REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE
NotedCommittee2 papers
AI summaryArgyll and Bute Council’s Environment, Development and Infrastructure Committee backed six more months of RIS Review consultancy, up to £90,000. It recommended that Council remove a £500k saving increase and have the RIS Review pursue recurring £500k savings from 2024/25 & 2025/26. [D]
Written from the decision and the officer reportPDF Pro
OutcomeNotedTwelve priority actions under review [P9]
MoneyUp to £90,000 [D]Six months beyond February 2026 [P9]
What happens nextReport due March 2026 [D]Pension Gain fallback if RIS resources insufficient [D]
Who it affectsRoads and Infrastructure Services [P9]Waste, asset data, customer service and staff [P9]
What was decided
The committee recorded progress on the 12 priority improvement actions, including their financial effects. Report P9
It agreed to receive a further RIS Review progress report in March 2026. It backed extending external consultancy for six months beyond February 2026, at a cost of up to £90,000. Report P9
The extension should use existing RIS resources where possible. The committee recommended that Council use the Strathclyde Pension Fund Gain earmarking if those resources are insufficient. It also recommended removing the £500k increase due in 2026/27 and having the RIS Review work towards the cumulative £500k saving from 2024/25 & 2025/26 on a recurring basis. Report P9
Why
The existing £150,000 funding will be fully spent by February 2026, so further consultancy is recommended for six more months. The review has four stages, with stages 3 and 4 running concurrently. The 12 priority actions are being introduced in stages to avoid an unsustainable burden on the service. Report 4.1, 4.2, P9
The £200k saving for 2024/25 and the £300k saving for 2025/26 had not been achieved, a cumulative £500k. Efficiencies were harder than expected, and service areas needed intervention for immediate operational challenges. Report P9
Roads and Infrastructure Services had already put forward over £900k of savings as part of council wide options to close the 2026/27 budget gap. With that contribution, there was low confidence that the RIS Review could also achieve the £1m saving target for 2026/27. The report therefore proposed removing the £500k increase. Report P9
What happens next
Provide a further progress report on the RIS Review in March 2026.
Continue the external consultancy for six months beyond February 2026. The work is to finalise service reshaping, progress RIAMS, reduce household residual waste and review commercial waste income. Report P9
Ask Council to approve removal of the £500k increase due in 2026/27, with the RIS Review working towards the cumulative £500k saving from 2024/25 & 2025/26 on a recurring basis. Seek approval for the pension gain earmarking if existing RIS resources are insufficient. Report P9
The money
£90,000 Maximum cost of extending external consultancy for six months beyond February 2026. Report P9
£500k Increase due in 2026/27 that Council is asked to remove. Report P9
£500k Cumulative saving to be pursued on a recurring basis from 2024/25 & 2025/26. Report P9
£1m p.a. Original target for 2026/27 and beyond, assessed as low confidence. Report P9
£700k Additional commercial waste contract income target for 2025/26. Report P9
over £450k Additional commercial waste contract income achieved to date. Report P9
£3m Capital released to other service priorities after the Helensburgh waste transfer station business case review. Report P9
over £900k Savings proposed within council wide options to close the 2026/27 budget gap. Report P9
Options considered
Chosen: Extend the external consultancy for a further six months beyond February 2026. Existing funding is due to end in February 2026, and the extension would support the remaining review work. Report P9
Chosen: Use existing RIS resources first. Existing resources are the first funding route for the extension. Report P9
Chosen: Recommend the pension gain earmarking as a fallback if RIS resources are insufficient. It is the stated fallback and requires Council approval. Report P9
Chosen: Remove the £500k saving increase due in 2026/27. There was low confidence that the £1m 2026/27 target would be achieved after over £900k had already been proposed. Report P9
Rejected: Retain the £1m p.a. RIS Review saving target for 2026/27 and beyond. Confidence was low that the target would be achieved alongside the savings already proposed by Roads and Infrastructure Services. Report P9
Chosen: Work towards the cumulative £500k saving from 2024/25 & 2025/26 on a recurring basis. Neither the 2024/25 nor the 2025/26 revenue saving had been achieved, leaving the cumulative £500k as the objective. Report P9
Implications
Financial: Some priority actions aim to increase efficiency and deliver financial benefits. Others may require further financial input and will be brought to members for consideration. Report P9
Legal: Legal aspects are being reviewed as part of each priority improvement action. Report P9
Equalities: Protected characteristics will be considered as each priority improvement action progresses. Report P9
Climate: Implementing waste disposal arrangements that respond to the ban on municipal waste to landfill will reduce carbon emissions. Report P9
Risk: Risks are being managed for each priority improvement action. Report P9
Staffing: Reshaping the organisation structure has implications for staff. All relevant Council policies and procedures are being followed. Report P9
Other: There are no direct policy implications from the report, although some priority actions change existing policies and may lead to further reports. Priority actions also aim to improve customer experience in household waste collection, commercial waste services and road maintenance. Report P9
Other: No Fairer Scotland Duty, Consumer Duty or Island Communities impacts were identified at this time. No children's rights and wellbeing impacts arise directly from this report. Report P9
Other service priorities within the service Report P9
Timeline
June 2024: Council agreed the £150,000 allocation after a June 2023 committee recommendation. Report P9
September 2025: The previous RIS Review update was provided to the committee. Report 1.2, 2.1
18th December 2025: The committee backed the consultancy extension and made the revised savings recommendation. Report P9
February 2026: Existing consultancy and administrative funding was due to be fully spent, with the extension running six months beyond this point. Report P9
March 2026: A further progress report on the RIS Review was due.
