Cabinet Approved the allocation of £2.5m from the Capital Programme to address the following a. £1.0m to replace footbridge structure at Underfall Yard Sluices; b. £500k to undertake immediate monitoring of all identified critical structures within the next two years; and c. £1.0m to undertake further structural and geotechnical investigations within the next two years. Authorised the Executive Director Growth and Regeneration (in consultation with the Cabinet Member for Transport and Energy) to take all steps required to procure and commission contractors to undertake the necessary services / works.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Floating Harbour and New Cut River – Condition Assessment Survey Report
Ward(s) Various Wards affected – Hotwells and Harbourside, Southville Central , Bedminster, Lawrence Hill, Brislington West, Brislington East and Easton wards.
Author: Chris Dooley Job title: Bridges and Highway Structures Team Manager Cabinet lead: Cllr Dudd Executive Director lead: Stephen Peacock – Executive Director, Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To identify high priority “At Risk” immediate conclusions for 11 No. critical strategic harbour and New Cut assets, derived from the Harbour and New Cut asset condition assessment work, carried out in 2019-2020. 2. Recommend Capital funding of £2.50m over the next two years; (a) £1.0m to replace footbridge structure at Underfall Yard Sluices (Asset No NCN03a). (b) £500k to undertake immediate monitoring of all identified critical structures within the next two years. (c) £1.0m to undertake further structural and geotechnical investigations within the next two years. 3. To note that this is just the first tranche in the “Asset Condition overview” investigation process for the whole of the Floating Harbour and the New Cut River and that further continuing detailed investigations and financial costings will need to be undertaken to provide a more exact and clearer overall asset condition risk register position, both to enable a more accurate and complete Risk Register in terms of Health and Safety compliance, as well as identify future financial risks and commitments. Evidence Based: Executive Summary of Findings 1. From the floating harbour and river asset condition survey undertaken in 2019/20 there are 194 retaining wall assets identified within the Harbour and New Cut waterways. This paper focuses only on 11 highest priority retaining wall assets of 68 retaining walls assets that were found to be in a critical or serious structural condition. See Appendix B. 2. Any failure of the identified 11 No. Harbour retaining wall assets (in the event of a failure), would result in potential loss of life or serious injury, major flooding, adjacent property damage and immediate closure of the strategic highway network in the vicinity of failure with knock on Citywide traffic congestion, and resultant financial, environmental and reputational damage to the Council and the local economy and South West region. 3. Appendix A sets out the overall findings of the full Harbour asset study and Appendix B for the 11 no. identified critical transport assets together with structural estimates to stabilise the assets.
Proposed Recommended Action Plan Timeline Plan and Programme 4. Early initial estimate capital requirement for the next 5 years to repair/replace 11 No. highest priority assets is assessed at being £14.35m (includes additional 40% contingency). Substantiation of this £14.35m estimate are contained within Appendix B of this paper. This estimate is to be heavily caveated due to the further need for structural/geotechnical investigations carried out before designs can be undertaken to inform detailed stabilisation. 5. The immediate need is for £2.5m to carry out certain works, monitoring and investigation, detailed below. 6. Asset NCN03a requires immediate replacement of this steel Girder beam footbridge supporting the Chocolate Path and associated PROW, this is to be done concurrently with Cumberland Road Stabilisation Contract, but must be designed and procured as a matter of urgency. BCC will not be able to reopen the Chocolate path following the Cumberland Road works due to the severity of the corrosion on this bridge. This work now requires £1.0m capital funding in 2021/2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.