Bury Metropolitan Borough Council
Cabinet, Wednesday 3 December 2025 at 6.00pm

AB Electrical EICR and LD2 Services Contract Award Decision

Approved Executive 1 paper

AI summaryBury Council awards a 3 year contract to AB Electrical and Building Ltd for electrical safety and fire detection work in its housing stock, with two possible 12 month extensions and an estimated total value of £2,500,000.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo AB Electrical and Building Ltd via Procure Plus framework
Money£2,500,000 over 5 years£500,000 per year, split £350,000 EICR and £150,000 LD2
What happens nextContract starts3 years initial, with two 12 month extension options
Who it affectsCouncil housing tenantsOver 7,500 properties including sheltered and extra care schemes

What was decided

Cabinet approved awarding a contract to AB Electrical and Building Ltd, ranked first on the Procure Plus framework, for an initial 3 year term with the option to extend for two further 12 month periods. Report P9

AB Electrical was found to be the most economically advantageous contractor after clarification and moderation of quality and price scores. Report P6

Why

The contractor is already carrying out the work and has helped Bury Council significantly reduce the number of outstanding EICRs over the last 18 months. Report P5

The services are a legal requirement under the Electrical Safety Standards in the Private and Social Rented Sectors (England) Regulations 2020/2025, the Electricity at Work Regulations 1989, and the HHSRS Electric Safety requirements of Awaab's Law from 2026. Report P4, P14

Using the Procure Plus framework was preferred over an open tender because it is quicker, ensures tenderers meet capability and compliance requirements, and allows the tender to be tailored to the council's needs. Report P12

What happens next

Legal and procurement advice will be provided on the contractual arrangements, with JCT contracts prepared by the Procure Plus framework. Report P21

The contract award is in line with the approved capital programme. Report P22

The money

  • £500,000 per year Estimated annual value of the EICR and LD2 contract Report P7
  • £2,500,000 in total Estimated total value over the 5 year contract life Report P7
  • £350,000 Annual allocation for EICR works Report P7
  • £150,000 Annual allocation for LD2 works Report P7

Options considered

  • Chosen: Award the contract to AB Electrical and Building Ltd via the Procure Plus framework. Ranked first overall for quality and price combined, already successfully carrying out the work, and the framework ensures compliance with capability and expertise requirements Report P5, P6, P9, P12
  • Rejected: Do nothing. The services are a legal requirement and the council would quickly become non-compliant without a contract Report P10
  • Rejected: Deliver in house. The council lacks the capacity to handle major contracts across over 7,500 properties, and the new Building Safety Team is designed to be contractor led and managed Report P11
  • Rejected: Open tender. Would involve a significantly extended procurement process in both time and cost compared to using the framework Report P12

Implications

  • Legal: The contract delivers landlord statutory compliance services required under the Electrical Safety Standards regulations and Awaab's Law from 2026. Failing to award would hinder the council in fulfilling its statutory duties. Report P4, P14, P21
  • Financial: The contract award is in line with the approved capital programme. Report P22
  • Equalities: The award will not have any adverse impact on people from equality groups as it is not a change of policy. Report P18
  • Climate: The programme has an indirect positive environmental impact by identifying faults that prevent energy waste and mitigate hazards, though it generates some electronic waste from replaced equipment and test materials. Report P19
  • Risk: Failing to award the contract would hinder the council in meeting its obligations under the Electricity at Work Regulations 1989 and the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020. Report P21

Who and where

  • Council tenants in over 7,500 housing properties, including sheltered and extra care schemes and communal blocks Report P11

Timeline

  • 03 December 2025: Cabinet decision to award the contract Report P2
  • 3 years initial term: Contract period commencing after award Report P9
  • Two further 12 month periods: Optional extensions available Report P9
  • 5 year contract life: Total potential duration if both extensions are exercised Report P7
  • 2026: Awaab's Law legislation comes into force, adding further duties related to HHSRS Electric Safety requirements Report P14

