Resolved
The Policy Committee for Transport and Connectivity noted the report and agreed with the approach and next steps outlined in the paper
Transport & Connectivity Policy Committee noted this item on Thursday 15 May 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Policy Committee for Transport and Connectivity noted the report and agreed with the approach and next steps outlined in the paper
1. To update Committee members on progress to date with the Parking and Kerbside Task and Finish Group.
Evidence Base / Context
1. On 24 October 2024 the Transport and Connectivity (T&C) Policy Committee agreed the terms of reference for a Parking and Kerbside Task and Finish Group.
2. The stated purpose of the group was to provide input and steer the development of a Parking and Kerbside Strategy.
3. Since 13 November the group has met a total of 7 times and – at the time of writing – has 2 meetings remaining in April and May.
4. Alongside its core aim of aiding in the development of the strategy the group has also dedicated 2 meetings to reviewing and agreeing urgent financial business pertaining to parking policy.
5. As a result – and barring the introductory meeting – the group has had 4 x 60-90min sessions to discuss the development of the strategy with a further two sessions to follow.
6. The meeting outputs and decisions can be summarised as follows:
7. 13 November: Introduction, forward plan discussion, parking charges discussion
8. 27 November: Presentation received from Lambeth Council on the development of their kerbside strategy
9. 11 December: Presentation on transport policy context to the strategy, key kerbside challenges, discussion and agreement confirming remit and objectives of the group across the meeting series
1 Version January 2024 10. 8 January: Agreed the scope of the strategy
11. 22 January: Cancelled (rearranged for May)
12. 12 February: Parking charges discussion
13. 26 February: Agreed draft objectives of the strategy
14. 12 March: Presentation from AppyWay on producing a baseline assessment of kerbside space; stakeholder mapping undertaken
15. April: Stakeholder presentations
16. May: Finalise and agree project brief.
17. Moving forward, the group has provided a strong mandate for the development of the kerbside strategy including:
18. Agreeing the case for change: there was broad agreement in the group that the current utilisation of the kerbside is not sustainable, equitable, safe or desirable and is not aligned with the Bristol Transport Strategy and supporting policy. There is a strong case for reallocating some kerbside space away from parking and parking infrastructure – which makes up circa 90% of kerbside space – to other uses such as tree planting, car clubs, EV charge points and informal crossing points.
19. Agreeing the scope: there was broad agreement that the kerbside strategy would predominantly focus on neighbourhood areas where transport plans were less defined. It was discussed that some kerbside initiatives would be more applicable to certain areas over others and that distinguishing between these different needs in the strategy would be important. One example of this is cycle hangars which are more relevant in areas of high housing density. Members acknowledged that the strategy would focus on the ‘road side’ of the kerbside and that policy relating to parking fees and resident parking schemes would be covered by other papers and documents. This includes a paper heading to a future committee on RPS policy, as well as work being undertaken on the Transport Investment Strategy which will set out the financial evidence base to inform updated parking policy.
20. Agreeing the objectives: the group reviewed and agreed the following objectives for the strategy noting that these would be further refined as the work progresses and stakeholder input is sought
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Kerbside and Parking Task and Finish GroupReport | 117 KB | DownloadRead as text |
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... | Approved | Open |
| 17 Sep 2026 | Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... | Decided | Open |
| 17 Sep 2026 | Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... | Agreed | Open |
| 17 Sep 2026 | Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. | Noted | Open |
| 17 Sep 2026 | 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.