AI summaryBristol councillors approved two bids worth about £85 million to the Department for Transport Structures Fund, targeting Cumberland Basin and the New Cut river walls, with a 3 August 2026 submission deadline.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo be finalised and submitted by 3 August 2026
MoneyAbout £85m total soughtMatch funding via prudential borrowing
What happens nextBids submitted by 3 August 2026DfT outcome expected Autumn 2026
Who it affectsHighway bridges and river wallsCumberland Basin and New Cut, Bristol
What was decided
The committee approved finalising and submitting two bids to the Department for Transport Structures Fund by 3 August 2026. Report P26
The Executive Director for Growth and Regeneration, in consultation with the committee chair, was authorised to submit the bids, accept funding if successful, and to procure, extend, vary or award related contracts. Report P28
Why
Highway maintenance spending fell 45 per cent between 2016/17 and 2021/22, and several structures are deteriorating, with the Avon Fixed Bridge at risk of full or partial closure within 12 years. Report P3, P14
Without investment, the council estimates a £5-10 billion economic cost by 2040 and 100,000 daily trips at risk of disruption, making the DfT fund a rare chance to leverage external money. Report P4, P6, P44
What happens next
Officers will finalise and submit both bids by 3 August 2026, withholding match-funding details for competitive reasons, and share working drafts with councillors in advance. Report P16, P18, P19, P20
If bids succeed, match funding approval and prudential borrowing must be brought back to Full Council through medium-term financial planning, and projects must be delivered by March 2030. Report P10, P41, P44, P46
The money
£40m Proposed DfT bid for Cumberland Basin, alongside match funding Report P16
£45m Proposed DfT bid for New Cut river walls, alongside match funding Report P18
approximately £85m Combined value of the two Structures Fund bids Report P39
£1m Cabinet-approved funding (September 2023) for Cumberland Basin investigation and feasibility work Report P15
£11.514 Cabinet-approved funding (9 March 2021) to stabilise and repair Cumberland Road wall Report P18
£21.6m to £11.8M Net highway maintenance spend, 2016/17 to 2021/22 (a 45% fall) Report P3
£1bn Total government spending committed to the DfT Structures Fund up to 2030 Report P6
£5-10 billion Estimated economic cost by 2040 of managed decline of structural assets Report P4
Options considered
Chosen: Submit two DfT Structures Fund bids for Cumberland Basin and New Cut river walls. Strongest strategic fit, scheme readiness and deliverability among candidates Report P5, P8, P26
Rejected: Cumberland Basin sub-bid for Avon Fixed Bridge repairs only. Would not address Plimsoll and Junction Lock issues, reducing efficiency and increasing disruption Report P21
Rejected: Single Cumberland Basin bid resolving all complex issues at once (over £110m). Weaker-case structures would dilute the bid and inflate cost, reducing chances of success Report P22
Rejected: St Phillips Causeway as the second exceptional bid. Strategic case weaker and less urgent than Cumberland Basin and New Cut river walls Report P23
Rejected: Do nothing. Misses a major funding opportunity for deteriorating assets; case for investment supported by finance advice Report P24, P44
Implications
Financial: Match funding is currently unfunded and assumed to come from prudential borrowing, creating borrowing costs and revenue implications to be approved in future medium-term financial planning. Report P39, P41, P44
Financial: If bids fail, the council would still face circa £85m of essential structural work, unaffordable within existing capital programmes. Report P42
Legal: Legal must be consulted on subsidy control, procurement, grant terms (including possible clawback) and ensuring works are delivered by March 2030. Report P46
Risk: Without investment, reactive maintenance is likely to be more expensive, and partial or full closure of Cumberland Basin could create emergency works costs, traffic management costs and safety liabilities. Report P43
Equalities: Public consultation not undertaken as repairs are essential; effort will focus on advance warning, limiting disruption and effective diversions for all modes of transport. Report P34
Other: No IT or HR implications identified by officers. Report P49, P51
Who and where
Residents, visitors and sub-regional travellers using Cumberland Basin (over 51,000 vehicles a day) and surrounding routes Report P13
Bristol City Council and the Harbour undertaking, which would otherwise bear the cost of structural deterioration Report P42, P43
Suppliers delivering design, investigation and construction contracts for the schemes Report P28
Timeline
15 April 2026: Department for Transport announces the Structures Fund, committing £1bn to 2030 Report P6
25 May 2026: Deadline to notify DfT of intention to submit a bid Report P12
9 July 2026: Transport and Connectivity Policy Committee considers the bids Report P1
3 August 2026: Deadline for submitting the two bids to the DfT Report P1, P12
Autumn 2026: DfT expected to announce successful bids Report P12
March 2030: All funded projects must be delivered by this date Report P10
Plain English for the jargon
Structures Fund: A Department for Transport grant programme, announced 15 April 2026, providing £1bn to 2030 for repair of structures local authorities cannot otherwise afford.
Match funding: Local financial contribution required alongside any DfT grant; larger contributions are viewed more favourably and may be provided through prudential borrowing.
Prudential borrowing: Council borrowing undertaken under the prudential framework, with associated revenue costs for interest and repayment.
Cumberland Basin: A strategic road complex in Bristol carrying over 51,000 vehicles a day, including the Avon Fixed Bridge, Plimsoll Bridge and Junction Lock Bridge.
New Cut river walls: Deteriorating river walls along the New Cut in Bristol, with recent failures at York Road and Cumberland Road.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
That the Committee for Transport and Connectivity: 1. Approved the proposal to finalise and submit two bids to the Department for Transport’s ‘Structures Fund’ by 3 August 2026 as outlined in this report. 2. Authorised the Executive Director Growth and Regeneration, in consultation with the Chair of Transport and Connectivity Committee, to take all steps required to finalise and submit the bids and if successful to accept and spend the funding as outlined in this report. Contractual: 1. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport Connectivity Committee to take all steps to required to procure/extend/vary and award contracts in-line with the procurement routes and maximum budget envelopes outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
1. To seek approval to submit two bids to the Department for Transport’s (DfT) ‘Structures Fund’ by 3 August 2026 and if successful, approval to delegate authority to the Executive Director for Growth and Regeneration in consultation with the Committee Chair for Transport and Connectivity to agree to funding terms and deliver the project, including entering into any necessary contracts with suppliers.
Evidence Base
1. The public highway is the council’s single biggest asset and is essential in keeping the city moving and the economy growing. It comprises of over 751 miles of on-road and off-road footways, cycleways, bridges, subways, streetlights and other critical infrastructure, and funding received for its repair and renewal has failed to keep pace with inflation nor what is required. For instance, net expenditure on maintenance decreased by 45% (£21.6m to £11.8M) between 2016/17 and 2021/22. Further information on the ‘funding gap’ for our highway assets can be found in Appendix A.
2. In this context many of our structural assets require urgent investment to stop them falling into a state of disrepair that requires more expensive remediation, while at the same time causing delays and disruption within Bristol and across the wider sub-region. Recent analysis of the impact of managing the decline of our assets to the point of closure estimates an economic cost of between £5-10 billion by 2040 and 100,000 daily trips at risk of disruption.
3. The Department for Transport’s (DfT) ‘Structures Fund’ provides an opportunity to bring much needed investment into two strategic assets: the Cumberland Basin complex and the New Cut river walls. Template approved October 25
OFFICIAL 4. The DfT Structures Fund was announced on 15 April 2026 and commits £1bn of government spending up to 2030 to repair structures that are otherwise unaffordable from local authority budgets.
5. 1 bid per local authority is permitted, but a second bid is permitted under exceptional circumstances. The council intends to submit a second exceptional bid for the New Cut river walls as outlined above.
6. To determine the priority of bids the council undertook an assessment of the various structures that could qualify for funding taking into account ‘strategic fit’ with the bid criteria, level of scheme development and deliverability. The Cumberland Basin had the strongest case, followed by the New Cut river walls.
7. There is no minimum or maximum level of funding that can be applied for, but local match-funding contributions are required. While no level is set, bids with a larger match-funding contribution will be looked upon more favourably.
8. All projects must be delivered by March 2030.
9. Broadly speaking bids will be assessed on their ability to meet the objectives of the fund, their value for money, their cost and their deliverability.
10. The deadline for submission is 3 August 2026, although local authorities were asked to notify of their intention to submit – including high level scheme details – by 25 May 2026 at the latest. The DfT is expected to announce successful bids in Autumn 2026.
11. Cumberland Basin is an important strategic route carrying over 51,000 vehicles a day and supporting cross city and sub-regional connections including traffic from the A4, A38 and M5. If there were disruption on the M5 crossing of the River Avon the Cumberland Basin would be the next major strategic crossing for the sub-region.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.