City Region Sustainable Transport Settlement (CRSTS) Project Delivery
ApprovedCommittee5 papers
Transport & Connectivity Policy Committee approved this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.
That the Committee for Transport and Connectivity: 1. Approved the commencement of procurement for the CRSTS programme of projects listed in Appendix A1, on the basis that a further report will be brought back to this Committee to seek approval of business cases and authority to award contracts. 2. Approved the commencement of early works in advance of full business case approval and wider project construction tender as outlined in this report and Appendix A2. 3. Authorised the Executive Director of Growth & Regeneration, in consultation with the Chair of the Transport & Connectivity to take all steps required to procure and award contracts for the construction of early works as detailed in Appendix A2.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Committee Report
PURPOSE: Final Decision Report
KEY OR NON-KEY DECISION: Key decision over £500k spend/save & impacts more than 2 wards
COMMITTEE: Transport and Connectivity Committee
DATE: 06 February 2025
TITLE: City Region Sustainable Transport Settlements (CRSTS) Project Delivery Ward(s): Citywide.
Officer presenting the report: Adam Crowther Job title: Head of City Transport
Committee Chair: Councillor Ed Plowden Executive Director lead: John Smith: Executive Director for Growth & Regeneration
Proposal origin: BCC Staff
Purpose of Report:.
To update on delivery of CRSTS projects in Bristol and seek approval for two elements of programme acceleration: a) The commencement of procurement for project construction before business case approval and b) The commencement of some specific ‘early works’ to enable early benefits realisation and derisk project overruns.
Evidence Base / Options to consider:
1. The CRSTS programme is a sub-regional programme of Sustainable Transport projects in Bristol funded by the Government over a 5 year period, ending in March 2027. Bristol’s programme is circa £200m including our Strategic Corridors programme and our Liveable Neighbourhood schemes in East and South Bristol.
2. The timescales for delivery of a large programme in line with these Government requirements does place a challenge on authorities to deliver at pace. At present, the government position is a very strict deadline around completion of CRSTS projects and there is a risk that projects completing after that deadline could require alternative funding arrangements. This is affecting all the authorities in the region and we have been working collectively with the Combined Authority (CA) on options for acceleration, to try to realise some early benefits and to derisk the potential for schemes to overrun the government deadlines.
3. Among these acceleration plans is the proposal to programme some elements concurrently rather than sequentially, to reduce overall programme length. We are therefore proposing to run procurement of some projects concurrently with the pathway for approval of their business cases, both at BCC and at the CA. The approval to procure does not assume, or commit to, business case 1 Version January 2024 approval, which will be sought from the Committee and the CA before contract for works is awarded. This will not necessarily apply to all projects in the programme but this report seeks approval to apply this across the programme, so that there is flexibility should this be required. The full programme is listed in Appendix A1. This also identifies those projects within the programme where will currently anticipate concurrent procurement and business case approval processes.
4. The second acceleration proposal is the commencement of early works. These are discrete parts of the wider project that could be procured and construction commenced in advance of the full business case approval and wider project construction tender. Starting construction of some elements early will derisk the overall delivery of the programme within the given timescales. Commencing these works early will also help to avoid the further compression of our construction timetable so that fewer works are completed at the same time across the programme. This will mitigate the potential negative network impact of the construction period. As above, the early works are discrete packages of work that are not dependent on the delivery of the whole project contained with the relevant business case. As such, it would not constrain Committee’s ability to revise or reject the project business case as a whole. The proposed early works are described in Appendix A2. Delivery will be subject to Committee approval and approval from the CA.
Officer Recommendations: -
That the Committee for Transport and Connectivity:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.