CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 5 November 2025 at 6.00pm

Northern Gateway (Transport Framework Document; Social Value Strategy; MDC Business Plan and annual Delivery Plan) - PART A

Noted Executive 5 papers

AI summaryBury Cabinet has endorsed the Northern Gateway Transport Framework Document and Social Value Strategy, and noted the draft MDC Business Plan and annual Delivery Plan ahead of the Mayoral Development Corporation being set up in early 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTransport Framework and Social Value Strategy endorsed; MDC plans noted
MoneyNo financial implicationsOfficers confirm none directly arising from this report
What happens nextMDC to be established in early 2026Secretary of State expected to designate the Mayoral Development Corporation
Who it affectsBury and Rochdale communities and businessesCross-border development of the Northern Gateway site

What was decided

Cabinet endorsed the Northern Gateway Transport Framework Document and the Social Value Strategy and Delivery Plan, delegating authority to the Executive Director (Place, Business, Growth and Infrastructure) to make adjustments as the project progresses. Report P5, P6

Cabinet noted the draft MDC 5-year Business Plan and annual Delivery Plan 2026/27 so the Strategic Board can keep work moving at pace until the MDC is set up, and noted the documents will return to Cabinet for final approval after the MDC Board is established. Report P7, P8

Cabinet noted that Rochdale Borough Council intends to take a similar report to its Executive. Report P9

Why

The Transport Framework Document is a best practice planning tool that will support sound decisions on future applications and help secure the investment needed for transport infrastructure. Report P11, P14

A single Social Value Strategy aligns priorities across Bury Council, Rochdale Council, GMCA and TfGM so that benefits reach communities and businesses in both boroughs, rather than depending on which organisation commissions each piece of work. Report P11, P15, P31

Noting the draft MDC Business Plan and Delivery Plan now avoids a gap between the 2024/25 plan ending and the MDC coming into force, which is not expected until early 2026. Report P12, P16, P39

What happens next

Once the Secretary of State designates the MDC in early 2026, the Business Plan and annual Delivery Plan will be approved by the MDC Board, then by Bury and Rochdale Councils and GMCA, before being adopted by the MDC and returning to this Cabinet. Report P3, P8, P40

The Social Value Strategy and Delivery Plan will be reviewed at least annually by a Social Value Delivery Group and every five years by the MDC Board. Report P37

Work continues on a recovery mechanism and legal agreements with developers to secure funding for transport infrastructure delivered up front by the public sector. Report P24

Options considered

  • Rejected: Require each developer to produce a separate Transport Plan for their application area. Risks a non-cohesive approach across the site Report P14
  • Rejected: Continue with social value based on each commissioning organisation's own objectives. Would not deliver consistent outcomes for Bury and would not reflect the agreed cross-border approach Report P15
  • Rejected: Carry on with the 2024/25 Business Plan and wait until the MDC is formally in place. Would leave a gap in direction for the Strategic Board before MDC implementation in early 2026 Report P16

Implications

  • Equalities: The Equality Impact Assessment concludes that impacts are positive and will continue to be assessed as the project progresses. Report P49
  • Climate: Environmental impacts will be assessed and monitored as delivery begins, in line with Council policy and the Northern Gateway Development Framework, including biodiversity net gain. Report P49
  • Risk: If the Transport Framework Document is not endorsed, the Council's ability to support sound planning decisions and to make the case for transport investment would be weakened; mitigation includes ongoing stakeholder engagement and a Technical Appendix. Report P50, P51
  • Legal: There are no procurement or legal implications at this stage; legal and procurement will be engaged when advice is needed. Report P53
  • Financial: There are no financial implications directly arising from this report. Report P54

Who and where

  • Communities of Bury and Rochdale within and around the Northern Gateway site Report P20, P31, P34
  • Existing and new local businesses on the Northern Gateway site Report P46, P48
  • Developers bringing forward planning applications across the site Report P14, P22
  • Partner organisations: Rochdale Council, GMCA and Transport for Greater Manchester Report P2, P30, P31
  • Future residents and workers on the Northern Gateway site Report P26, P44

Timeline

  • September 2024: Cabinet endorsed interim governance arrangements and a Business Plan for Northern Gateway Report P3, P60
  • 5th March 2025: Cabinet approved the Northern Gateway Development Framework Supplementary Planning Document Report P1, P19, P61
  • July 2025: Cabinet supported the designation of the Atom Valley Northern Gateway Mayoral Development Corporation Report P2, P63
  • Early 2026: Secretary of State expected to formally designate the Mayoral Development Corporation Report P3, P39
  • 2026 to 2031: Period covered by the draft 5-year MDC Business Plan Report P41
  • 2026/27: First annual Delivery Plan to operate in the run up to MDC implementation Report P39, P58
  • 2040: Greater Manchester ambition for zero net increase in car traffic, supported by the Transport Framework Report P26
  • 20-year period: Expected timescale for full delivery of the Northern Gateway and its transport infrastructure Report P28

Plain English for the jargon

  • SPD: Supplementary Planning Document
  • PfE: Places for Everyone Plan, the joint Greater Manchester development plan
  • TFD: Transport Framework Document for the Northern Gateway
  • MDC: Mayoral Development Corporation, a special purpose delivery body for the Northern Gateway
  • GMCA: Greater Manchester Combined Authority
  • TfGM: Transport for Greater Manchester
  • SRN: Strategic Road Network
  • SoS: Secretary of State
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.70

Resolved

Cabinet: 1. Endorsed the Northern Gateway Transport Framework Document and delegated authority to the Executive Director (Place – Business, Growth and Infrastructure) to make adjustments to the document as the Northern Gateway project progresses; 2. Endorsed the Northern Gateway Social Value Strategy and Delivery Plan and delegated authority to the Executive Director (Place – Business, Growth and Infrastructure) to make adjustments to the documents as the Northern Gateway project progresses; 3. Noted the implementation of the MDC Business Plan and annual Delivery Plan in advance of MDC implementation to enable the work of the Northern Gateway Strategic Board to move forward at pace and delegated authority to the Executive Director (Place – Business, Growth and Infrastructure) to make adjustments to it as the project progresses; 4. Noted the MDC Business Plan and annual Delivery Plan will be brought back to Cabinet for final approval once the MDC Board has been established and has formally approved the documents; and 5. Noted the Rochdale Borough Council’s intention to take a similar report to ... view the full minutes text for item CA.70
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1. On 5th March 2025 the Northern Gateway Development Framework Supplementary Planning Document (SPD) was approved by Cabinet and provides a material consideration for and framework against which future planning applications on the Northern Gateway site will be considered. To further support and inform decision-making through the planning process for future applications, a Northern Gateway Transport Framework Document (TFD) (Appendix A) has been developed to set out a transport vision and plan for delivering the transport infrastructure and services needed to unlock the full potential of the Northern Gateway. This report outlines the detail of the TFD and seeks Cabinet endorsement of the document.

2. Further to the resolution in July 2025 by Cabinet to support the designation of the ‘Atom Valley Northern Gateway’ Mayoral Development Corporation (MDC), and ongoing work to develop the MDC governance arrangements, a Social Value Strategy (Appendix B) and accompanying Social Value Delivery Plan (Appendix C) have been developed. The purpose of these documents is to align the social value priorities of Bury Council, Rochdale Council, Greater Manchester Combined Authority (GMCA) and Transport for Greater Manchester (TfGM) to maximise the social value potential and ensure tangible and quantifiable outcomes for local communities and businesses irrespective of the organisation commissioning work on behalf of Northern Gateway. This report outlines the detail of Northern Gateway Social Value Strategy and accompanying Delivery Plan and seeks Cabinet approval of both documents.

3. Following adoption of the Places for Everyone (PfE) joint development plan, and in recognition of a need for more formal working arrangements with key partners in the absence of a formal delivery mechanism for the Northern Gateway at that time, Cabinet endorsed the implementation of interim governance arrangements for Northern Gateway in September 2024. This included approval of a Business Plan which has successfully directed work for the last 12 months. In light of the imminent establishment of the Northern Gateway MDC by the Secretary of Stage, a 5-year MDC Business Plan (Appendix D – Part B) and accompanying annual Delivery Plan (Appendix E – Part B) have been developed by the Northern Gateway Strategic Board and Cabinet are requested to note the documents, which are currently in draft form. As the MDC is anticipated to be implemented by the Secretary of State in early 2026, the draft Business Plan and annual Delivery Plan will allow the work of the Northern Gateway Strategic Board to move forward at pace until the point of MDC implementation. Upon implementation of the MDC, as per the requirements of draft MDC Constitution, the Business Plan and annual Delivery Plans will be approved by the MDC Board, then approved by both Bury and Rochdale Councils and GMCA, then subsequently adopted by the MDC.

Recommendation(s) 1. It is recommended that Cabinet:

i. Endorse the Northern Gateway Transport Framework Document and delegate authority to the Executive Director (Place – Business, Growth and Infrastructure) to make adjustments to the document as the Northern Gateway project progresses.

ii. Endorse the Northern Gateway Social Value Strategy and Delivery Plan and delegate authority to the Executive Director (Place – Business, Growth and Infrastructure) to make adjustments to the documents as the Northern Gateway project progresses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Northern Gateway Transport FrameworkAppendix A 8.2 MB Download
PDF
Northern Gateway Social Value StrategyAppendix B 1.2 MB Download
PDF
Northern Gateway Social Value Delivery PlanAppendix C 869 KB Download
PDF
Northern Gateway (Transport Framework Document; Social Value Strategy; MDC Business Plan and annual Delivery Plan): PART ADecisions 400 KB DownloadRead as text
PDF
Northern Gateway Transport Framework EqIADecisions 197 KB Download

At this meeting

Whole meeting

Who was there

9 of 19 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
SA
Councillor Shahbaz ArifCommittee Member, in attendance
RB
Councillor Russell BernsteinCommittee Member, in attendance
MS
Councillor Mike SmithCommittee Member, in attendance

All 19 on the meeting page

On this subject at Bury

Search all
  1. Northern Gateway (Transport Framework Document; Social Value Strategy; MDC Business Plan and annual Delivery Plan) - PART AThis decision
  2. Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Approved
  3. Northern Gateway Mayoral Development Corporation UpdateNoted
  4. Northern Gateway, Western Access scheme: Approval of Main Construction Contract to undertake Pre-construction and Construction Stage activitiesDecided
  5. Northern Gateway MDCNoted
  6. Northern Gateway Development Framework Supplementary Planning DocumentNoted

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies