Bury Metropolitan Borough Council
Cabinet, Tuesday 16 July 2024 at 5.00pm

PRU Phase 2 Whitefield Centre - Part A

Approved Executive 2 papers

Cabinet approved this item on Tuesday 16 July 2024. Below is the council's own wording, with the papers it was decided on.

ItemCA.191

Resolved

Cabinet: Approved the project sum value, the extent of works and programme detailed within part B of this report. Delegate authority to the Executive Director of Education in consultation with the Director of Law and Governance to negotiate and execute the building contract. Reasons for recommendation(s): Approval of the works is required in order for the Whitefield Centre project to progress to manufacture and construction phase. Key considerations within this document have informed both the scope and the methodology for carrying out the works as proposed. Alternative options considered and rejected: Delay instructing the contract: This would delay overall Whitefield Centre completion date by two months as Cabinet approval cannot be sourced in the August cycle. This would prevent the school from receiving the additional intake of pupils in and they would have to be housed in alternative provision outside the Borough of Bury. This would also push the works into the winter months, potentially extending the duration on site and associated costs of construction. Seek an alternative solution for the contract: The Council have considered alternative options to deliver the additional accommodation within the timescales provided. This included use of other Council owned property, and the use of modular accommodation on the existing site, partial reconfiguration only. No other Council owned property could meet the needs of the school within the available timescale. Partial reconfiguration would not provide the classroom accommodation the school requires and there was insufficient space within the school to site modular accommodation or extend. A split site was also discounted as the school would not have the staffing and safeguarding arrangement available to accommodate this. None of alternative options explored where able to deliver the additional accommodation with the available timescales.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Report to: Cabinet – PART A Date: 16 July 2024 Subject: PRU-Phase 2-Whitefield Centre-PRU – Interim Arrangements. Report of Deputy Leader and Cabinet Member for Children and Young People

Summary 1.1 The purpose of this report is to request Cabinet approval of the project sum for works in relation to the Pupil Referral Unit, following conclusion of the tender exercise, and specifically in relation to the PRU’s Whitefield Centre building. These are phase 2 of works following the relocation of the main PRU building from Spring Lane to the New Kershaw Centre.

1.2Approval will ensure the preferred contractor P McVey Building Systems are able to proceed to manufacture and construction. Plans and a proposed programme are appended to this paper. These will inform the proposed delivery of the works to completion. The works have been fully market tested and independently verified via a formal tender process.

1.3The Whitefield Centre phase 2 works are in addition to the phase 1 works, which was given Cabinet Approval in December 2023.

1.4The Whitefield Centre works will be funded from the Children’s Services Capital Programme, using grant funding allocated by the Department for Education.

Recommendation(s) 2.1 Approve the project sum value, the extent of works and programme detailed within part B of this report.

2.2That Cabinet delegate authority to the Executive Director of Education in consultation with the Director of Law and Governance to negotiate and execute the building contract.

Reasons for recommendation(s) 3.1 Approval of the works is required in order for the Whitefield Centre project to progress to manufacture and construction phase. Key considerations within this document have informed both the scope and the methodology for carrying out the works as proposed.

Alternative options considered and rejected 4.1 Delay instructing the contract: This would delay overall Whitefield Centre completion date by two months as Cabinet approval cannot be sourced in the August cycle. This would prevent the school from receiving the additional intake of pupils in and they would have to be housed in alternative provision outside the Borough of Bury. This would also push the works into the winter months, potentially extending the duration on site and associated costs of construction. 4.2 Seek an alternative solution for the contract: The Council have considered alternative options to deliver the additional accommodation within the timescales provided. This included use of other Council owned property, and the use of modular accommodation on the existing site, partial reconfiguration only. No other Council owned property could meet the needs of the school within the available timescale. Partial reconfiguration would not provide the classroom accommodation the school requires and there was insufficient space within the school to site modular accommodation or extend. A split site was also discounted as the school would not have the staffing and safeguarding arrangement available to accommodate this. None of alternative options explored where able to deliver the additional accommodation with the available timescales.

_________________________________________________________ Report Author and Contact Details: Name: Samantha Horrocks / Ian D’Arcy (BGI) Position: Asset Manager Department: Children’s Services E-mail: [email protected] ________________________________________________________________ Background 5.1 In December 2023 cabinet approved the relocation of Spring Lane School to the New Kershaw Centre (NKC). This was to enable the construction of the new secondary school to proceed, to be sited on land off Spring Lane, Radcliffe.

5.2The relocation of Spring Lane School to New Kershaw Centre (phase 1) was required before the 1st March 2024 in order to provide DfE with vacant possession of the site. This date was achieved with the PRU relocating at the end of February 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PRU Phase 2 Whitefield Centre: Part ADecisions 376 KB DownloadRead as text
PDF
Whitefield Centre PART A: Appendix 1: July 2024: EIADecisions 454 KB Download

At this meeting

Whole meeting
CA.186MinutesOn the agenda CA.187Prestwich funding - Part ANoted CA.188Bury Market & Flexi Hall Levelling Up scheme – enabling and main works contract - Part AApproved CA.189Buy Back & Acquisitions Policy & Procedures 2024 - 2028Agreed CA.190Proposed Major Works Programme for the Councils housing stock 2024/25Approved
CA.191PRU Phase 2 Whitefield Centre - Part AThis decision
CA.192Objections to the proposed disposal of Public Open Space - Land off Manchester Road/Radcliffe Road, BuryAgreed CA.193Six Town Housing Board GovernanceApproved CA.194The Acceptance of the Lowest Tender for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) - Part AApproved CA.195Top Park, Ramsbottom 3G football pitchApproved CA.196Year End/Quarter Four Corporate Plan Performance Report 2023/24 and submission of the productivity planNoted CA.197Star Academy Radcliffe – Capital costs - Part AApproved CA.198Budget Update ReportNoted CA.199Radcliffe School FundingRefused CA.200Implementation of the Children's Services leadership restructureNoted CA.201Exclusion of Press and PublicDecided CA.202The Acceptance of the Lowest Tender for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) - Part BPrivate CA.203Bury Market & Flexi Hall Levelling Up scheme – enabling and main works contract - Part BPrivate CA.204PRU Phase 2 Whitefield Centre - Part BPrivate CA.205Star Academy Radcliffe – Capital costs - Part BPrivate CA.206Prestwich funding - Part BPrivate

Who was there

15 of 20 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, apologies
AQ
Councillor Alan QuinnCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
LR
Lynne RidsdaleOfficer, present
JD
Jacqui DennisOfficer, present
PM
Paul McKevittOfficer, expected

All 20 on the meeting page

On this subject at Bury

Search all
  1. PRU Phase 2 Whitefield Centre - Part AThis decision
  2. PRU-Phase 2-Whitefield Centre-request approval to invite tenders for work in relation to the Pupil Referral Unit - Part AApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies