Transport & Connectivity Policy Committee approved this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.
That the Committee for Transport and Connectivity: 1. Approved the pausing or stopping of charging delay damages to KB and refund those levied to date (without prejudice). 2. Accepted new funding from CRSTS over-programming (£3.5m) and EDF (£2.7m). 3. Approved increasing the budget of the project from £3.5m to £6.2m, plus the existing £3.5m – a total of £9.7m. 4. Approved the use of up to £3.5m of the existing project budget to negotiate an agreement with KB. 5. Authorised the Executive Director Growth and Regeneration in consultation with the Committee Chair for Transport and Connectivity to extend/ vary the contract as necessary to enact recommendations 1 and 4. 6. Authorised the Executive Director for Growth and Regeneration to invoke any subsequent extensions/ variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report as per recommendation 4.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Background
1. The Harbour Walkway is an ambitious and complex project to install a 400m floating path from Totterdown Basin (Cattle Market Road) to the ferry stop by Valentine’s Bridge. Providing a continuous pedestrian and cycling route along the harbour, it will significantly improve access and active travel in this part of the Bristol Temple Quarter regeneration area and is in line with the Council’s ‘Quayside Walkways’ planning policy. 2. Funding of £3.5m was allocated to the project from the capital receipts from the sale of the former Post Office site at Temple Meads. The site was sold to University of Bristol (UoB) for the Temple Quarter Enterprise Campus (TQEC) and delivery of the Harbour Walkway is a condition of the land sale agreement. 3. The part-complete project has faced a number of design and delivery challenges which have caused delays and cost pressures. Despite the issues summarised below, good progress has been made in the past year in delivering the scheme. All the foundations have been installed, along with most of the posts, and the floating pontoons have been constructed in Spain with delivery planned for February 2025. The current timetable for the scheme to be completed, including the bank stabilisation, is November 2025.
1 Version January 2024
OFFICIAL Contract sum 4. The contract to build the walkway was let to Knights Brown (KB) with a contract start date in May 2018 and a contract price of £2.46m. However, the contract does not include for inflation, and as with other capital projects this has been significant over the period of the contract.
Cost increases 5. To date, cost increases totalling £2.7m have been approved. These have been for a variety of reasons, including: delays to the dredging of the harbour; unavailability of land needed for construction work; issues relating to installation of materials on the unstable harbour bed; and investigation and design work in relation to the harbour bank which collapsed in April 2024 (representing over 50% of the increase). The costs associated with these challenges have been exacerbated by the generally inflationary environment in which the project has been progressed. 6. Contractually, the council has sought ‘delay damages’ from the contractor because the project has not progressed to programme. This has introduced further pressure on the deliverability of the project. 7. As identified by KB and the NEC PM (New Engineering Contract Project Manager (Jacobs)), there are other potential increases in cost ahead, including the expectation of the District Heat Networks to work in the same areas at the same time and continuing access to land. 8. This paper seeks approval for a new funding approach so that the project can be completed and deliver the walking and cycling benefits to connect the city to this important regeneration area.
Additional funding 9. The contract has had a variety of issues which have impacted on its implementation and cost. The full details of these, and the proposed additional funding, are set out in the Exempt Appendix E. 10. The Harbour Walkway has been put forward as a potential over-programming scheme for the City
2 Version January 2024
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.