Cabinet: Approved the project sum value, the extent of works and programme detailed within part B of this report. Delegate authority to the Executive Director of Education in consultation with the Director of Law and Governance to negotiate and execute the building contract. Reasons for recommendation(s): Approval of the works is required in order for the Whitefield Centre project to progress to manufacture and construction phase. Key considerations within this document have informed both the scope and the methodology for carrying out the works as proposed. Alternative options considered and rejected: Delay instructing the contract: This would delay overall Whitefield Centre completion date by two months as Cabinet approval cannot be sourced in the August cycle. This would prevent the school from receiving the additional intake of pupils in and they would have to be housed in alternative provision outside the Borough of Bury. This would also push the works into the winter months, potentially extending the duration on site and associated costs of construction. Seek an alternative solution for the contract: The Council have considered alternative options to deliver the additional accommodation within the timescales provided. This included use of other Council owned property, and the use of modular accommodation on the existing site, partial reconfiguration only. No other Council owned property could meet the needs of the school within the available timescale. Partial reconfiguration would not provide the classroom accommodation the school requires and there was insufficient space within the school to site modular accommodation or extend. A split site was also discounted as the school would not have the staffing and safeguarding arrangement available to accommodate this. None of alternative options explored where able to deliver the additional accommodation with the available timescales.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Report to: Cabinet – PART A Date: 16 July 2024 Subject: PRU-Phase 2-Whitefield Centre-PRU – Interim Arrangements. Report of Deputy Leader and Cabinet Member for Children and Young People
Summary 1.1 The purpose of this report is to request Cabinet approval of the project sum for works in relation to the Pupil Referral Unit, following conclusion of the tender exercise, and specifically in relation to the PRU’s Whitefield Centre building. These are phase 2 of works following the relocation of the main PRU building from Spring Lane to the New Kershaw Centre.
1.2Approval will ensure the preferred contractor P McVey Building Systems are able to proceed to manufacture and construction. Plans and a proposed programme are appended to this paper. These will inform the proposed delivery of the works to completion. The works have been fully market tested and independently verified via a formal tender process.
1.3The Whitefield Centre phase 2 works are in addition to the phase 1 works, which was given Cabinet Approval in December 2023.
1.4The Whitefield Centre works will be funded from the Children’s Services Capital Programme, using grant funding allocated by the Department for Education.
Recommendation(s) 2.1 Approve the project sum value, the extent of works and programme detailed within part B of this report.
2.2That Cabinet delegate authority to the Executive Director of Education in consultation with the Director of Law and Governance to negotiate and execute the building contract.
Reasons for recommendation(s) 3.1 Approval of the works is required in order for the Whitefield Centre project to progress to manufacture and construction phase. Key considerations within this document have informed both the scope and the methodology for carrying out the works as proposed.
Alternative options considered and rejected 4.1 Delay instructing the contract: This would delay overall Whitefield Centre completion date by two months as Cabinet approval cannot be sourced in the August cycle. This would prevent the school from receiving the additional intake of pupils in and they would have to be housed in alternative provision outside the Borough of Bury. This would also push the works into the winter months, potentially extending the duration on site and associated costs of construction. 4.2 Seek an alternative solution for the contract: The Council have considered alternative options to deliver the additional accommodation within the timescales provided. This included use of other Council owned property, and the use of modular accommodation on the existing site, partial reconfiguration only. No other Council owned property could meet the needs of the school within the available timescale. Partial reconfiguration would not provide the classroom accommodation the school requires and there was insufficient space within the school to site modular accommodation or extend. A split site was also discounted as the school would not have the staffing and safeguarding arrangement available to accommodate this. None of alternative options explored where able to deliver the additional accommodation with the available timescales.
_________________________________________________________ Report Author and Contact Details: Name: Samantha Horrocks / Ian D’Arcy (BGI) Position: Asset Manager Department: Children’s Services E-mail: [email protected] ________________________________________________________________ Background 5.1 In December 2023 cabinet approved the relocation of Spring Lane School to the New Kershaw Centre (NKC). This was to enable the construction of the new secondary school to proceed, to be sited on land off Spring Lane, Radcliffe.
5.2The relocation of Spring Lane School to New Kershaw Centre (phase 1) was required before the 1st March 2024 in order to provide DfE with vacant possession of the site. This date was achieved with the PRU relocating at the end of February 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.