Bury Metropolitan Borough Council
Cabinet, Wednesday 9 September 2026 at 6.00pm

Northern Gateway Mayoral Development Corporation Update

Noted Executive 3 papers

AI summaryBury Cabinet approves Northern Gateway Mayoral Development Corporation operational arrangements and accepts up to £300,000 a year from the GMCA for three years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedDelegated contract work to senior officers
MoneyUp to £300,000 per yearGMCA grant for MDC, 2026/27 to 2028/29
What happens nextOfficers to finalise contractsExecutive Director for Place and Legal lead
Who it affectsNot stated

What was decided

Cabinet noted and approved the MDC operational arrangements, costs and cost sharing approach set out in Appendix 2.

Cabinet noted and approved the GMCA offer of additional grant funding of up to £300,000 per year to part-fund the MDC for three years from 2026/27 to 2028/29.

Cabinet authorised and delegated to the Executive Director for Place and the Director of Legal and Democratic Services the negotiation, preparation and completion of the necessary contracts for the MDC and the GMCA grant.

Why

Following the July 2025 Cabinet approval to create the Atom Valley Northern Gateway MDC, the report sets out how it will be hosted in Rochdale, its running costs, and how those costs will be shared and funded by MDC partners. Report P3, P11

The MDC is intended to progress delivery of the Northern Gateway sites, providing new homes, jobs, infrastructure and economic growth locally. Report P12

An equality analysis of the underlying Places for Everyone Plan found a positive overall effect on equality, with positive effects identified for disability and age groups. Report P16, P19, P37

What happens next

The Executive Director for Place and the Director of Legal and Democratic Services will negotiate and complete the contractual arrangements for the MDC and the GMCA grant.

The PfE Joint Plan will be continually monitored to determine the effectiveness of its policies, including the Northern Gateway allocations JPA1.1 and JPA1.2. Report P42, P3

The money

  • up to £300,000 per year GMCA additional grant funding to part-fund the MDC for three years from 2026/27 to 2028/29

Implications

  • Equalities: Disability and age groups are identified as receiving a positive effect from the Places for Everyone Plan underpinning the MDC; the overall effect on equality is judged positive. Report P16, P19, P37
  • Financial: GMCA additional grant of up to £300,000 per year for three years will part-fund the MDC; the decision also references an interest free loan offer from the GMCA, but the amount and terms are not visible in the supplied papers.
  • Legal: Authority to negotiate and complete contracts is delegated to the Executive Director for Place and the Director of Legal and Democratic Services.
  • Other: The Places for Everyone Plan is now part of Bury's statutory development plan and its policies will be used in determining planning applications. Report P40

Who and where

  • Local residents across the nine Greater Manchester districts covered by Places for Everyone (Bolton, Bury, Manchester, Oldham, Rochdale, Salford, Tameside, Trafford and Wigan) Report P3, P9, P13
  • Developers, landowners, businesses, planning and development consultants working on the Northern Gateway sites Report P13
  • Statutory consultees, infrastructure providers, interest groups and representative bodies Report P13

Timeline

  • March 2025: Cabinet approved the MDC as the preferred delivery vehicle for the Northern Gateway and agreed the MDC boundary. Report P11
  • July 2025: Cabinet approved the creation of the Atom Valley Northern Gateway MDC. Report P3
  • 2026/27 to 2028/29: Three year period covered by the GMCA additional grant of up to £300,000 per year.
  • 19 June 2026: Date the Equality Analysis form was completed. Report P4, P7

Plain English for the jargon

  • MDC: Mayoral Development Corporation, a body set up to deliver strategic development sites.
  • Northern Gateway: Strategic allocation within the Places for Everyone Plan, covering sites JPA1.1 and JPA1.2.
  • PfE: Places for Everyone Plan, a joint development plan for nine Greater Manchester authorities to 2039.
  • GMCA: Greater Manchester Combined Authority.
  • EqIA: Equality Impact Assessment, a process to show due regard to the Public Sector Equality Duty.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.54

Resolved

Decision(s) Cabinet: · Noted and approved the MDC operational arrangements, costs, and cost sharing approach as set out at Appendix 2. · Authorised and delegated to the Executive Director for Place and Director of Legal and Democratic Services the negotiation, preparation, and completion of the necessary contractual arrangements to provide for the MDC operational arrangements, costs, and cost sharing as set out at Appendix 2. · Noted and approved the GMCA’s offer to contribute additional grant funding of up to £300,000 per year to in-part fund the MDC for a period of three years from 2026/27 to 2028/29. · Authorised and delegated to the Executive Director for Place and Director of Legal and Democratic Services the negotiation, preparation, and completion of the necessary contract(s) in relation to the GMCA’s additional grant funding to provide for the MDC (referred to at recommendation 4.3 above). 4 · Noted the GMCA’s offer of an interest free loan of ... view the full minutes text for item CA.54
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Equality Analysis Form The following questions will document the effect of your service or proposed policy, procedure, working practice, strategy or decision (hereafter referred to as ‘policy’) on equality, and demonstrate that you have paid due regard to the Public Sector Equality Duty. 1. RESPONSIBILITY

Department Place

Service Strategic Planning and Infrastructure Following adoption of Places for Everyone Plan: A Joint Proposed policy Development Plan Document for nine Greater Manchester Local Authorities (Bolton, Bury, Manchester, Oldham, Rochdale, Salford, Tameside, Trafford and Wigan) 2022- 2039 (The Places for Everyone Plan), work continues to progress on the Northern Gateway (PfE; JPA1.1 and JPA1.2). Following approval of the creation of the Atom Valley Northern Gateway MDC by Cabinet in July 2025 and a request to present a further report outlining the operational arrangements for hosting the MDC in Rochdale, its associated operating costs and to confirm how these costs will be shared and funded between the MDC partners, this report sets out those arrangements.

Date 19 June 2026

Officer responsible Name Hollie Good for the ‘policy’ and for completing the Post Title Major Project Manager: Strategic equality analysis Planning and Infrastructure

Contact Number 0161 253 5282

Signature H.Good Date 19 June 2026

2. AIMS

What is the purpose ‘Places for Everyone’ (PfE) sets out a plan for homes, of the jobs, and the environment across nine of the ten Greater policy/service and Manchester districts (excluding Stockport). It sets out what is it intended where we will build the new homes we need, where our to achieve? businesses will locate to sustain and create jobs for our people, what infrastructure is needed to support the development and to protect and enhance our towns,

-1- cities and landscapes. It is proposed that the Plan will cover a timeframe up to 2039. Whilst one of the key purposes of PfE is to make provision for the homes and jobs needed across the plan area in a co-ordinated and managed way, it is also about establishing a framework for reducing inequalities, improving the lives of our residents and transforming Greater Manchester into a world-leading city-region. Northern Gateway (JPA1.1 and JPA1.2) is a strategic allocation within PfE.

In March 2025, Cabinet approved the creation of an MDC as the preferred delivery vehicle for the Northern Gateway along with the boundary within which the MDC will operate. A public consultation was subsequently undertaken by the Mayor, supported by Bury and Rochdale Councils and the GMCA.

The MDC will progress delivery of the Northern Gateway sites, providing a significant boost to employment opportunities, new homes, infrastructure and economic growth locally.

Who are the main The main stakeholders involved in PfE are local residents, stakeholders? developers, landowners, businesses, planning and development consultants, statutory consultees, infrastructure providers, interest groups and representative bodies.

3. ESTABLISHING RELEVANCE TO EQUALITY 3a. Using the drop down lists below, please advise whether the policy/service has either a positive or negative effect on any groups of people with protected equality characteristics. If you answer yes to any question, please also explain why and how that group of people will be affected.

Protected Positive Negative Explanation equality effect effect characteristic (Yes/No) (Yes/No)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2b. Appendix 1: EqIA: Part A: as 06.08.26 (1)Decisions 120 KB DownloadRead as text
PDF
2c. Appendix 2: MDC Operational Arrangements and Costs: Part A (1)Decisions 303 KB Download
PDF
Northern Gateway Mayoral Development Corporation UpdateDecisions 217 KB Download

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, apologies due to council business
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Northern Gateway Mayoral Development Corporation UpdateThis decision
  2. Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Approved
  3. Northern Gateway, Western Access scheme: Approval of Main Construction Contract to undertake Pre-construction and Construction Stage activitiesDecided
  4. Northern Gateway (Transport Framework Document; Social Value Strategy; MDC Business Plan and annual Delivery Plan) - PART ANoted
  5. Northern Gateway MDCNoted
  6. Northern Gateway Development Framework Supplementary Planning DocumentNoted

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open