Cabinet Approved the preferred approach of adaptive raised defences to manage the risk of flooding from the river Avon as set out in the SOC in full; Noted capital costs for delivery of phase one is estimated at £216m, of which £88m to £123m funding is identified in principle; Approved the development of a funding strategy to address the additional capital funding required to deliver phase one; Noted additional spend in developing the SOC of £475,438 as set out in Appendix A1; Approved the development of Outline Business Case(s) to further refine proposals and progress the case for investment; Authorised an application for up to £2m local levy grant funding to fund supporting work in developing the Outline Business Case; Authorised the Executive Director for Growth and Regeneration in consultation with the S151 officer and Cabinet Member for Finance, Governance and Performance, to accept the grant if successful and take all steps required to enter into any agreements or contracts to spend the grant; Authorised the Executive Director for Growth and Regeneration to invoke any extensions/variations defined in the contracts referred to above, up to the budget envelope of £2m as outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Hotwells and Harbourside, Central, Bedminster, Southville, Lawrence Hill, Brislington West, Brislington East, St George Troopers Hill, Avonmouth & Lawrence Weston Author: Matthew Sugden Job title: Principal Flood Risk Officer Cabinet lead: Cllr Nicola Beech, Cabinet Member Executive Director lead: Stephen Peacock, Executive Director of for Spatial Planning and City Design Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. The Bristol Avon Flood Strategy’s Strategic Outline Case (SOC) sets out the approach to managing flood risk from the river Avon for existing property which, once its delivery is reasonably certain, will also greatly reduce the constraint of flood risk on new development.
2. Following public consultation which demonstrated strong support for the proposals we are seeking approval from Cabinet to endorse the preferred approach of adaptive raised defences to manage the risk of flooding from the river Avon as set out in the SOC. We also seek approval to progress to the development of an Outline Business Case, and apply for grant funding to aid its development.
Evidence Base: 1. Parts of Bristol city centre are at increasing flood risk from the River Avon from high river flows and tidal surges. Today a severe flood from the River Avon would result in the flooding of approximately 1,100 homes and businesses. By the end of this century the number of properties at risk is expected to increase to approximately 4,500 existing properties if we do not take action. The threat of flooding in the central area also poses a significant constraint to potential future development in areas subject to flood risk. In the absence of a flood risk strategy with reasonable prospects of delivery, it is difficult or impossible to demonstrate that development in areas subject to flood risk will be safe for its lifetime as required by national planning policy. The strategic approach to managing the risk of flooding will:
• Future proof substantial parts of the city to ensure flood risk to existing and future homes and businesses is adequately addressed, taking an adaptive approach to allow measures to change in response to climate change • Facilitate the development and regeneration of areas currently subject to flood risk, as soon as a reasonable prospect of the delivery of flood defences has been secured • Provide opportunities for improved walking and cycling links, enhanced green spaces and biodiversity gains, and public realm improvements to be integrated in to proposals • Provide nearly £1bn in economic benefit to the UK and unlock over £7bn benefits to the local economy by enabling growth at sites currently constrained by flood risk and avoiding damage and disruption to business and infrastructure
2. Evidence to support the proposed approach is provided in the Strategic Outline Case including executive
1 Version May 2019 summary provided in Appendix A.
3. The feedback from consultation is reported in Appendix B. Feedback was overwhelmingly positive, 84% of respondents agreed or strongly agreed with the proposal for adaptive flood defences which allow for changes in height over time.
4. The Strategic Outline Case has been given technical approval and financial scheme of delegation approval by the Environment Agency for additional work to inform the preparation of the Outline Business Case. Approval of up to £2m spend has been granted pending successful grant application.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.