Transport & Connectivity Policy Committee noted this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.
That the Policy Committee for Transport and Connectivity 1. Noted the approvals granted on Item 10 at the Cabinet Meeting on 05 March 2024. 2. Approved the submission of a Full Business Case (Appendices E) to the West of England Mayoral Combined Authority (WECA). 3. Authorised the Executive Director of Growth and Regeneration in consultation with the Director of Finance and the Committee Chair for Transport and Connectivity, subject to approval of the Full Business Case by WECA to: - (I) Take all steps required to accept and spend the City Region Sustainable Transport Settlement (CRSTS) funding amount as set out in this report and appendices, (ii) Tender and procure contracts (including any over £500K) necessary to deliver the works, (iii) Award contracts and spend the funding to deliver the works as set out in the Full Business Case up to the maximum budget envelope outlined in this report . (iv) Accept, tender, award and spend on contracts to deliver re-surfacing should further CRSTS funding become available which may be over the key decision threshold.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Committee Report
PURPOSE: Final Decision Report
KEY OR NON-KEY DECISION: Key decision over £500k spend/save & impacts more than 2 wards
COMMITTEE: Transport and Connectivity Committee
DATE: 06 February 2025
TITLE: A4 Portway Full Business Case Ward(s): Avonmouth and Lawrence Weston, Stoke Bishop, Clifton, Hotwells and Harbourside
Officer presenting the report: Alex Hearn / Adam Crowther Job title: Director of Economy of Place / Head of Service for City Transport
Committee Chair: Cllr Ed Plowden, Chair of the Transport and Connectivity Board Executive Director lead: John Smith: Executive Director for Growth & Regeneration
Proposal origin: BCC Staff
Purpose of Report: To seek approval for the submission of a Full Business Case (FBC) to the West of England Mayoral Combined Authority (WECA) for City Regional Sustainable Transport Settlement (CRSTS) funding and subject to approval, to accept and spend the funding to deliver the A4 Portway Strategic Corridor project.
Evidence Base / Options to consider:
1. Bristol, like many other global cities, is facing a climate emergency. Transport directly contributes to a third of the city’s emissions and without action this will continue and potentially even increase as we move into 2030. 2. The A4 Portway is one of Bristol’s key transport corridors and is currently facing issues including congestion and bus delays, a bus patronage that has been recovering since the pandemic, high dependency on private vehicles and a lower modal share on public transport, poor air quality, safety, and poor perception of safety. 3. The A4 Portway Strategic Corridor is proposing to tackle these issues through the introduction of 24- hour bus lanes, wider paths for shared use between pedestrians and cyclists, speed limit reductions, and various junction improvements along the route. Further details on the proposals can be seen in Figure 1, and in Appendices A and H2.
1 Version January 2024
OFFICIAL Figure 1: A4 Portway Corridor Proposals
2 Version January 2024
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.