Transport & Connectivity Policy Committee, Thursday 9 July 2026 at 4.30pm

East Bristol Liveable Neighbourhood Full Business Case

Approved Committee 6 papers

AI summaryTransport and Connectivity Committee approves the Full Business Case for the East Bristol Liveable Neighbourhood, making the scheme permanent and submitting it to the MCA for CRSTS funding, with a £500,000 capital bid ring-fenced for mitigation on surrounding roads.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMakes EBLN scheme permanent, subject to MCA approval
Money£10,102,033.97Total scheme cost, mostly CRSTS funded
What happens nextSubmit to MCA, deliver permanent schemeSubject to design, quality assurance, statutory consultation
Who it affectsEast Bristol residents and road usersPlus surrounding roads like Crews Hole Road

What was decided

The committee approved the Full Business Case and its submission to the West of England Mayoral Combined Authority for City Region Sustainable Transport Settlement funding, and, subject to MCA approval, accepted the funding to make the East Bristol Liveable Neighbourhood scheme permanent. Report P19

The committee approved acceptance and investment of match funding, including possibly more Section 106 money or alternative sources, within the overall budget envelope, and authorised the Executive Director for Growth and Regeneration, in consultation with the committee chair, to make those decisions. Report P19

Officers were instructed to develop a £500,000 capital budget bid for mitigations on surrounding roads shown to be affected by traffic changes, such as Crews Hole Road and Troopers Hill Road; to bring a paper on a citywide bus gate and camera-controlled modal filter exemptions policy; and to keep the Pile Marsh Bus Gate under review before and after the Blackswarth Road/Church Road junction redesign.

Why

Independent monitoring of the trial scheme found a general reduction in motorised traffic on internal roads, an overall increase in active travel, and continuing bus patronage growth on the corridor. Report P9

A Benefit-Cost Ratio of 4.33 was calculated, classed as very high value for money under the Department for Transport framework, with health benefits making up just under half of total benefits. Report P9

The scheme supports the council's corporate aims of healthy neighbourhoods, greener and safer travel, and accelerating climate action, and helps meet the target to reduce personal car miles by 40 per cent by 2030. Report P22, P15

What happens next

The Executive Director for Growth and Regeneration, in consultation with the committee chair, will submit the Full Business Case to the MCA, accept and spend the funding, and procure and award any contracts needed, including those over the key decision threshold. Report P19

Statutory consultation will be carried out on Traffic Regulation Order-dependent elements, such as extending double yellow lines and introducing one-ways on Derby Street, and informal engagement will inform final public realm layouts at Victoria Avenue and Ducie Road. Report P28

A £500,000 capital budget bid for mitigations on surrounding roads will go through the council's capital programme prioritisation and budget-setting process; officers will report back on a citywide bus gate exemptions policy; and the Pile Marsh Bus Gate will continue to be monitored.

The money

  • £10,102,033.97 Total scheme cost, including all spend to date and the £542,001.26 of historic 2021-23 IF/TCF spend Report P31
  • £9,398,962.53 CRSTS funding figure, including the £1,009,846.90 already approved and released via DN CRSTS066 Report P31
  • £161,070.18 Section 106 match funding contribution Report P31
  • £542,001.26 Historic IF/TCF capital spend (2021-23) included in total Report P31
  • £1,009,846.90 Already approved and released by WECA via DN CRSTS066 Report P31
  • £1.55 million MCA funding confirmed for development of the trial scheme and Full Business Case Report P34
  • £3.2 million Already spent by the council as of 27 March 2026 Report P34
  • £3.5 million Expected spend prior to completion of the Full Business Case Report P34
  • £9.941 million Total to be funded by the MCA (TCF feasibility plus CRSTS) Report P34
  • £6.4 million Requested from the MCA for delivery of the permanent scheme, including 25% contingency on unspent costs Report P34
  • £500,000 Capital budget bid to be developed for traffic mitigations on surrounding roads
  • circa £2m Alternative funding that would need to be found if the scheme is not taken forward, to cover revenue reversion of unfunded CRSTS spend Report P15

Options considered

  • Chosen: Proceed with the permanent scheme as set out in the Full Business Case. Highest value for money with a BCR of 4.33; meets transport, health and climate targets; supports corporate strategy; trial monitoring shows intended impacts. Report P9, P22, P25
  • Rejected: Do not proceed with the project. Would risk revenue reversion of approximately £2m of unfunded CRSTS spend, require alternative funding, and incur the cost of removing the trial scheme; would not meet climate and transport targets. Report P15
  • Rejected: Reduce or otherwise alter the scope of the scheme. Detailed design already incorporates feedback; further changes are not considered necessary and could compromise outcomes, with significant delays and cost increases. Schemes of this type need to be comprehensive area-wide interventions to be effective. Report P15, P17

Implications

  • Financial: Total scheme cost estimated at £10,102,033.97, with approximately £9.941 million from the MCA and around £0.161 million from Section 106; the council had already spent £3.2 million as of 27 March 2026, temporarily covered by Clean Air Zone operational surplus. Report P31, P34
  • Legal: Any procurement must comply with the Procurement Act 2023 and the council's own procurement rules; statutory consultation responses on Traffic Regulation Order-dependent elements must be conscientiously taken into account; the Public Sector Equality duty applies. Report P36, P37
  • Equalities: The fifth Equality Impact Assessment has been undertaken since 2022; a total of 525 bus gate exemptions had been granted by end of May 2026, including for blue badge holders, professional carers, and 108 people added in 2026 for residents near Pile Marsh and Wellspring Surgery patients. Report P11
  • Climate: The scheme contributes to the council's target to reduce personal car miles by 40 per cent by 2030, with permanent planting, reduced motor traffic, and active travel uptake expected to cut environmental impact and improve climate resilience. Report P15, P22, P25
  • Risk: Risks noted include adverse publicity and protest activity at Traffic Regulation Order stage if the scheme is made permanent; HGV volumes have increased overall and will continue to be monitored; some surrounding roads such as Crews Hole Road and Troopers Hill Road have seen increased traffic volumes. Report P9, P15
  • Staffing: Officers were reported as having no HR implications arising from the report. Report P41, P42

Who and where

  • Residents within the East Bristol Liveable Neighbourhood area Report P1, P9
  • Blue badge holders, disabled residents, and professional carers using bus gates Report P11
  • Local businesses in the scheme area, with ongoing engagement and grants Report P9
  • Bus passengers, with patronage noted as continuing to grow on the corridor Report P9, P11
  • Pedestrians, cyclists and wheelers using the scheme's active travel routes Report P1, P9, P25
  • Residents and road users on surrounding roads including Crews Hole Road and Troopers Hill Road, where traffic volumes have increased Report P9
  • Pupils and congregation at the local school and church near the Pile Marsh Bus Gate

Timeline

  • 4 April 2023: Outline Business Case approved by Cabinet Report P9
  • 3 September 2024: Executive Director for Growth and Regeneration approved delivery of trial scheme works Report P9
  • 29 September to 7 November 2025: Public engagement exercise for the Full Business Case undertaken Report P9, P27
  • February 2026: Equality Impact Assessment published (fifth iteration since 2022) Report P11
  • February 2026: Transport and Connectivity Committee approved use of Clean Air Zone operational surplus to temporarily cover overspend Report P34
  • 27 March 2026: Date used for cumulative spend figure of £3.2 million Report P34
  • End of May 2026: 525 bus gate exemptions granted in total, including 108 new exemptions Report P11
  • 1 June 2026: Legal advice dated Report P38
  • 2 June 2026: Finance Business Partner advice dated Report P35
  • 9 July 2026: Transport and Connectivity Policy Committee meeting

Plain English for the jargon

  • EBLN: East Bristol Liveable Neighbourhood
  • FBC: Full Business Case
  • OBC: Outline Business Case
  • MCA: West of England Mayoral Combined Authority
  • CRSTS: City Region Sustainable Transport Settlement, a government capital funding programme
  • BCR: Benefit-Cost Ratio, used to assess value for money
  • S106: Section 106 planning obligations, used as match funding
  • TRO: Traffic Regulation Order, the legal mechanism for certain road restrictions
  • IF/TCF: Integrated Fund / Transport Capital Fund, historic capital funding streams
  • CAZ: Clean Air Zone, whose operational surplus is currently temporarily covering scheme overspend
  • LTN: Low Traffic Neighbourhood
  • Modal filter: A physical feature that restricts motor vehicle movement while allowing walking, cycling and other modes
  • Bus gate: A short stretch of road restricted to buses, cycles and other permitted vehicles, enforced by camera
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

That the Committee for Transport and Connectivity: 1. Approved the Full Business Case (FBC) and its submission to the West of England Mayoral Combined Authority (MCA) for City Region Sustainable Transport Settlement (CRSTS) funding and, subject to MCA approval, approves the acceptance and investment of the funding to make the East Bristol Liveable Neighbourhood scheme permanent. 2. Approved the acceptance and investment of match funding in relation to this project (noting that this may include use of a greater amount of Section 106 funding if this becomes available during the project’s lifecycle; or use of alternative match funding, in the event that S106 contributions reduce and/or other sources become available), subject to the overall approved budget envelope. 3. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to approve a greater amount of Section 106 funding should this become available or alternative match funding if appropriate. 4. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to take all steps required to submit the full business case to the MCA and to deliver the permanent scheme (subject to further detailed design work, internal quality assurance processes and applicable statutory consultation). 5. Instructed transport officers to work with the finance and capital officers as part of the capital budget setting development, to include for the emerging capital programme prioritisation work a capital budget bid of £500,000 (this will then be subject to programme funding sufficiency, prioritisation and approval via the budget setting process for the relevant financial year) to deliver mitigations to surrounding roads and areas demonstrably impacted by changes to traffic patterns following completion of the scheme. This will include roads such as Crews Hole Rd and Troopers Hill Rd that have been shown to have increased traffic volumes and other impacted roads will also be considered. 6. Instructed transport officers to bring a paper to this committee on proposals for a citywide policy for exemptions for bus gate and camera controlled modal filters exemptions, informed by good practice from around the country; noting but not limited to the temporary exemptions agreed in EBLN for groups such as Blue Badge Holders, carers and other groups. 7. Instructed officers to keep monitoring the layout, location of and need for the Pile Marsh Bus Gate before and after the redesign of the Blackswarth /Church Roads junction, which is to be delivered as a priority. During this time to work with local residents , the school and church to consider the need for specific additional exemptions for this bus gate. Contractual: 1. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to take all steps required to accept and spend the funding including to procure and award contracts which may be over the key decision threshold, to deliver the permanent scheme, in line with the maximum budget envelope outlined in this report. 2. Authorised the Executive ...
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Purpose of report

1. To seek approval to make the East Bristol Liveable Neighbourhood (EBLN) scheme permanent, to enable improvements such as: (a) Optimising road space reallocation (e.g. junction changes that could not be delivered during the trial phase) (b) Installing permanent infrastructure to maximise benefits (e.g. accessibility enhancements, including measures suggested by the West of England Centre for Inclusive Living as part of their audit of the trial scheme, such as more dropped kerbs, tactile paving at crossing points and seating; a full list of their recommendations can be found in the Full Business Case’s Appendix B) and eliminate issues that are inherent with temporary infrastructure (e.g. planters being movable, motorists sometimes physically-but-illegally being able to drive on pavements to get around planters) (c) Permanent planting (trees and other permanent planting; noting that the current temporary planters would not be a feature of the final scheme), and associated long-term benefits (d) Other enhanced and additional public realm provision (e.g. improved street lighting) The illustration below shows an example modal filter (at Beaufort Road) as it is currently alongside how it is proposed to be, to demonstrate the kind of improvements that making the scheme permanent would bring:

Template approved March 25

OFFICIAL The drawing below shows the proposed permanent layout for the Chalks Road/Church Road junction – where the enabling of further turning movements would simplify routes for vehicles accessing the scheme area and reduce the length of diversions that people might need to drive to reach the strategic road network:

The Full Business Case’s Appendix L contains drawings that show all proposed permanent layouts. Proposed permanent measures (including those already in place on a trial basis) are as follows:

Location Design Type(s) Chalks Road / Church Road New crossings Blackswarth Road / Pile Marsh New crossings Crews Hole Road / Conham Road New crossings Glebe Road Basic modal filter The Avenue Basic modal filter Template approved March 25

OFFICIAL Beaufort Road / Northcote Basic modal filter Wicket Lane Basic modal filter Ducie Road Bridge Basic modal filter Lincoln Street Basic modal filter Victoria Avenue East Pocket park plus Ducie Road / Barton Hill Road Pocket park plus Barnes Street Pocket park Cobden Street Pocket park Avonvale Road / Marsh Lane Bus gate plus Avonvale Road / Pile Marsh Bus gate plus Marsh Lane / Glendare Street Pedestrian improvements Derby Street One ways

2. To seek approval of the Full Business Case (FBC) and its submission to the West of England Mayoral Combined Authority (MCA) for City Region Sustainable Transport Settlement (CRSTS) funding and, subject to MCA approval, approval to accept and spend the funding to make the East Bristol Liveable Neighbourhood scheme permanent.

Evidence Base:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App A1C: East Bristol Liveable Neighbourhood Co-develop Engagement report: Executive summaryAppendix 236 KB Download
PDF
App A1D1: East Bristol Liveable Neighbourhood pilot scheme: Options Assessment note V1Appendix 438 KB Download
PDF
EBLN Full Business CaseAppendix A1 4 MB Download
PDF
EBLN Monitoring ReportAppendix A1A 15 MB Download
PDF
Combined App A1B (incl Appendices A-G)Appendix 11 MB Download
PDF
East Bristol Liveable Neighbourhood Full Business CaseReport 550 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
EP
Councillor Ed PlowdenChair, present
NC
Councillor Nicholas CoombesCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
SR
Councillor Serena RalstonCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
TW
Councillor Toby WellsCommittee Member, present
MW
Councillor Mark WestonCommittee Member, present
JS
John SmithOfficer, expected
AH
Alex HearnOfficer, expected
PM
Patsy MellorOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. East Bristol Liveable Neighbourhood Full Business CaseThis decision
  2. Adult Social Care Review of East Bristol Intermediate Care CentreApproved
  3. East Bristol Liveable Neighbourhood Pilot Outline Business CaseNoted
  4. North and East Bristol Universal Business Support ProjectApproved
  5. University of Bristol – Second Campus at Temple Meads EastApproved

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Supported Bus Services Task and Finish GroupThat the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Ser... Agreed Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies