Bristol City Council
Cabinet, Tuesday 9 March 2021 at 4.00pm

Temple Quarter Development Update

Approved Executive 6 papers

Cabinet approved this item on Tuesday 9 March 2021. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Cabinet Authorised the Executive Director for Growth and Regeneration, in consultation with the Mayor and the Working Group, to finalise and implement proposals for detailed engagement and consultation for the Temple Quarter Development Framework as set out in the report. Authorised the Executive Director of Growth and Regeneration, in consultation with the Mayor, Deputy Mayor, Finance Governance and Performance, the S.151 Officer, and Director of Legal Services to seek reallocation of £560k of WECA Early Investment Fund through WECA’s change control process and to bid for and use £500k of Housing and Regeneration Enabling Fund grant funding and to defray those monies on staffing costs in accordance with the WECA approvals. Authorised the Executive Director for Growth and Regeneration, in consultation with the Mayor, Deputy Mayor, Finance Governance and Performance, the S.151 Officer, and Director of Legal Services, to agree the final schedule of enabling works to support the opening up and servicing of the Temple Island site, to secure the variation of any WECA approvals necessary, and to defray this funding in accordance with the terms of the funding decision and in line with all appropriate procurement routes. Authorised the Executive Director of Growth and Regeneration, in consultation with the Deputy Mayor, Finance Governance and Performance, the S.151 Officer, and Director of Legal Services to agree the detailed terms on which any monies allocated to the Temple Quarter project by central government are received by the four parties to the bid (BCC, WECA, Homes England and Network Rail), to agree the detailed terms of the Inter Authority Agreement between the partners to defray such monies, and to receive and defray any portion of those monies subsequently allocated to the Council under separate project Funding Agreements. Noted that further reports will be received setting out progress with the actions set out in the report and the Development generally.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway – Report

PURPOSE: Key decision

MEETING: Cabinet

DATE: 09 March 2021

TITLE Temple Quarter Development Update

Ward(s) Windmill Hill and Lawrence Hill

Author: Colin Molton Job title: Interim Programme Director, Temple Quarter Cabinet lead: Mayor Executive Director lead: Stephen Peacock Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report:

1. An update on the status of the Temple Quarter Development Framework, including the publication of a strategic visioning document for Temple Quarter and an outline of the proposed approach to Engagement and Consultation for the area; 2. Approval to seek reallocation of £560k of WECA Early Investment Fund grant funding to provide capacity in both current BCC teams and the new Temple Quarter Joint Delivery Team to progress the Temple Quarter objectives; 3. Approval to bid for and use £500k of Housing and Regeneration Enabling Fund grant funding from WECA for work in Temple Quarter, including funding Joint Delivery team resource, consultancy support, and public engagement activity; 4. An update on the status of the proposed enabling works to open up and service the Temple Island site; 5. An update on the establishment of the Joint Delivery Team for Temple Quarter, the work being undertaken by the Temple Quarter Member-led Working Group and the initial work being undertaken to explore longer term delivery vehicles; 6. An update on the progress of the bid to secure central government funding to support development proposals in Temple Quarter;

Evidence Base:

1. Temple Quarter Development Framework

The Temple Quarter Development Framework was commissioned by Bristol City Council, Network Rail, Homes England and West of England Combined Authority, and is intended to set out the combined aspirations and objectives of these partners through evidence-based proposals for the future development of the area.

An update on the status of the Development Framework was brought to Cabinet in October 2020, outlining the context to the work; how and why it was commissioned, the purpose of the document, what the proposals seek to achieve, and the approach to ensuring sustainable and inclusive economic growth is embedded within it.

Since that update a visioning document has been produced which provides a strategic overview of the proposals considered in the Development Framework (see Appendix A) This document is intended to be an accessible, non-technical, public-facing document, that will quickly allow a wide range of stakeholders to understand what is being proposed, and to prompt conversation and engagement on the future of the area. Importantly, the document references our proposed approach to future engagement and consultation which is set out in further detail in this Cabinet Paper. This underlines the Council’s commitment to businesses, residents and wider city stakeholders, and sets out an approach for how everyone can help to shape the proposals.

1 Version Jan 2021 The Development Framework itself will be shaped and refined as this further engagement and consultation takes place, and the views and feedback of stakeholders are taken into account, prior to publication of the completed document.

2. Engagement Approach

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TQ Vision DocumentAppendix A 9.2 MB Download
PDF
Temple Quarter_Risk RegisterAppendix D 33 KB Download
PDF
TQ equalities impact assessment March 2021 FINALAppendix E 568 KB Download
PDF
TQ eco impact assessment March 2021 FINALAppendix F 432 KB Download
PDF
Temple Quarter Development UpdateReport 269 KB DownloadRead as text
PDF
Temple Quarter vision document March 2021 FINAL 2Report 9.2 MB Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
MR
Marvin ReesCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, present
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
HG
Councillor Helen GodwinCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
AK
Councillor Anna KeenCommittee Member, present
SP
Councillor Steve PearceCommittee Member, apologies
AS
Councillor Afzal ShahCommittee Member, present
LD
Louise deCordovaOfficer, expected
RA
Rachel AbbaOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Temple Quarter Development UpdateThis decision
  2. Bristol Temple Quarter Update – Quarterly Update June 2026Decided
  3. Bristol Temple Quarter Update – Quarterly Update July 2025Noted
  4. Bristol Temple Quarter UpdateNoted
  5. Bristol Temple Quarter acquisitionsAgreed
  6. Temple Quarter Delivery StrategyAgreed

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies