Cabinet Approve the additional allocation of Capital expenditure of £2,491,190.61 to complete the full Project, based on the revised Qualitative Risk Assessment (QRA) undertaken and the detailed substantiation’s given in this Report. Authorise the Executive Director Growth and Regeneration to take all steps required to spend the additional allocation to complete the full project.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Author: Chris Dooley Job title: Bridges and Highway Structures Team Manager Cabinet lead: Cllr Dudd Executive Director lead: Stephen Peacock – Executive Director, Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To update Cabinet on Works progress of the Cumberland Road Stabilisation Works project and to inform Cabinet of the findings of recently undertaken further instructed updated QRA, now forecasted a revised new increase in Capital funding risk shortfall of £2,491,190 to execute the full Project, this is very similar to previous forecast (£2.52 million) reported in previous CMD Report. Refer to Appendix D for the additional instructed updated QRA Risk Register. Evidence Base: A section of the river Avon retaining wall failed overnight on 23rd January 2020 causing a 40m long section of the Chocolate Path and Heritage railway to fall in to the river. BCC Engineers were informed of failure at 07:00am on 24th January 2020. Cumberland Road was immediately closed except for the footway which remained open for pedestrians and cyclists. Tenders for the Cumberland Road Stabilisation Works were returned on 24th Jan 2020.
Project Background and Works Progress 1. Works commenced on site on Monday 15th June, Activities included mobilisation, establishment of site and changeover of Traffic management and commencement of site clearance trial trenching and investigation. 2. Contractor encountered uncharted obsolete cast Iron Docks rising main within envelope of works. The cast iron main was attributed to be historic and associated with the original Vauxhall swing bridge operational function. Section removed and then capped off. 3. Phase 1a Temporary Works approval submitted to Wessex Water (WW) and is now fully approved. 4. Exploratory test CFA piling drilling operation now completed successfully and CFA piling is underway. 5. CFA Piling commenced in mid-November 2020, and by close of working shift on Friday 29th January the Principal Contractor had installed 208 no. CFA piles, which is has now completed Phase 1a temporary Works. Phase 1b now continues to progress and is on Programme. 6. Project is currently assessed by NEC PM to be back on the new approved Works Programme timeline. 7. Advance warning letter to go out to targeted businesses and local residents has been issued to all Ward Councillors and Transportation member for comment. No major issues have resulted from this. Advanced warning letters hand delivered to the identified catchment by Monday 9th November. Some minor responses from some residents regarding Traffic Management issues which have all been responded to. 8. Current Traffic Management arrangement is fully bedded in and seems to be working very well. 9. One single Piling complaint received in November/December 2020 from a resident in Meredith Court. 10. Traffic Management signage and fencing subject to high levels of vandalism. Contractor is dealing with this issue and may install further security measures and CCTV cameras. Overall Project Financial Position – Cabinet Approved Capital Funding of £9,023,190.00
1 Version March-2018 Design and Supervision Fees Jacobs Consultants design fee = £919,000.00 Jacobs – NEC PM & Supervisor Duties = £300,000 Jacobs Secondment (Steve Whitehead BCC PM for the Project and other duties) = £386,000 BCC Internal Staff Fees = £100,000 Sub Total = £1,677,500
Miscellaneous Structural Enabling Works Structural Soils (ground investigation and monitoring) = £245,000 ETM Enabling Works (as a consequence of Jan 2020 collapse) = £100,000 Other Associated Costs (incl. traffic signals, drone and LIDAR survey, modelling etc.) = £120,000 Sub Total = £465,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.