2026/27: The £500k increase was recommended for removal. The RIS Review was to work towards the cumulative £500k saving from 2024/25 & 2025/26 on a recurring basis. Report P9
2025/26: The RIS Review saving target was £300k. A separate £700k commercial waste contract income target also applied, and the revenue saving had not yet been achieved. Report P9
2024/25: The RIS Review saving target was £200k. It was not achieved. Report P9
Plain English for the jargon
RIS Review: The Roads and Infrastructure Service Review, covering service improvement and reshaping. [1.1][P9]
RIAMS: Roads and Information Asset Management Systems. Its improvement project supports customer service and service efficiency. [P9]
Strathclyde Pension Fund Gain earmarking: Money set aside for transformation and spend to save initiatives. [P9]
Priority improvement actions: The 12 actions being progressed under Stage 4 of the RIS Review. [P9]
Recurring saving: A saving stated as £1m p.a. for 2026/27 and beyond, or as £500k from 2024/25 & 2025/26. [P9][D]
Commercial waste income: Income from commercial waste contracts, with a separate target for 2025/26. [P9]
SOLACE: The consultancy used to provide RIS Review support. [P9]
Municipal waste landfill ban: The ban shaping waste disposal arrangements and expected to reduce carbon emissions. [P9]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
Decision The Environment, Development and Infrastructure Committee: 1. noted the progress made in relation to the priority improvement actions, including the financial impacts of these; 2. agreed to receive a further report on the progress of the RIS Review in March 2026; 3. endorsed the extension of the external consultancy to support the RIS review project at a cost of up to £90,000 noting that where possible this would be funded from within existing resources but recommend to Council that should there be insufficient existing resources within RIS that this is funded from the Strathclyde Pension Fund Gain earmarking set aside for transformation/spend to save initiatives; and 4. agreed to recommend to Council that: i. the increase in saving target of £500k due to be applied in 2026/27 to the RIS Review be removed; and ii. instead, the RIS Review work towards achievement of the cumulative £500k saving from 2024/25 & 2025/26 recurring. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated December 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee, 6 pages
Executive summary
1.1The purpose of this report is to provide Members of the Environment, Development and Infrastructure Committee with an update on progress and next steps in relation to the Roads and Infrastructure Service Review (RIS Review).
1.2In providing this update reference is made to information contained in the previous report to this Committee in relation to the RIS Review in September 2025 and to the actions taken in the intervening period.
1.3It is recommended that Members of the Environment, Development and Infrastructure Committee:-
a) Consider the progress made in relation to the priority improvement actions, including the financial impacts of these, and; b) Agree to receive a further report on progress of the RIS Review in March 2026. c) Endorse the extension of the external consultancy to support the RIS review project at a cost of up to £90,000 noting that where possible this would be funded from within existing resources but recommend to Council that should there be insufficient existing resources within RIS that this is funded from the Strathclyde Pension Fund Gain earmarking set aside for transformation/spend to save initiatives. d) Agree to recommend to Council that i. the increase in saving target of £500k due to be applied in 2026/27 to the RIS Review be removed and ii. instead, the RIS Review work towards achievement of the cumulative £500k saving from 2024/25 & 2025/26 recurring. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE ROADS AND INFRASTRUCTURE 18th DECEMBER 2025
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES - UPDATE
2.0INTRODUCTION
2.1This report provides an update to Members of this Committee on progress of the Roads and Infrastructure Service Review (RIS Review), since the last update in September 2025.
Recommendations
3.1It is recommended that Members of the Environment, Development and Infrastructure Committee:-
a) Consider the progress made in relation to the priority improvement actions, including the financial impacts of these, and; b) Agree to receive a further report on progress of the RIS Review in March 2026. c) Endorse the extension of the external consultancy to support the RIS review project at a cost of up to £90,000 noting that where possible this would be funded from within existing resources but recommend to Council that should there be insufficient existing resources within RIS that this is funded from the Strathclyde Pension Fund Gain earmarking set aside for transformation/spend to save initiatives. d) Agree to recommend to Council that i. the increase in saving target of £500k due to be applied in 2026/27 to the RIS Review be removed and ii. instead, the RIS Review work towards achievement of the cumulative £500k saving from 2024/25 & 2025/26 recurring. 4.0 DETAIL
4.1The RIS Review has been structured around 4 stages of activity as illustrated below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.