Cumberland Road Stabilisation Project

Approved Executive 4 papers

Cabinet approved this item on Tuesday 9 March 2021. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

Cabinet Approve the additional allocation of Capital expenditure of £2,491,190.61 to complete the full Project, based on the revised Qualitative Risk Assessment (QRA) undertaken and the detailed substantiation’s given in this Report. Authorise the Executive Director Growth and Regeneration to take all steps required to spend the additional allocation to complete the full project.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway Report

PURPOSE: Key decision

MEETING: Cabinet

DATE: 09 March 2021

TITLE Cumberland Road Stabilisation Project

Ward(s) Hotwells and Harbourside

Author: Chris Dooley Job title: Bridges and Highway Structures Team Manager Cabinet lead: Cllr Dudd Executive Director lead: Stephen Peacock – Executive Director, Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To update Cabinet on Works progress of the Cumberland Road Stabilisation Works project and to inform Cabinet of the findings of recently undertaken further instructed updated QRA, now forecasted a revised new increase in Capital funding risk shortfall of £2,491,190 to execute the full Project, this is very similar to previous forecast (£2.52 million) reported in previous CMD Report. Refer to Appendix D for the additional instructed updated QRA Risk Register. Evidence Base: A section of the river Avon retaining wall failed overnight on 23rd January 2020 causing a 40m long section of the Chocolate Path and Heritage railway to fall in to the river. BCC Engineers were informed of failure at 07:00am on 24th January 2020. Cumberland Road was immediately closed except for the footway which remained open for pedestrians and cyclists. Tenders for the Cumberland Road Stabilisation Works were returned on 24th Jan 2020.

Project Background and Works Progress 1. Works commenced on site on Monday 15th June, Activities included mobilisation, establishment of site and changeover of Traffic management and commencement of site clearance trial trenching and investigation. 2. Contractor encountered uncharted obsolete cast Iron Docks rising main within envelope of works. The cast iron main was attributed to be historic and associated with the original Vauxhall swing bridge operational function. Section removed and then capped off. 3. Phase 1a Temporary Works approval submitted to Wessex Water (WW) and is now fully approved. 4. Exploratory test CFA piling drilling operation now completed successfully and CFA piling is underway. 5. CFA Piling commenced in mid-November 2020, and by close of working shift on Friday 29th January the Principal Contractor had installed 208 no. CFA piles, which is has now completed Phase 1a temporary Works. Phase 1b now continues to progress and is on Programme. 6. Project is currently assessed by NEC PM to be back on the new approved Works Programme timeline. 7. Advance warning letter to go out to targeted businesses and local residents has been issued to all Ward Councillors and Transportation member for comment. No major issues have resulted from this. Advanced warning letters hand delivered to the identified catchment by Monday 9th November. Some minor responses from some residents regarding Traffic Management issues which have all been responded to. 8. Current Traffic Management arrangement is fully bedded in and seems to be working very well. 9. One single Piling complaint received in November/December 2020 from a resident in Meredith Court. 10. Traffic Management signage and fencing subject to high levels of vandalism. Contractor is dealing with this issue and may install further security measures and CCTV cameras. Overall Project Financial Position – Cabinet Approved Capital Funding of £9,023,190.00

1 Version March-2018 Design and Supervision Fees Jacobs Consultants design fee = £919,000.00 Jacobs – NEC PM & Supervisor Duties = £300,000 Jacobs Secondment (Steve Whitehead BCC PM for the Project and other duties) = £386,000 BCC Internal Staff Fees = £100,000 Sub Total = £1,677,500

Miscellaneous Structural Enabling Works Structural Soils (ground investigation and monitoring) = £245,000 ETM Enabling Works (as a consequence of Jan 2020 collapse) = £100,000 Other Associated Costs (incl. traffic signals, drone and LIDAR survey, modelling etc.) = £120,000 Sub Total = £465,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Case: Chocolate Path Wall Repairs: Rev AAppendix A 674 KB Download
PDF
Updated QRA Risk RegisterAppendix D 149 KB Download
PDF
Chocolate Path Stabilisation_EQIA Relevance Check: March 2021Appendix E 230 KB Download
PDF
Cumberland Road Stabilisation ProjectDecisions 291 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
MR
Marvin ReesCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, present
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
HG
Councillor Helen GodwinCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
AK
Councillor Anna KeenCommittee Member, present
SP
Councillor Steve PearceCommittee Member, apologies
AS
Councillor Afzal ShahCommittee Member, present
LD
Louise deCordovaOfficer, expected
RA
Rachel AbbaOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Cumberland Road Stabilisation ProjectThis decision
  2. Petition Debate ~ Publish full feasibility report on Cumberland Basin road optionsNoted
  3. Cumberland Road Stabilisation ProjectApproved

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies