Millwood Special School-update & request for approval to go to tender

Approved Executive 1 paper

Cabinet approved this item on Wednesday 12 February 2025. Below is the council's own wording, with the papers it was decided on.

ItemCA.304

Resolved

Cabinet: · approved the indicative budget and provisional works programme with an anticipated 12 month build scheme and targeted completion of September 2026. · approved the seeking of competitive tenders for the works, subject to a further report being brought back to a future Cabinet meeting for approval of the tender sum and contract award to the preferred contractor. Reasons for recommendations: · Approval to proceed to tender is required for the Millwood scheme to progress. The scheme will include a new build extension it will also address the roofing remedial works/other defects that are unfinished due to the original contractors going into Administration in September 2024. · Development of additional capacity at Millwood Primary Special School, as set out in the Project Safety Valve agreement between the Council and the Department for Education, is a key element of the specialist place sufficiency strategy. Taken together, the Agreement and strategy set out the business case for the development of new provision and expansion of existing specialist provision to meet increasing demand within Bury and reduce the reliance on placements in Independent Non-Maintained Special Schools (INMSS). The extension scheme at Millwood Primary Special School is a priority within this strategy.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

This report is presented to Cabinet with a full explanation of the latest position, details of the provisional programme including estimated budget costs and is seeking approval to go out to tender for the construction of the new wing extension, roofing remedial and other outstanding defects scheme. This report is issued without finalised figures as these will not be available until after the tenders have been returned. They will then be reviewed internally and validated by independent Quantity Surveyors. Provided that the tender figures can be recommended, an updated report will then be issued for approval. Cabinet approval to proceed to tender is required at the February Cabinet meeting to ensure a start on site to complete the outstanding roofing remedial/other outstanding defects that have been an issue for a considerable length of time. Recommendation(s) Cabinet is requested as follows:

(a) To approve the indicative budget and provisional works programme with an anticipated 12 month build scheme and targeted completion of September 2026. (b) To approve the seeking of competitive tenders for the works, subject to a further report being brought back to a future Cabinet meeting for approval of the tender sum and contract award to the preferred contractor.

Reasons for recommendation(s)

Approval to proceed to tender is required for the Millwood scheme to progress. The scheme will include a new build extension it will also address the roofing remedial works/other defects that are unfinished due to the original contractors going into Administration in September 2024. Development of additional capacity at Millwood Primary Special School, as set out in the Project Safety Valve agreement between the Council and the Department for Education, is a key element of the specialist place sufficiency strategy. Taken together, the Agreement and strategy set out the business case for the development of new provision and expansion of existing specialist provision to meet increasing demand within Bury and reduce the reliance on placements in Independent Non-Maintained Special Schools (INMSS). The extension scheme at Millwood Primary Special School is a priority within this strategy. Alternative options considered and rejected

Do nothing. If we don't proceed with the extension this would mean pupils being sent to out of borough provisions which would be at a large cost to the council We must address the roofing remedial works/other defects as a priority as the original contractors only re-roofed approximately half of the school roofs. The roof is deteriorating and needs to be replaced as soon as practically possible. _________________________________________________________ Report Author and Contact Details: Name: Samantha Horrocks Position: Asset Manager (Education Operations) Department: CYP E-mail: [email protected] ________________________________________________________________ Background

Cabinet have received a suite of reports regarding progress and approvals in relation to this scheme. Below are the dates of the cabinet reports/Urgent Decision Form: -  14 December 2022  12 July 2023  6 September 2023  5 June 2024  26 June 2024 – Urgent Decision Form

At the June Cabinet meeting the following was approved:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Millwood Special School-update & request for approval to go to tenderDecisions 445 KB DownloadRead as text

At this meeting

Whole meeting
CA.300MinutesOn the agenda CA.301Annual HRA Budget 2025/26 & Rent SettingApproved CA.301aThe Council’s 2025/26 Revenue Budget and Medium-Term Financial Strategy (MTFS) for 2026/27 through to 2027/28Approved CA.301bCouncil Tax Support SchemeApproved CA.302Procurement and approval of contract for the HRA Capital Programme 2024/25Approved CA.303Electric Vehicle Charging Infrastructure - Supplier for LEVI and CRSTS FundingApproved
CA.304Millwood Special School-update & request for approval to go to tenderThis decision
CA.305Skyline GMCA residential children's homesNoted CA.306Adult Social Care Provider Fees 25/26Noted CA.307Annual Review of Adult Social Care Fees & Charges 2025-26Approved CA.308Carers Strategy and Commissioning IntentionsApproved CA.309Acquisition of New and Pre-Owned Properties in the BoroughApproved CA.310Northern Gateway Western Access Scheme – Strategic Outline Business Case endorsement and Contract Award Appointment of Construction Contractor and associated Multi-disciplinary consultant teamApproved CA.311Disposal of former Library, Pinfold Lane, WhitefieldApproved CA.312Unit 4 System Upgrade & Transformation ReportApproved CA.313Restructure of the Revenues and Benefits Department –Approval of redundancy costAgreed CA.314Appointments ReportNoted CA.315Minutes Of Association Of Greater Manchester Authorities / Greater Manchester Combined AuthorityOn the agenda CA.317Exclusion of Press and PublicDecided CA.318Millwood Special School-update & request for approval to go to tender - Part BPrivate CA.319Disposal of former Library, Pinfold Lane, Whitefield - Part BPrivate CA.320Unit 4 System Upgrade & Transformation Report - Part BPrivate

Who was there

9 of 20 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
PM
Paul McKevittOfficer, expected

All 20 on the meeting page

On this subject at Bury

Search all
  1. Millwood Special School-update & request for approval to go to tenderThis decision
  2. Millwood Primary Special School - Part AApproved
  3. Millwood Primary Special School-Request for approval to proceed to the PCSA stage with a contractor.Approved
  4. Millwood Primary Special School - Programme Update & request for approval to appoint contractor - Part AApproved
  5. Millwood Primary Special School: Update on Remediation Programme & Expansion ProposalNoted

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies