REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATE

Noted Committee 2 papers

AI summaryArgyll and Bute's environment committee has noted progress on the Roads and Infrastructure Services review and agreed to reallocate the balance of £90,000 of December 2025 consultancy funding to fleet service strategic improvements, ending the consultant's commission two months early.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBalance of consultancy budget to support fleet strategy work
Money£90,000Approved in December 2025 for further external support
What happens nextFurther reports to future meetingsProgress updates on the 12 priority actions
Who it affectsRoads and Infrastructure ServiceStaff, customers and residents across Argyll and Bute

What was decided

The committee noted progress to date on the Roads and Infrastructure Services review. Report 3.1

The committee noted that further reports on progress would be presented to future meetings of the committee. Report 3.1

The committee agreed to reallocate the balance of the external consultancy support funding approved in December 2025 to strategic improvements within the fleet service. Report 3.1, 4.5

Why

Senior leadership level external consultancy support is no longer required as the priority projects are complete or have moved into implementation phases that no longer need this input. Report 4.5

The organisational reshape has been achieved without growth in the revenue cost of the staffing establishment. Report 4.2, 5.1

The reallocation will free up funding to develop a fleet replacement strategy and a target operating model for fleet requirements. Report 4.5

What happens next

End the existing consultant's commission two months earlier than the original August 2026 end date. Report 4.5

Use the freed balance to develop a fleet replacement strategy and a target operating model for fleet requirements. Report 4.5

Bring further progress reports on the 12 priority improvement actions to future meetings of the EDI Committee. Report 3.1, 4.1

The money

  • £90,000 Additional external support allocation approved in December 2025 to extend consultancy engagement for six months from February 2026 Report 4.5

Options considered

  • Chosen: Reallocate the balance of the December 2025 consultancy funding to fleet service strategic improvements and end the existing consultant's commission two months early. Senior leadership level external support is no longer required as priority projects are complete or in implementation Report 4.5, 3.1

Implications

  • Financial: The re-balancing of capacity has been achieved without an increase in the revenue cost of the staffing establishment. Report 5.1, 4.2
  • Legal: Legal aspects are being reviewed as part of each of the priority improvement actions. Report 6.3
  • Staffing: The organisational reshape has implications for staff and all relevant Council policies and procedures are being followed. Report 6.4, 4.2
  • Other: Customer experience improvements are being developed in relation to household waste collection, commercial waste services and road maintenance. Report 6.5
  • Risk: Risks are being managed in relation to each of the priority improvement actions. Report 6.6
  • Climate: Reduction in carbon emissions is expected from the implementation of post PPP waste management arrangements. Report 6.7
  • Equalities: Equalities considerations for protected characteristics will be considered as part of each of the priority improvement actions. Report 6.9

Who and where

  • Directly affected employees in the Roads and Infrastructure Service involved in the organisational reshape Report 4.2
  • Customers using the roads service web interface to report faults Report 4.3, P19
  • Residents receiving assisted bin uplifts or second domestic waste bin collections Report 4.4
  • Front line teams receiving maintenance schedules via tablet devices Report 4.3

Timeline

  • 20 June 2024: Initial stage 1 review with 119 recommendations from PeopleToo reported to the EDI Committee Report 2.1
  • December 2024 to March 2026: Regular progress updates provided to the EDI Committee Report 2.2
  • December 2025: Further £90,000 external support allocation approved, extending consultancy by six months from February 2026 Report 4.5
  • February 2026: Extended period of consultancy engagement began Report 4.5
  • 18 June 2026: Update report considered by the EDI Committee Report P5
  • End of August 2026: Original end date for the extended consultancy engagement Report 4.5

Plain English for the jargon

  • RIS: Roads and Infrastructure Services
  • EDI: Environment, Development and Infrastructure Committee
  • RIAMS: Roads Information and Asset Management System
  • PeopleToo: External consultancy that carried out the initial stage 1 review
  • CRM: Customer Relationship Management system used to link related enquiries
  • APSE: Association for Public Service Excellence
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

Decision The Environment, Development and Infrastructure Committee: 1. noted the progress to date on the Roads and Infrastructure Services review; 2. noted that further reports on progress would be presented to future meetings of the Committee; and 3. agreed to reallocate the balance of the funding for external consultancy support approved in December 2025 to activity specifically related to strategic improvements within the fleet service. (Reference: Report by Executive Director with Responsibility for Roads and Infrastructure, dated 18 June 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Executive summary

1.1This report provides a further update on progress of key aspects of with the Roads and Infrastructure Services (RIS) Review.

