Northern Gateway, Western Access scheme: Approval of Main Construction Contract to undertake Pre-construction and Construction Stage activities
DecidedExecutive2 papers
AI summaryBury Cabinet delegates final approval of a £2,830,403 contract sum and main construction contract for the Northern Gateway Western Access scheme to senior officers.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedFinal contract sign-off handed to director
Money£2,830,403Provisional maximum contract sum
What happens nextNot stated
Who it affectsNot stated
What was decided
Cabinet delegated final acceptance of a contract sum, up to a provisional maximum of £2,830,403, covering finalisation of the Outline Business Case stage work packages (Stage 2b) for the Northern Gateway Western Access scheme.
Cabinet delegated finalisation of the main pre-construction and construction contract, an NEC4 ECC Option C X22 contract, including appropriate break clauses.
The money
£2,830,403 Provisional maximum final contract sum for Outline Business Case Stage 2b work packages
Implications
Legal: Final contractual decisions are delegated to the Director of Law and Democratic Services, in consultation with the Executive Director of Place, the Director of Finance, the Council Leader and the Cabinet Member for Strategic Growth.
Financial: Acceptance is capped at a provisional maximum of £2,830,403.
Risk: The main contract will include appropriate break clauses to allow exit.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.84
Resolved
Cabinet: 1. Delegated final acceptance of a final contract sum, up to a provisional maximum of £2,830,403 covering the finalisation of the Outline Business Case stage work packages (Stage 2b), to the Director of Law and Democratic Services in consultation with the Executive Director of Place and Director of Finance and the Council Leader and Cabinet Member for Strategic Growth; and 2. Delegated finalisation of the Main Pre-Construction and Construction Contract (NEC4 ECC Option C X22 contract) including appropriate break clauses, to the Director of Law and Democratic Services in consultation with the Executive Director of Place and the Council Leader and Cabinet Member for Strategic Growth.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Equality Analysis Form The following questions will document the effect of your service or proposed policy, procedure, working practice, strategy or decision (hereafter referred to as ‘policy’) on equality, and demonstrate that you have paid due regard to the Public Sector Equality Duty. 1. RESPONSIBILITY
Department Business Growth and Infrastructure
Service Strategic Planning and Infrastructure
Proposed policy Adoption of Places for Everyone Plan: A Joint Development Plan Document for nine Greater Manchester Local Authorities (Bolton, Bury, Manchester, Oldham, Rochdale, Salford, Tameside, Trafford and Wigan) 2022-2039 (The Places for Everyone Plan).
Date 20 March 2024
Officer responsible Name David Wiggins for the ‘policy’ and for completing the Post Title Service Manager: Strategic Planning equality analysis and Infrastructure
Contact Number 0161 253 5282
Signature D. Wiggins Date 4 March 2024
2. AIMS
What is the purpose ‘Places for Everyone’ (PfE) sets out a plan for homes, jobs, of the and the environment across nine of the ten Greater policy/service and Manchester districts (excluding Stockport). It sets out what is it intended where we will build the new homes we need, where our to achieve? businesses will locate to sustain and create jobs for our people, what infrastructure is needed to support the development and to protect and enhance our towns, cities and landscapes. It is proposed that the Plan will cover a timeframe up to 2039. Whilst one of the key purposes of PfE is to make provision for the homes and jobs needed across the plan area in a co-ordinated and managed way, it is also about establishing a framework for reducing inequalities, improving the lives of our residents and transforming Greater Manchester into a world-leading city-region.
-1- Who are the main The main stakeholders which are involved in PfE are local stakeholders? residents, developers, landowners, businesses, planning and development consultants, statutory consultees, infrastructure providers, interest groups and representative bodies.
3. ESTABLISHING RELEVANCE TO EQUALITY 3a. Using the drop down lists below, please advise whether the policy/service has either a positive or negative effect on any groups of people with protected equality characteristics. If you answer yes to any question, please also explain why and how that group of people will be affected.
Race No No PfE has been subject to an Integrated Appraisal and part of this has involved and Equality Impact Assessment which has considered in its scope, the likely effects on discriminatory practices; the potential to alter the opportunities of certain groups of people; and/or effect on relationships between different groups of people, including race.
Disability Yes No PfE includes policies that seek to ensure that all neighbourhoods are designed to enable residents to live healthier, happier and more fulfilling lives, with the barriers to doing so minimised as far as possible. This must include recognising and responding to the difficulties that people may face due to age, disability, illness or financial circumstances. The Plan has also been subject to an Integrated Appraisal and part of this has involved and Equality Impact Assessment which has considered in its scope, the likely effects on discriminatory practices; the potential to alter the opportunities of certain groups of people; and/or effect on relationships between different groups of people, including disability.
Gender No No
-2- Gender No No PfE has been subject to an Integrated reassignment Appraisal and part of this has involved and Equality Impact Assessment which has considered in its scope, the likely effects on discriminatory practices; the potential to alter the opportunities of certain groups of people; and/or effect on relationships between different groups of people, including gender reassignment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Northern Gateway, Western Access scheme: Approval of Main Construction Contract to undertake Pre-construction and Construction Stage activitiesDecisions
CA.84Northern Gateway, Western Access scheme: Approval of Main Construction Contract to undertake Pre-construction and Construction Stage activitiesThis decision
Northern Gateway, Western Access scheme: Approval of Main Construction Contract to undertake Pre-construction and Construction Stage activitiesThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.