Plain English for the jargon

  • EICR: Electrical Installation Condition Report: inspection and testing of electrical installations required at least every five years
  • LD2: A fire detection system standard covering circulation areas forming escape routes and specified high fire risk rooms or areas, governed by BS 5839-6:2019+A1:2020
  • Procure Plus: A procurement framework specialising in social housing investment works
  • HHSRS: Housing Health and Safety Rating System, used to assess housing conditions
  • Awaab's Law: Legislation requiring landlords to fix health and safety hazards in social housing within set timeframes
  • JCT: Joint Contracts Tribunal, a standard form of building contract used in the UK
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.92

Resolved

Cabinet approved the award of a contract to the contractor placed number 1 on the Procure Plus Framework, AB Electrical and Building Ltd for the initial period of 3 years with the option to extend for a further two periods of 12 months.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Report to: Cabinet Date: 03 December 2025 Subject: AB Electrical EICR and LD2 Services Contract Award Decision Report of Cabinet Member for Housing Services

Summary 1. The purpose of this report is to seek formal approval of a contract award, through the Procure Plus framework, for the completion of Electrical Installation Condition Reports (EICR) and the installation of fire detectors to a Category LD2 system standard required in all domestic property circulation areas that form part of the escape routes and in all specified rooms or areas that present a high fire risk to occupants.

2. The Electrical Safety Standards in the Private and Social Rented Sectors (England) Regulations 2020/2025 mandate that landlords in England must have the electrical installations in their rental properties inspected and tested at least every five years. Installation work for a Category LD2 fire alarm system in domestic premises is primarily governed by the recommendations of British Standard BS 5839- 6:2019+A1:2020 and the relevant Building Regulations for the specific region of the UK (e.g., Approved Document B for England and Wales).

3. The contractor who is in first place on the Procure Plus framework is AB Electrical who are currently and successfully carrying out these services within our housing stock. They have worked with Bury Council to significantly reduce the number of outstanding EICRs over the last 18 months.

4. Following full clarification process on the commercial submissions and moderation of the quality scores, AB Electrical are ranked 1st overall for quality and price combined on the Procure Plus Framework, therefore are deemed to be the most economically advantageous contractor for Bury Council to appoint for these works.

5. The estimated value of the contract is £500,000 per year and £2,500,000 in total over the 5 year life of the contract. This is split £350,000 (EICR) and £150,000 (LD2) per year.

Recommendation(s)

Cabinet is asked to: 6. Approve the award of a contract to the contractor placed number 1 on the Procure Plus Framework, AB Electrical and Building Ltd for the initial period of 3 years with the option to extend for a further two periods of 12 months. Reasons for recommendation(s)

7. The contract delivers Landlord Statutory Compliance Services on behalf of the Council. Alternative options considered and rejected 8. Do nothing: There is no current contract in place for these services which are a legal requirement under The Electrical Safety Standards in the Private and Social Rented Sectors (England) Regulations 2020/2025 so the Council would quickly become non- compliant

Deliver in house: These are major contract’s carried out in our housing stock of over 7500 properties, sheltered and extra care schemes and communal blocks and we lack the capacity in house. The new structure of the Building Safety Team is designed to be contractor led and managed by the Building Safety Team.

Open tender: This option was considered and is possible. However, this would involve a significantly extended procurement process in both time and cost. The use of the Procure Plus framework which specialises in social housing investment works adds benefits in ensuring all tenderers meet capability, expertise and compliance requirements and the mini- competition allows the tender to be tailored to the Councils specific requirements. Using the framework offers clear benefits over the open tender route. Similarly exercising a 12 months contract extension on the same rates as the original contract allow us to bring forward investment quick without further drawn-out tendering processes.

Report Author and Contact Details: Name: Ben Tunnicliffe Position: Head of Building Safety Department: Housing Services E-mail: [email protected] ________________________________________________________________ Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AB Electrical EICR and LD2 Services Contract Award DecisionDecisions 385 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, apologies
RG
Councillor Richard GoldCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
SA
Councillor Shahbaz ArifCommittee Member, apologies
RB
Councillor Russell BernsteinCommittee Member, in attendance
MS
Councillor Mike SmithCommittee Member, in attendance

All 22 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open