Canons Road and College Green Signals Refurbishment Scheme
ApprovedCommittee5 papers
Transport & Connectivity Policy Committee approved this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.
That the Committee for Transport and Connectivity: 1. Approved the report to invest £1,037,560 in this junction refurbishment as part of the CRSTS programme and under our statutory duties to maintain this failing highway asset. 2. Authorised the Executive Director for Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to procure and award the Canons Road/College Green Signals Refurbishment contract, in-line with the procurement routes and maximum budget envelopes outlined in this report. 3. Authorised the Executive Director for Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
1. To seek approval to accept and invest £1,037,560 of funding from the Mayoral Combined Authority as part of the City Region Sustainable Transport Settlement (CRSTS) programme. 2. To procure and award contracts (including any over £500k) necessary to deliver the works within the existing Highways Framework. Evidence Base / Options to consider:
1. The traffic signals junction of College Green / Canons Road / St Augustines Parade has been earmarked for refurbishment by both the Traffic Signals Capital Refurbishment Programme and the A37/A4018 transport corridor project. The refurbishment will deliver key walking and cycling improvements at this busy city centre junction. The existing substandard facilities for visually impaired pedestrians will be brought up to current design standards and the new layout will reduce the number and length of pedestrian crossings. It also improves the cycle facilities with greater segregation from general traffic and a new crossing across College Green, improving cycle connectivity between Park Street and the City Centre.
2. It is proposed to deliver this junction refurbishment in advance of the main A37/A4018 corridor works as this brings the opportunity to start delivery and spend funding, helping to relieve the project’s programme pressures with the CRSTS funding deadline. This junction refurbishment is independent of the Park Street proposals and makes no changes or restrictions to any of the existing movements that can be made through the junction. It is, however, also complementary of the Park Street proposals meaning that these works will not include any abortive work should the Park Street proposals be implemented. 1 Version January 2024 3. The junction refurbishment scheme will be included within the Full Business Case for Work package 3 of the A37/A4018 Strategic Corridors scheme.
4. The traffic signals at this junction are life expired with obsolete equipment that can no longer be maintained. This includes failed vehicle detection and inability to coordinate with City Centre Urban Traffic Control (UTC) system. As a result, they are at risk of failure with no repair solution apart from full replacement and day-to-day they are causing local delays and congestion, including to public transport. The proposed junction refurbishment will resolve this significant maintenance risk and ensure the council meets its statutory duties to maintain the highway. The refurbished signals will improve road safety for all users and ensure all equipment is electrically and structurally safe for the next 20 years, reducing the risk of faults and unavailability of facilities.
5. The A37/A4018 Strategic Corridors scheme proposes additional enhancements to active travel and public realm. To refurbish the signals before this scheme, purely as a maintenance job replacing like- for-like, would not represent good value for money as it would be largely abortive work and bring significant network disruption to the area twice within a couple of years. By bringing forward the delivery of the Strategic Corridors scheme it ensures both the essential Traffic Signal maintenance works, and the strategic enhancements are undertaken at the same time.
Officer Recommendations:
That the Committee for Transport and Connectivity
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.