Cabinet Recognised the importance of the to the city’s cultural offer and in doing so, approves the revised cost envelope of £106.9m and incorporating the following (total increase of £58.1m in addition to £48.8m previously approved): a) £3.405m WECA funding for project inflation (approved by WECA in June 2020) b) £2.930m WECA further funding support (approved by WECA in January 2021) c) £6.201m from Arts Council England Kickstarter grant d) £44.464 from Bristol City Council own capital programme and resources funded by Prudential Borrowing (proposed to be released from capital programme contingency) e) £1.1m further funds to be raised by BMT; Authorised the Executive Director for Growth & Regeneration in consultation with Cabinet Member Finance, Governance and Performance, Section 151 officer and the Monitoring officer to take all steps required to enter into any contracts required and negotiate and agree changes to existing contract terms to give effect to the above including; a) Enter contracts for professional services required to complete the project; b) Amend the construction contract to transfer risk and secure greater cost and programme certainty; c) Agree any new/additional terms of grant with any grant funding bodies.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Central Ward directly (the whole city, region and nationally operationally) Author: James Anderson Job title: Head of Capital Projects Cabinet lead: Mayor Executive Director lead: Stephen Peacock Proposal origin: BCC Staff Decision maker: Mayor Decision forum: Cabinet Purpose of Report: 1. For Information – to update on action taken since last Cabinet paper 2. For information - to confirm cost and delay implications associated with issues found within the building and Covid-19 3. To approve funding to ensure the project is completed and delivers the expected long-term benefits to the city and give delegated authority to enter into and amend existing contracts required to deliver the project The building Bristol Beacon (formerly Colston Hall) has been Bristol’s most iconic live music and arts venue for 150 years, playing an important part of the city’s cultural life and the region’s creative economy. The Grade 2 listed building is a Bristol City Council owned freehold asset, operated since 2011 by Bristol Music Trust (BMT) under a peppercorn lease. It has a capacity of more than 2,000 and hosts a programme of pop, jazz, world and classical music as well as stand-up comedy. The building sits on a constrained site and has suffered from a lack of maintenance and modernisation with no major refurbishment for 60 years.
Restoring a degraded asset It has long been understood that the building itself needed a complete refurbishment, with profound and visible degradation to its fabric, constraints that limit its commercial potential and significant increasing costs of ensuring the building remains safe for public use. From the late 1990s successive administrations considered these issues. Appendix A3 sets out a brief chronology.
Following the completion of the Phase 1 development in 2009 (the Foyer) there was virtually no progress on the redevelopment of the main building until a report was taken to the first Cabinet of the current administration in June 2016. This authorised a £1.6m investment to enable the preparation and submission of a detailed planning application for Phase 2. Further Cabinet reports in 2017 and 2018 paved the way for a £48.8m redevelopment project. In 2017 KPMG was commissioned to undertake an Economic Impact Assessment on the proposed plans for the hall. The report concluded that a restored hall would directly contribute £324.6 million over a 20 year period (£16.2m annual GVA) and directly create/safeguard 294 jobs.
Delivery challenges The Council is the owner of the freehold of the building and has the role of client with ultimate responsibility for underwriting the full costs of the Phase Two redevelopment. The specification, programme and estimated capital cost were all derived using the industry standard RIBA process with BCC project officers supported by an external team of professional advisors.
Work began on Phase 2 in August 2018, following the procurement of contractors. The act of removing the fabric from the building to undertake extensive surveys created a commitment to rectify any issues that were found, as the fabric cannot simply be reinstated once items are uncovered. As a live performance venue it was not feasible to carry out extensive intrusive surveys before proceeding with the main project as this would have required the closure of the venue with no certainty over when and if the refurbishment project would go ahead.
The standard construction contract used was an NEC A. This places responsibility for risk of design development and the
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.