1.2It is recommended that Members of the Environment, Development and Infrastructure Committee:

a) Consider the progress to date on the Roads and Infrastructure Services review. b) Note that further reports on progress will be presented to future meetings of EDI Committee. c) Agree to reallocate the balance of the funding for external consultancy support approved in December 2025 to activity specifically related to strategic improvements within the fleet service. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE

ROADS AND INFRASTRUCTURE SERVICES 18 JUNE 2026

REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATE

2. INTRODUCTION

2.1As Members will be aware, Roads and Infrastructure Service has been undergoing a significant service review. The initial stage 1 review was completed by PeopleToo consultancy and provided 119 recommendations, along with indicative timescales and priorities. These were reported to the Environment, Development and Infrastructure (EDI) Committee on 20 June 2024. An update on progress in relation to all 119 recommendations was provided at the last meeting of this Committee in March along with an update on the 12 priority improvement actions at the 12-month anniversary of the approval of these.

2.2Since the initial report, progress updates have been provided to EDI in: • December 2024 • March 2025 • June 2025 • September 2025 • December 2025 and • March 2026

2.3This report provides a further update on progress in relation to the 12 priority improvement actions.

2.4The full PeopleToo report was not released previously because of issues around commerciality and personal information. As is clear from the terms of this report, matters have now moved on and in the interests of openness and transparency a copy of that report, suitably redacted, is now attached as Appendix 1.

Recommendations

3.1It is recommended that Members of the Environment, Development and Infrastructure Committee:

a) Consider the progress to date on the Roads and Infrastructure Services review. b) Note that that further reports on progress will be presented to future meetings of EDI Committee. c) Agree to reallocate the balance of the funding for external consultancy support approved in December 2025 to activity specifically related to strategic improvements within the fleet service.

4. DETAIL

4.1Since approval of the 12-priority improvement actions regular updates have been provided, as set out at 2.2 above. This report provides a further update with a particular focus on those priority improvement actions that have been the major focus of activity over the period since the last update was provided.

4.2Priority Improvement Action: Organisational Reshaping. This has now moved into the implementation stage. Outcomes in regard to direct matching, expressions of interest and assessment have been confirmed to all the directly affected employees in line with Council policy and the processes that lead to the filling of new posts by the directly affected employees is currently underway.

The organisational reshape achieves a much more balanced structure for the service by increasing management resource in areas that were previously under- resourced and lacked sufficient resilience. In particular, the reshape has resulted in increased resource for the Council’s marine operations, waste disposal, fleet, and infrastructure design functions. The reshaping has also resulted in a structure which greatly improves clarity in roles and responsibilities. The structure is now more clearly aligned to key areas of front-line service delivery, key strategic objectives and statutory duties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Review of RIS: Final Report v8 (24 April 2024) 1 _Redacted 1 (1)Appendix 1 37 MB Download
PDF
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATEReport 158 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 20 attended
IP
Councillor Iain PatersonMember, apologies
JS
Julieann SmallSecretary, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, present
GH
Councillor Graham HardieMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainMember, present
JL
Councillor Jim LynchMember, present
TM
Councillor Tommy MacPhersonMember, apologies
IM
Councillor Ian MacQuireMember, present

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATEThis decision
  2. Review of roads and infrastructure services updateNoted
  3. Review of roads and infrastructure services - updateNoted
  4. Review of roads and infrastructure services - updateNoted
  5. Review of roads and infrastructure services - updateNoted
  6. Review of roads and infrastructure services - updateNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open