulties in effectively providing public transport services in a cost-effective manner.
1.5The current budget for the service is £8.486m, £5.394m of which is allocated to payments to transport operators. The council transports approximately 3,500 pupils to 78 schools daily, managing complex logistics across a large rural and island area.
1.6The budget for 2025 / 26 was increased by £0.876m following recent tender exercises. The budget for 2026/27 has been increased by an additional £0.400m.
1.7Systra’s review set out the current environment in terms of legislation, operations and community expectations, as well as challenges and future pathways for the transport services that we deliver.
1.8Through detailed analysis of operations, engagement with stakeholders, costs and benchmarking, and consideration of four scenarios for future delivery models, it identifies practical actions and recommendations to support a resilient, affordable, and future-proof transport network tailored to the unique characteristics and needs of the area’s communities.
1.9It is recommended that members of the Environment, Development and Infrastructure Committee - a. Note that the council’s existing service delivery arrangements are currently the most viable option, b. Agree that officers continue to review service provision with contractors and the council’s own team to ensure that school and public transport services continue to deliver best value for the council, c. Note the options for reducing costs identified at paragraph 4.11b, d. Agree that officers review the policy options at paragraph 4.11b to ensure that our services reflect best practice, and e. Agree that officers continue to implement the action plan identified in paragraph 5.5 of this report. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
ROADS AND INFRASTRUCTURE SERVICES 19 MARCH 2026
UPDATE ON THE REVIEW OF SCHOOL AND PUBLIC TRANSPORT
2.0INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.